How a British building with spare power becomes a paid AI request: who does each job between the two, how they make money, who stands behind whom, and where we sit.
Draft of 31 October 2026 · For discussion · Market study, no returns · Figures as published, sterling at October 2026 rates · Download the PDF to read offline
How a British building with spare power becomes a paid AI request, who does each job between the two, how they make money, and where we sit. Chapter zero maps the chain and sets out how the rest will be researched.
For discussion. This is a market study, not a model. It carries no returns. Rent, where it appears, is £750k per MW of firm supply a year. Every figure is labelled by source and, where a third party quoted dollars or euros, converted to sterling at October 2026 rates. Nothing here has been shared outside the partners.
Firm power at a substation becomes a powered site, a fitted hall, a rack of compute, a sold contract, a model behind an API, and finally an answer on someone's screen.
Who finances each layer and at what cost, and which contract hands the asset to the next layer. Both run the full length of the chain and get their own chapters.
We own the building and the connection and lease it to a layer 2 or layer 3 operator. We do not own the compute. Layers 3 to 6 matter to us in so far as they decide whether our tenant is still paying rent in year eight.
Hyperscale campuses run at 50 MW and up and wait years for grid. Sovereign and edge inference runs at 5 to 15 MW a site and wants power this decade. That band is where our buildings fit.
Read left to right. Each box is a layer with its own owners and its own economics. The label on each arrow is the contract that moves the asset to the next layer. The two bands beneath are the money and paper threads, which run the length of the chain.
| # | Layer | Who holds it in the UK today | Where the money comes from | What goes wrong |
|---|---|---|---|---|
| 0 | Grid | UK Power Networks and the other DNOs; NESO for transmission | Regulated revenue; connection charges paid by the applicant | Reinforcement cost and queue time; capacity oversubscribed; agreed supply lost when an occupier leaves |
| 1 | Powered site | Yeats Edge; Segro-type developers; Telereal's exchange estate; owners of ex-industrial supply | Property equity and debt sized on rent | Power priced into the purchase; tenant default; fallback use lost |
| 2 | Fitted hall | Kao, Ark, Pulsant, nLighten, Latos, Datum, Yondr, the London campus operators | Infrastructure equity, project debt, green bonds | Density outruns cooling; fit-out stranded by a tenant's exit |
| 3 | Compute | Nscale, Civo, Nebius, CoreWeave, Ori, the hyperscalers' own clusters | Venture equity, GPU-backed debt, vendor finance, Nvidia itself | GPUs lose value in three to five years; a lab walks away; power never arrives |
| 4 | Capacity sale | Microsoft, Google, OpenAI, Anthropic, Meta as buyers; SF Compute and Nvidia Lepton as markets; BT and Crown Hosting as channels | Hyperscaler balance sheets; take-or-pay contracts; marketplace fees | Spot GPU prices fall; off-taker renegotiates; concentration in one buyer |
| 5 | Model and app | Labs and API platforms; UK AI firms; enterprises; the public sector via G-Cloud | Venture, subscriptions, enterprise contracts, public procurement | Inference gets cheaper per token faster than demand grows |
| 6 | User | People and firms in the UK who need an answer in under a few hundred milliseconds | Their own spend | They do not care where the compute is, unless it is slow or abroad |
Holders named are examples from public sources, to be verified in the chapters. The highlighted row is our position.
Each chapter answers the same eight questions in the same order, so layers can be compared like for like. The answers to the last question are collected in chapter 9.
| # | Question | What it produces |
|---|---|---|
| 1 | What is it? | The asset and the unit it is sold in |
| 2 | Who are the UK players? | A named list, tiered |
| 3 | What are they? | Ownership, scale, funding, age |
| 4 | What do they do? | The service and the customer |
| 5 | Who runs them? | Background of the leadership, by role not name |
| 6 | How do they make money? | Pricing, margins, capital intensity, where debt sits |
| 7 | Why now? | The force pushing them: power scarcity, sovereignty, latency, cheap or dear capital |
| 8 | What does it mean for us? | One paragraph: a tenant, a risk, a term to ask for, or a thing to avoid |
| Ch | Title | Brief | The visual |
|---|---|---|---|
| 0 | The map | This document | The chain infographic above |
| 1 | Grid | How UK distribution capacity is allocated, who the DNOs are, what the queue and the 2030 forecasts mean, Ofgem's thresholds, where power is actually spare | GB map of spare capacity at 5 and 10 MW, from power.yeats.com |
| 2 | Powered site | Who else owns buildings with power: Segro, Telereal, industrial landlords, the US miner precedent; what a powered shell lets for; how our position compares | Rent stack per MW across layers 1 to 3 |
| 3 | Fitted hall | The UK colocation and regional edge operators; what a fit-out costs and who pays; what £ per kW per month buys | Anatomy of one MW of hall: landlord scope against lessee scope |
| 4 | Compute | The neoclouds and sovereign providers in Britain; how they are funded; what a GPU earns and loses; who has already failed | Life of a GPU: cost, earnings and value over five years |
| 5 | Capacity sale | Hyperscaler off-take, backstops, marketplaces, public-sector channels; what sits between a GPU owner and a buyer | Who pays whom: the money flow behind one 10 MW lease |
| 6 | Model, app and user | UK inference demand: who runs models here, why latency and sovereignty pull compute onshore, and how far from London it needs to be | Latency rings around UK population from candidate sites |
| 7 | Money | Finance for the full chain in one place: cost of capital by layer, where debt is sized, what a lender will and will not lend on | Capital stack by layer |
| 8 | Paper | The contracts: connection offer, lease and its clauses, backstop, power pass-through, planning, sovereignty rules | One lease on one page, clause by clause |
| 9 | What it means for us | Where we sit, who we lease to, what we ask for, what we never do; the target list, revised | The ask list, and the chain with our position marked |
| A | Cards | One card per player: deep cards for eight, short cards for the rest | A card template, repeated |
UK only, and spread across the chain rather than clustered in one layer. The deep eight are the firms whose behaviour sets the terms we will be offered. The cards cover everyone else a tenant, lender or broker might mention. The seed list is the operator and broker target list of 31 October; this study will revise it.
| Layer | Firm | Why deep |
|---|---|---|
| 0 | UK Power Networks | Our DNO. Its connection process, queue and forecasts decide what a Kent or London site can hold |
| 1 | Segro | The UK's largest industrial landlord now building powered shells to order; the closest thing to a competitor in our position |
| 2 | Kao Data | Landlord of choice for neoclouds in Britain; hosts Nebius, Ori and Civo; shows what fitted halls lease for and on what terms |
| 2 | Pulsant | The regional edge consolidator; buys sites of our size with fresh debt |
| 3 | Nscale | The UK neocloud: BT, Microsoft and OpenAI relationships, grid-delayed at Loughton, IPO filed. Its delays show what a site with confirmed power is worth |
| 3 | Civo | Forty edge sites planned at about 8 MW each; the clearest statement of UK inference demand at our size |
| 3 | Nebius | The international neocloud scaling fastest in Britain; shows how a well-funded operator chooses between a shell and a hall |
| 4 | Microsoft UK | The buyer behind Nscale and Nebius; its UK commitments and its exits set the credit behind our tenants |
| Layer | Firms |
|---|---|
| 0 | NESO; National Grid Electricity Distribution; SSEN; Northern Powergrid; Electricity North West; SP Energy Networks; Ofgem (as rule-setter) |
| 1 | Telereal Trillium and Openreach; BT Group as counterparty; the US miner precedent (TeraWulf, Cipher, Applied Digital) as a structure, not a UK player |
| 2 | Ark and Crown Hosting; Latos; nLighten and Proximity; Datum; Yondr; Green Mountain; Equinix, Digital Realty, Global Switch and Telehouse |
| 3 | CoreWeave UK; Ori; DataVita; Fluidstack (as structure); Lambda and Sesterce (watch); the hyperscalers' own UK regions |
| 4 | Google UK; OpenAI and Stargate UK; Anthropic; Meta; SF Compute; Nvidia DGX Cloud Lepton; Crown Commercial Service and G-Cloud |
| 5 and 6 | UK model and app firms that buy inference (to be identified in chapter 6); API platforms such as Together, Baseten and Fireworks; Cloudflare and Akamai at the network edge; Isambard-AI and the UK sovereign programme |
| Money | GPU and data-centre lenders active in the UK (to be identified in chapter 7); the green ABS and infrastructure funds behind the operators |
| Intermediaries | CBRE, JLL, Cushman & Wakefield, Knight Frank, Savills, Avison Young; DC Byte, datacenterHawk, Structure Research |
Layer 0. Where firm power comes from, who allocates it, why the queue broke in 2025, what the regulator and the government are doing about it, and where in Britain the capacity actually is. Chapter 1 of From power to answer.
Basis. Market study, no returns. Capacity figures are the network operators' own published headroom, marked Indicated unless a connection agreement is cited. Dollar figures converted at October 2026 rates. Sources in section 1.9.
Six private groups run the fourteen distribution licences. They connect anything up to tens of MW; above that NESO and the transmission owners are involved.
Demand applications rose from 41 GW to 125 GW in seven months to June 2025, 460% at transmission alone. About 140 data centres, c.50 GW, sit in the transmission queue; only 11 to 13 GW of demand can connect before 2030.
From 1 June 2026 any demand connection of 5 MVA or more must prove land, authority and a programme. Ofgem proposes a commitment fee for data centres above 40 MW, and government will prioritise named strategic projects.
A building that already holds an agreed supply sits outside the queue. 1,029 primary substations publish 10 MW or more spare today; 536 still do on the 2030 forecast. Those are the areas we search.
Every building in Britain is connected to a distribution network at low or high voltage. What matters for compute is not the connection but the agreed supply capacity written into the connection agreement: the MVA the network operator has promised to deliver, firm, at that point of supply. A building's physical substation might be rated at 2 MVA while its agreement says 1 MVA; the agreement governs. Anything above the agreement needs a new application, and that application joins the queue.
The network has four tiers between a building and the national grid. Headroom at any one of them can bind.
| Tier | What it is | Typical voltage | Who owns it | What binds here |
|---|---|---|---|---|
| Local substation | The transformer that feeds a street or an estate | 11 kV to 400 V | DNO | Transformer rating; usually the cheapest thing to upgrade |
| Primary substation | The 33/11 kV site that feeds a town or a district; c.4,300 in GB | 33 kV to 11 kV | DNO | Firm capacity (one transformer out) against peak demand plus accepted offers. This is the tier our power map reads |
| Bulk supply point | Feeds several primaries | 132 kV to 33 kV | DNO | Transformer and circuit ratings; reinforcement takes years |
| Grid supply point | Where the DNO meets the transmission network | 400/275 kV to 132 kV | Transmission owner, operated by NESO | Transmission impact; anything large enough to matter here needs a NESO assessment |
A 10 MW demand connection normally lands at a primary at 11 kV or 33 kV. Whether it needs a transmission assessment depends on the headroom at the grid supply point above it, not on a fixed MW threshold.
Distribution is a regulated monopoly by area. The licences were privatised in 1990 and have changed hands many times since; two changed in the last two years. The regulatory settlement is the same for all six and matters more than the owner, but the owner shows whose capital is behind the reinforcement programme.
| Group | Licence areas | Owner (2026) | Scale | Note for us |
|---|---|---|---|---|
| UK Power Networks | London, South East, East of England | Engie, since 7 May 2026 (bought from CK Infrastructure, Power Assets and CK Asset at a £10.5bn equity value) | c.8.3m homes and businesses | Our DNO. Kent, London and Essex are all UKPN. A UKPN director has said data centres on its network draw only 30 to 40% of their agreed capacity on average |
| National Grid Electricity Distribution | East Midlands, West Midlands, South Wales, South West | National Grid plc (bought Western Power Distribution from PPL for £7.8bn, 2021) | c.8m customers; the largest DNO | Publishes the most complete capacity data; the Midlands hold the most industrial floorspace |
| SSEN Distribution | Southern England, North Scotland | SSE plc (the 25% Ontario Teachers' stake is in SSEN Transmission, not distribution) | c.3.1m customers in the south; the north is sparse | Southern England borders UKPN's South East; no 2030 forecast in its published data |
| Northern Powergrid | North East, Yorkshire | Berkshire Hathaway Energy | 3.9m customers | Yorkshire has the second-largest count of primaries with 10 MW spare |
| SP Energy Networks | Central and Southern Scotland; Merseyside, Cheshire and North Wales | Iberdrola (ScottishPower) | c.3.5m customers (Indicated) | Central Scotland publishes the most spare capacity of any area, and has the least demand to use it |
| Electricity North West | North West | Iberdrola 88% (completed 2025, £2.1bn), Kansai-led consortium 12% | c.2.4m connections, 5m people | Now the same owner as SPEN; two of the six groups are Iberdrola |
Above them all sits NESO, the National Energy System Operator, publicly owned since October 2024. It runs the transmission queue, assesses large demand for transmission impact, and is now being directed by government on which demand projects go first. Ofgem sets the price controls (RIIO-ED2 runs April 2023 to March 2028 with £22.2bn of allowed spend; ED3 from April 2028 is being designed now) and writes the connection rules.
Cost. A 10 MW connection therefore costs mostly the sole-use works: the cable from the primary, the intake switchgear and metering. On a site that already holds the capacity, there is no connection cost at all, only the intake. The landlord scope in our model carries the intake and the network operator's charge; the biggest variable is whether the supply needs raising.
| Measure | Figure | Date and source |
|---|---|---|
| Transmission demand queue | 96 GW | End June 2025, when the queue closed; up 460% in six months (DESNZ, Mar 2026) |
| Waiting at distribution | 29 GW | Same date and source |
| Total demand offers, Nov 2024 to Jun 2025 | 41 GW to 125 GW | Ofgem, reported by law-firm briefings 2026 |
| Data centres in the transmission queue | c.140 projects, c.50 GW | NESO Call for Input, 2025 |
| Data centre queue by Ofgem's count | c.315 projects, c.73 GW | Ofgem Curate consultation, Jul 2026; 99% of that capacity is in projects above 40 MW |
| Demand that can connect before 2030 | 11 to 13 GW | NESO queue results, Dec 2025 (DCD says 13; Savills and Slaughter and May say 11); a further c.86 GW between 2030 and 2035 |
| London data centres live and queued | c.760 MW live, 8 GW+ queued | GLA figures via press, 2026; another count puts live at 1,050 MW |
| Data centres applying for gas instead | c.117 cases | Ofgem Connect update, Jun 2026: operators seeking gas generation to run before the grid arrives |
| Wait for a new 50 MW data centre connection | c.7 years | Burges Salmon, 2026; against c.4 in Northern Virginia and c.8 in Dublin |
Nscale's Loughton campus is the example. Planned at 50 MW rising to 90 MW, it lost its anchor customer in October 2026 when Microsoft withdrew, and is now reported for the 2030s. The constraint was 90 MW of new connection in Essex, not the building.
The DESNZ consultation of March 2026 (closed 15 April; summary updated 28 October 2026) uses the Planning and Infrastructure Act 2025 to: tighten queue entry for data centres across transmission and distribution together; designate a list of strategic demand projects, including AI Growth Zones, to which NESO must reallocate capacity freed when others leave the queue and for which it may reserve capacity ahead of need; and, later, align data centre connections to a national data centre strategy. A Connections Accelerator Service has run since December 2025 for a small number of named projects. Distribution-connected projects are not yet inside the prioritisation rules; the paper says a parallel process will be designed "as soon as possible".
The ENA's minimum information requirements for demand of 5 MVA and above took effect on 1 June 2026 across all DNOs: letter of authority, heads of terms, site plan, single-line diagram and a dated programme. The rule is aimed at speculators holding capacity on land they do not control. It also means an application in our name needs the site under contract first.
Effect. Each of these measures falls hardest on large, speculative, new-build connections. None of them touches a building that already holds an agreed supply. The reforms widen the gap between a 90 MW application and a 5 MW building whose capacity is already agreed.
The DNOs are regulated to a revenue allowance, so they reinforce when Ofgem lets them. ED2 allowed £22.2bn across the six groups for 2023 to 2028. The National Infrastructure Commission put the distribution need at £37bn to £50bn to 2050, at least double current annual allowances, and Ofgem's ED3 methodology decision of May 2026 moves to a build-and-flex model with the regional plans as the demand reference and a higher allowed return on equity. National Grid's chief executive said in 2024 that data centre demand would rise six-fold in ten years. The funding is in place or planned; the constraints are plant and people, and reinforcement at a bulk supply point still takes years.
Meanwhile the DNOs' own 2030 forecasts show headroom falling at 1,820 of the 2,940 primaries that publish one, as heat pumps, vehicles and housing take the slack. Headroom published today may not be there in four years.
Our own schedule reads the published headroom at 4,277 primary substations across the fourteen areas and tests it against each operator's 2030 forecast where one exists. The map and table below count primaries with 10 MW or more spare, the size that matters to us.
| Area | DNO | Primaries | 5 MW+ spare | 10 MW+ | of which hold to 2030 | 20 MW+ | Published headroom, MW |
|---|---|---|---|---|---|---|---|
| Central and Southern Scotland | SPEN | 389 | 305 | 211 | 141 | 12 | 4,011 |
| Yorkshire | Northern Powergrid | 363 | 175 | 118 | 75 | 11 | 2,271 |
| East of England | UKPN | 442 | 267 | 93 | 68 | 21 | 3,241 |
| London | UKPN | 106 | 102 | 88 | 69 | 47 | 3,208 |
| Southern England | SSEN | 424 | 153 | 80 | no forecast | 17 | 2,103 |
| South East | UKPN | 233 | 155 | 70 | 41 | 20 | 2,045 |
| North East | Northern Powergrid | 179 | 106 | 66 | 48 | 8 | 1,338 |
| Merseyside, Cheshire and North Wales | SPEN | 335 | 123 | 60 | 40 | 8 | 1,729 |
| West Midlands | NGED | 212 | 87 | 57 | mostly no forecast | 29 | 1,622 |
| North West | ENWL | 368 | 151 | 52 | 28 | 5 | 1,724 |
| East Midlands | NGED | 367 | 104 | 48 | 13 | 4 | 1,288 |
| South West | NGED | 305 | 72 | 45 | 7 | 5 | 990 |
| North Scotland | SSEN | 360 | 57 | 21 | no forecast | 0 | 762 |
| South Wales | NGED | 194 | 53 | 20 | 4 | 5 | 858 |
| Great Britain | 4,277 | 1,910 | 1,029 | 536 | 192 | 27,190 |
power.yeats.com, read 31 Oct 2026, from each DNO's published capacity data and long-term development statement. "Hold to 2030" counts primaries whose own operator's forecast keeps 10 MW or more spare; 209 of the 1,029 publish no forecast. All figures Indicated: a verdict band is never a DNO confirmation.
UKPN's three areas hold 251 of the 1,029 primaries with 10 MW spare, and 178 of the 536 that hold to 2030. For this size of load our DNO is the best placed in the country. Central Scotland has the most spare capacity and the least demand to use it, which is why the AI Growth Zone went to Lanarkshire. The Midlands have the most industrial floorspace but publish no 2030 forecast, so a building there is harder to underwrite than a weaker one in Kent.
Layer 1, our position in the chain. What a powered site is and the three forms it is sold in, who else holds one in Britain, what the market pays for power on land and in a building, what the American conversions show, and where our rent sits. Chapter 2 of From power to answer.
Basis. Market study, no returns. Rent is £750k per MW of firm supply a year; cost £4.0m per MW all in. Third-party figures are quoted as published, with sterling in brackets at October 2026 rates (£1 = $1.33 = €1.18). "Derived" means our arithmetic from a published total. Sources in section 2.7.
Sold three ways: powered land, powered shell, or fitted hall. We sell the powered shell in an existing building. The operator funds the kit.
In London and the other big European hubs, land with a connection carries that premium per megawatt (Linklaters, Jul 2026). Savills puts data-centre-ready land at £8m to £15m an acre against £4.5m to £6m for ordinary industrial.
The listed landlords are moving up the stack to fitted halls at 50 to 150 MW. The owner of the 4,600 closing exchanges has so far sold them for housing. Nobody is doing 5 to 15 MW in existing buildings at scale.
£750k a MW is £62.50 per kW a month, against CBRE's £145 for fitted London capacity. The operator funds the hall and the kit; we fund the building and the connection.
A powered site is land or a building with a firm electricity supply already agreed with the network operator. The industry sells it in three forms, and the form decides who funds what and what the rent is called.
| Form | What the landlord provides | What the occupier provides | How it is priced | Who sells it in Britain |
|---|---|---|---|---|
| Powered land | A site with a connection agreement, usually sold freehold | Everything above ground | £ per acre, or £ per MW of agreed capacity | Harworth, Segro (selected plots), landowners near substations, hyperscalers buying |
| Powered shell | A secure building, intake switchgear and metering at the point of supply, the connection | Internal distribution, generators, UPS, cooling, racks, fibre fit-out, the compute | £ per MW of firm supply a year, indexed, 10 to 15 years | Segro (Slough), Tritax (Manor Farm, planned), Yeats Edge in existing buildings |
| Fitted hall (turnkey, wholesale) | All of the above plus cooling, UPS, generators and often fibre | Racks and compute | £ per kW of IT load a month | Segro with Pure DC, Kao, Ark, Yondr, the London campus operators (chapter 3) |
Grid MW and IT MW are different numbers. A fitted hall quotes IT load, the power the racks draw. A powered shell quotes the agreed supply at the intake, which must also run cooling, losses and reserve. The gap is the operator's efficiency: a well-run liquid-cooled hall turns roughly 1 MW of supply into 0.8 MW of IT load; an old air-cooled one, less. Our rent is per MW of firm supply. Each comparison below states its basis. UK Power Networks has observed that data centres on its network draw on average only 30 to 40% of the capacity they hold. Operators therefore guard their agreements, and a building with a large, under-used agreement is worth looking at.
| Who | What they are | What they hold | What they do with it | Read for us |
|---|---|---|---|---|
| Segro | FTSE 100 industrial REIT; Slough Trading Estate | A "power bank" of 3.0 GVA across European availability zones (July 2026), 1.4 GVA of it to lease within seven years | Moving from powered shells to fully fitted halls in joint ventures with Pure DC: Park Royal (56 MW IT, c.£1bn, 70 MVA incoming, ready 2029) and a second in Paris. Still signs shells where a customer wants one: Slough, 50 MVA, pre-let March 2026 with the customer contracting the power directly | The reference landlord. Its move up the stack leaves the shell product to others, and its scale starts at 50 MVA |
| Tritax Big Box | FTSE 250 logistics REIT | Manor Farm, 74 acres by Heathrow, bought January 2025 for an initial £70m plus 21% of phase-one profit to the vendor | 107 MW phase one (147 MW with phase two), consented after a judicial review, to be built as a powered shell subject to a pre-let; a 50% joint venture with an unnamed European generator secures connections to two substations | Shows what a listed landlord pays for powered land and that it needs a pre-let before it builds |
| Harworth Group | Listed regenerator, now a pure-play powered land and logistics specialist | About 0.8 GW of further connections beyond Skelton Grange; up to six hyperscale sites, all freehold or under option | Sold two plots at Skelton Grange, Leeds, to Microsoft for £106m (resolution to grant April 2026); exclusivity on a second site to an unnamed provider, August 2026 | The purest powered-land seller in Britain. Its buyers are hyperscalers, not neoclouds |
| TT Group (Telereal Trillium) | Private property group; bought c.6,700 BT properties in 2001 for £2.38bn | Nearly all of Openreach's c.5,600 exchanges, c.4,600 of which close from 2025 into the early 2030s; the main lease runs to 2031 | Exited exchanges and offices sold so far have gone to housing; no data-centre reuse found, no marketing programme announced; first exits (Deddington 2025) done, next pilots slipped to November 2026 | The counterparty for the exchange channel. Slow, small per site, and not yet pricing the power |
| Stellanor (DWS) | Infrastructure fund platform | Eight Redcentric data centres, bought October 2025, completed May 2026 | Enterprise value up to £127m for "41 MW", of which 23 MW is secured grid: £3.1m to £5.5m per MW derived | A UK price for existing small sites with power |
| Gravity Edge (BlackRock, DGP) | Edge platform | Camberley enterprise data centre, September 2025, expandable to 20 MW | More than £100m including modernisation; strategy is 5 to 20 MW sites with under-used capacity | The closest strategy to ours in Britain, at the fitted-hall layer and with institutional money behind it |
| The hyperscalers as buyers | Microsoft, Google, Amazon | Buying powered land outright where it exists (Microsoft at Skelton Grange; Google's £5bn UK programme) | Build their own halls | They set the top of the land market and will not lease a 10 MW building |
| Yeats Edge | Sponsor-developer | A national screen of c.80,000 buildings against published headroom; two seed sites under appraisal | Buys existing buildings whose connection agreement already holds the capacity, does the landlord works, leases as a powered shell at £750k a MW | The gap: 5 to 15 MW, existing buildings, this decade |
| Evidence | Figure | Source | What it says |
|---|---|---|---|
| London industrial land | £4.5m to £6m an acre | Savills, reported April 2026 | The data-centre premium on an acre is £3.5m to £9m in London. At the rule-of-thumb half to one acre per MW, that is the price of the connection |
| London land suitable for a data centre | £8m to £15m an acre | Savills, same | |
| Powered land, FLAPD hubs (Frankfurt, London, Amsterdam, Paris, Dublin) | €0.8m to €1.4m per grid MW (c.£0.7m to £1.2m) | Linklaters, 8 July 2026 | The market value of a megawatt of agreed supply before any building; the cleanest figure in the table |
| Powered land, northern UK | €0.2m to €0.7m per grid MW (c.£0.17m to £0.6m) | Linklaters, same | Power is worth a third as much where the users are not |
| Northern Virginia, for comparison | c.$4m an acre entitled without power; $6m+ with | US trade press, 2026 | The same premium exists in the deepest market in the world |
| Manor Farm, Heathrow | £70m initial for 74 acres (c.£0.95m an acre) plus 21% of phase-one profit | Tritax RNS, January 2025 | Bought before the connection was secured; the power came afterwards through the generator joint venture |
| Skelton Grange, Leeds | £106m for two plots to Microsoft | Harworth, 2025 to 2026 | A hyperscaler paying for powered land in the north |
| Deal | Where, when | MW | Price | Per MW, derived |
|---|---|---|---|---|
| Stellanor buys Redcentric's eight sites | UK, May 2026 | 41 MW; 23 MW secured grid | EV up to £127m | £3.1m to £5.5m |
| Gravity Edge buys Camberley | Surrey, Sep 2025 | to 20 MW | more than £100m with modernisation | above £5m at 20 MW |
| I Squared buys ten Cogent data centres (converted Sprint switch sites) for an inference platform | US, May 2026 | c.53 MW | $225m (c.£170m) | $4.25m (c.£3.2m) |
| Cogent's asking prices, six converted sites | US, Feb 2025 | 3.9 to 8.1 MW each | $44m to $140m asked | $10m to $17m asked; a letter of intent later fell over on vendor finance |
| Loudoun net-lease hyperscale campus | Virginia, Dec 2025 | 160 MW | $555m | $3.47m (c.£2.6m); powered-shell cap rate 5.0%, turnkey 6.5% in the county's 2026 guidelines |
Our model carries £4.0m per MW all in (£2.5m building, £1.5m works). It sits inside the range paid for converted and edge stock in Britain and America. The Cogent asking prices show what a seller tries for when the site is already fitted and running.
| Lease | Form | MW, term | Contracted value | Per MW a year, derived |
|---|---|---|---|---|
| Yeats Edge, our model | Powered shell, existing building | per MW of firm supply, 10 to 15 years, indexed | n/a | £750k |
| Segro, Slough pre-let | Powered shell, new build | 50 MVA | not disclosed | n/d |
| TeraWulf to Fluidstack, Lake Mariner, New York | Turnkey, landlord-built on a former coal site; modified gross; Google backstop | c.200 MW, 10 years + two 5-year options | $3.7bn initial term ($8.7bn with extensions) | c.$1.85m (c.£1.4m); landlord cost $8m to $10m per critical MW; expected site margin c.85% |
| TeraWulf and Fluidstack joint venture, Texas | Turnkey, 51% TeraWulf; Google backstop | 168 MW, 25 years | c.$9.5bn | c.$2.26m (c.£1.7m) |
| Applied Digital to CoreWeave, North Dakota | Turnkey, landlord-built | 250 MW rising to 400 MW, 15 years | c.$7bn rising to c.$11bn | c.$1.85m (c.£1.4m) |
| Core Scientific to CoreWeave, 70 MW expansion | Modified site | 70 MW, 12 years | $1.225bn | c.$1.46m (c.£1.1m) |
| London fitted capacity, 20 MW+ | Fitted hall | per kW | up to £145 per kW, up 12% in a year | c.£1.74m if per month, on IT load |
| Segro and Pure, Park Royal | Fitted hall, c.£17.9m per MW to build | 56 MW IT | "9 to 10% net yield on cost" as published | c.£1.6m to £1.8m net |
The American figures are contract revenue over critical IT load and may bundle power pass-through and services; they are turnkey, not shell. They are precedent, not UK fact. The CBRE figure is a capacity price whose period is not stated in the release; per month is the industry convention.
Capital per MW and income per MW a year across the first three layers, from the figures above. Our position carries the smallest capital for the smallest rent; the fitted layer is two to four times both; the compute layer is another £26m per MW, funded by the operator. Sterling at October 2026 rates; US and CBRE figures on the bases stated in the tables.
The nearest precedent for buying power as a building is the United States in 2024 and 2025, where bitcoin miners, telecoms carriers and infrastructure funds turned existing powered sites into AI capacity faster than new capacity could be built.
The counter-evidence. Savills' view is that retrofits are "less compelling than occupiers expect because the critical cost sits in M&E". That holds for a fitted hall, where the building is a small part of £9.5m to £18m per MW. It does not hold for a powered shell, where the landlord provides the building and the connection and the tenant funds the M&E. Our model depends on keeping that split between landlord and tenant.
Layer 2. What a fitted data hall is and what it is sold in, who runs them in Britain and who owns those firms, what a megawatt of hall costs and who pays for each piece, how dense the racks are getting, and why the regional operators are the tenants to court. Chapter 3 of From power to answer.
Basis. Market study, no returns. Rent is £750k per MW of firm supply a year. Costs are "indicative" where derived from published shares of a whole-hall figure, and converted at £1 = $1.33. Sources in section 3.8.
A fitted hall sells IT load by the kW a month with power passed through at cost. London capacity at 20 MW+ is up to £145 per kW, up 12% in a year. The UK has 1,803 MW live, 91% of it in London, 8% vacant.
Virtus, Equinix, Digital Realty, Vantage, Ark, Kao, Global Switch, Telehouse and Yondr run the big London halls. Pulsant, nLighten, Latos and Datum run 1 to 5 MW sites in the regions, and are buying sites.
Of a c.£9m London hall, the landlord's share is £0.5m to £1.3m: the connection, the intake and the building. Everything beyond the intake is the lessee's, and liquid cooling adds £1m to £2.5m more.
A regional operator leasing our shell at £750k a MW and selling kW at the London rate has margin. The split at the intake switchgear keeps us a landlord. Density is the lessee's problem.
A fitted hall is a powered site with the critical plant installed: the distribution and transformers beyond the intake, uninterruptible power supplies, standby generators, cooling, fire suppression, monitoring, carrier fibre and the racks themselves. The product is not space but conditioned, backed-up IT load, sold by the kilowatt per month with the electricity recharged at cost.
| Term | What it means | Why it matters to the money |
|---|---|---|
| Wholesale colocation | Whole halls or suites, 1 MW and up, 10 to 15 year terms, to hyperscalers, neoclouds and large enterprises | 1,163 MW of the UK's live capacity. Priced per kW; the customer brings its own racks and often its own operations team |
| Retail colocation | Racks or cages, 3 to 5 year terms, to enterprises and service providers | 347 MW of live capacity. Higher price per kW, higher churn, more management |
| Power pass-through | Electricity billed to the customer at cost on metered consumption, "plus E" | The energy bill usually exceeds the base rent. It must never reach the landlord |
| PUE, power usage effectiveness | Total power drawn divided by IT power. 1.2 is good; 1.5 is old | Every 0.1 of PUE is a 10% difference in the customer's energy bill and in how much IT load one MW of supply can carry |
| Density | kW per rack | Decides whether air cooling will do and how many racks fit in a megawatt. See section 3.5 |
| Availability | The uptime promised, typically 99.99% or better, backed by service credits | The generators, UPS and concurrent maintainability exist to meet it; most of the hall's capital goes on this |
The campus operators run the London halls that hyperscalers and neoclouds lease at scale. The regional edge operators run 1 to 5 MW sites in the cities where enterprises and the public sector sit. The campus tier builds its own halls; the regional tier buys existing sites. Ownership is given where it could be confirmed from public sources.
| Operator | Owner | UK footprint | Who sits in their halls | Read for us |
|---|---|---|---|---|
| Virtus | ST Telemedia Global Data Centres (Singapore) | Largest UK operator by capacity in the 2025 portfolio reports; London5 at Slough estimated at c.90 MW | Hyperscalers, large enterprise | Builds its own campuses at 50 MW+; not a shell tenant |
| Equinix | NYSE-listed REIT | Slough and Docklands campuses; bought the undeveloped 85-acre DC01UK site in Hertfordshire | Interconnection, enterprise, cloud on-ramps | Reference for retail pricing; builds its own |
| Digital Realty | NYSE-listed REIT | Crawley (LGW15 and 16, 24 MW across the campus) and London; CoreWeave's first UK landlord | Neoclouds, cloud, enterprise | Shows a neocloud will take fitted space from a REIT on day one for speed |
| Global Switch | Jiangsu Shagang Group with Avic Trust; sale attempts since 2021 stalled on price | London East and North, Docklands; CoreWeave's second UK site | Carriers, cloud, neoclouds | A legacy Docklands position with Chinese ownership that some customers screen out |
| Telehouse | KDDI (Japan) | Docklands; North Two at c.73 MW (secondary estimate) | Carriers and the London internet exchange | Fibre density no other UK site matches |
| Vantage | DigitalBridge and Silver Lake-backed, US | 223 MW across 2.6m sq ft in the UK; Cardiff campus (£254m raised) | Hyperscalers | Wholesale at 50 MW+ per building |
| Ark Data Centres | Elliott Investment Management; TPG reported in talks to buy at c.$5bn (c.£3.8bn), late October 2026; Crown Hosting joint venture with the Cabinet Office | 27 UK and Belgian facilities; Cody Park and Longcross; £807m Longcross expansion for Nebius; 25 MVA "AI power hub" in Surrey | Government via Crown Hosting; Nebius | The public-sector channel, and a sale that will reprice UK halls |
| Kao Data | Infratil 53%, Legal & General Capital 32%, Goldacre NOÉ 15% (2023 split) | Harlow campus; Stockport 40 MW consented; Manchester £350m due 2026 | Nebius (22 MW, ten years), Ori, Civo | The neocloud landlord of choice; it knows every tenant on our list |
| Yondr | DigitalBridge-backed | Slough 100 MW campus; first 10 MW live April 2025; £532m green securitisation February 2026 | Hyperscalers | Shows the debt market will lend against fitted halls |
| CyrusOne, Colt DCS, Green Mountain | KKR and GIP; Fidelity; Azrieli | Iver Heath 90 MW planned; Hayes; LON-East Romford, where a neocloud took 14 MW in September 2026 | Hyperscale, enterprise, neocloud | Secondary references |
| Operator | Owner | Footprint | What they have done lately | Read for us |
|---|---|---|---|---|
| Pulsant | Antin Infrastructure Partners (since 2021) | 14 UK sites, platformEDGE; revenue c.£126m and EBITDA c.£24m in the latest figures a data vendor lists, year unstated | Bought two SCC sites (Birmingham c.2 MW, Fareham c.3 MW) in 2025; £187m facility refreshed October 2025 for acquisitions; 1.2 MW AI-ready hall at Milton Keynes, £1m into Birmingham for inference; customer racks up from c.4 kW to 10 to 20 kW | Buys sites of our size with fresh debt and is retrofitting for density |
| nLighten | I Squared Capital, with more than $500m (c.£375m) of committed equity; owns Proximity Data Centres in the UK (bought 2023, price undisclosed) | Ten UK edge sites from Proximity plus Europe | £100m UK programme; £85m financing led by Rivage, March 2026; Bristol refit for AI density, June 2026 | Pitches inference at the edge; acquisitive in the regions |
| Latos Data Centres | Founder-led; investors not disclosed online | Cardiff: three buildings, 90 MVA, under construction; Stockton-on-Tees £100m approved; East Manchester application | Targets 40 sites by 2030 with modular edge for AI | A pipeline model that needs sites; funding to be tested |
| Datum Datacentres | Ownership not confirmed online | Farnborough; two Manchester sites | 1 MW hall expansions | Too small to take 10 MW alone |
| Gravity Edge | BlackRock and DGP | Camberley, to 20 MW | Strategy of 5 to 20 MW sites with under-used capacity (chapter 2) | Closest strategy to ours, one layer up |
| Measure | Figure | Source and date |
|---|---|---|
| UK live capacity | 1,803 MW; London 1,637 MW (91%) | Savills, June 2026 |
| Of which wholesale / retail | 1,163 MW / 347 MW | Savills, same |
| Vacancy | 8% UK, 7% London (27% in 2016) | Savills Q1 2026; CBRE sees London at 5.9% by year end |
| Take-up | 217 MW in 2025; 19 MW in Q1 2026 | Savills; CBRE expects London above 200 MW in 2026 |
| Under construction, UK | 242 MW; c.66 MW completing in 2026, 96% pre-sold | Savills, June 2026 |
| Price, London 20 MW+ new capacity | up to £145 per kW, up 12% in a year | CBRE Q1 2026; providers raised prices at least 10% for buyers of 10 MW+ to cover build costs, and are raising indexation rather than headline rates |
| Build cost, London, air-cooled cloud hall | $12.0 per W (c.£9m per MW) | Turner & Townsend 2025–26 index; AI premium 7 to 10% (US data) |
| Build cost, Ofgem's planning assumption | £9.5m per MW | Ofgem, via Linklaters, September 2026 |
| Build cost, fully fitted, Segro and Pure | c.£17.9m per MW; "9 to 10% net yield on cost" | Segro RNS, 2025 |
| Site margin on a turnkey lease | c.85% NOI margin expected | TeraWulf, Lake Mariner, August 2025 (US precedent) |
| Retrofit for liquid cooling | c.$2m per MW against $11m+ greenfield | STL Partners, May 2026; a contrary view calls dense retrofits "reconstruction, not incremental retrofit" |
A London hall costs £9m to £18m a megawatt to fit and earns up to £1.7m a megawatt a year gross at the CBRE rate, with power passed through. The operator's margin is the gap between that rent and its cost of capital. The margin is wide while vacancy is 7% and every completing megawatt is pre-sold. The risk sits in the plant, which is bespoke to a density and a cooling method that change every two years. A hall fitted for 10 kW racks in 2022 is being refitted for 100 kW racks in 2026.
The figure below splits a fitted megawatt into its parts, with the landlord's items in teal and the lessee's in grey. The landlord's figures are from our own scope table; the lessee's are derived from the published shares of a c.£9m London hall (electrical 40 to 45%, cooling about 20%) and the cooling-method ranges quoted in 2026, so they are indicative and will vary by site.
| Landlord provides (our scope) | Lessee provides |
|---|---|
| The connection: network operator's charge, intake switchgear and metering at the point of supply | HV and LV distribution and transformers beyond the intake |
| Security: fence, gates, CCTV, access control | UPS and batteries; generators and fuel |
| Making good and refurbishment to a presentable standard | Cooling plant, air or liquid; dry coolers, pipework, CDUs |
| Welfare: toilets, kitchen, offices | Data-hall fire suppression, BMS, inside security |
| Base-building fire compliance; asbestos and surveys; planning | Floor strengthening for racks; fibre fit-out and carrier entries |
| Fees and contingency | Racks, PDUs, containment, and the compute itself |
The split at the intake switchgear defines our scope. On the landlord's side, c.£0.5m to £1.3m per MW with £1.5m carried; on the lessee's, £4m to £9m before a single GPU. The lease must set out where the split falls, in terms a lender's engineer can check.
Space is not the constraint. One megawatt at today's average density of 27 kW a rack is about 37 racks; at AI densities of 120 to 230 kW it is five to eight. With coolers, a megawatt needs roughly 650 sq ft. A 10 MW tenant needs about 6,500 sq ft of a building that may have 60,000.
| What | kW a rack | Cooling | Source |
|---|---|---|---|
| Average rack, 2026 survey | 27 (16 a year earlier) | Air | AFCOM 2026, via tenant advisory |
| Pulsant's customers | 10 to 20 (from c.4) | Air, rear-door exchangers | Pulsant, 2026 |
| Air cooling, practical ceiling | 30 to 50 | Rear-door heat exchangers at the top of the range | Several 2026 sources |
| Nvidia GB200 NVL72 | c.120 to 132 | Direct-to-chip liquid | 2025–26 specifications, figures vary |
| Nvidia Vera Rubin NVL72 | c.190 to 230 | Liquid | Schneider Electric, May 2026 |
| Inference, by model size | under 20 to 140 | Air to liquid | Schneider Electric, July 2026 |
The cooling decision belongs to the lessee. Whether a hall is air or liquid follows from the tenant's hardware, and it is their £1m to £4m a megawatt, not ours. Liquid cooling at the chip also makes the building less important. The heat is captured in a loop and rejected outside through dry coolers, so the room no longer has to move large volumes of air. An ordinary industrial shell with floor strength, a yard for coolers and a firm supply is a better host for a 2026 rack than a 2015 data hall built for air.
Layer 3. The firms that own the chips: who they are in Britain, how they are funded, what a GPU earns and loses over its life, who stands behind them, and who has already stumbled. Our tenant sits in this layer. The question for us is whether it will still be paying in year eight. Chapter 4 of From power to answer.
Basis. Market study, no returns. Company figures are as filed or announced, with sterling in brackets at £1 = $1.33. "Our arithmetic" is marked where we have derived a per-MW or per-GPU figure from a published total. Sources in section 4.8.
A megawatt of H100-class compute costs c.£26m to buy and earns c.£7m to £20m a year gross at 70% busy, depending on a rental price that fell from c.$8 an hour in 2023 to c.$2 in 2025 and sits at $2.6 to $4.2 today.
One is filing to list on $140m of half-year revenue and a $1bn loss; one has £1.7bn committed here; one has $50bn of debt and bonds yielding 16%; one is founder-owned with a 1 GW plan; one is Brookfield's.
Hyperscaler take-or-pay contracts, GPU-backed loans now rated investment grade, vendor leases, and Nvidia renting back unused capacity. A refinancing wall sits in 2026 to 2028.
A neocloud's credit is its contract book and whoever stands behind it. Our lease should test both: customer concentration, any backstop, whether the financing is in place, and a re-let right if it is not.
A compute operator buys accelerators, racks them in a hall, and sells their time: by the hour on demand, by the month reserved, or by the year and the cluster under a take-or-pay contract with a hyperscaler or a lab. The unit of sale is a GPU-hour; the unit of capacity is still a megawatt, because the chips are bought to fill a power budget.
| Generation | Rack | Power a rack | GPUs a MW, our arithmetic | Rental, on demand, Oct 2026 |
|---|---|---|---|---|
| Hopper H100 / H200 (2023–25) | 8-GPU servers, air or rear-door cooled | c.10 to 40 kW | c.800 to 1,000 at c.1 to 1.2 kW a GPU all in | $2.6 to $4.2 an hour median; $1.6 on the SF Compute market; $7 to $12 at hyperscalers |
| Blackwell GB200 NVL72 (2025–26) | 72 GPUs, liquid cooled | c.120 to 132 kW | c.550 | c.$8 median; $2 to $6 by tier and term |
| Vera Rubin NVL72 (2026–27) | 72 GPUs, liquid | c.190 to 230 kW | c.330 to 380 | $9.50 median for B300, Rubin not yet quoted |
Rental figures from the Uvik index of 7 October 2026 and the IntuitionLabs comparison, both vendor-maintained; treat as indicative. Each generation puts fewer, dearer chips in a megawatt and asks the hall for liquid cooling.
| Who | What they are | In Britain | Money and risk, as published | Read for us |
|---|---|---|---|---|
| Nscale | UK neocloud, founded 2024, Nvidia holds over 5%; filed an S-1 on 18 September 2026 to list on the NYSE | Loughton 50 to 90 MW, grid-delayed to the 2030s, lost Microsoft as anchor 18 October 2026 and says it is looking at other power; three BT sites, 14 MW; Stargate UK with OpenAI; sovereign pitch | H1 2026 revenue $140.6m (c.£106m), net loss $1.02bn (c.£770m), of which $457m currency; $103.4bn (c.£78bn) of active and contracted value over c.461,000 GPUs; Microsoft up to $43.8bn, Anthropic up to $44.6bn, both conditional on delivery; largest customer 52% of revenue; "has not yet obtained binding commitments for the financing" of the GPUs and sites those contracts need | The strongest demand in Britain; its prospectus also sets out the layer's risk more clearly than any other source. A tenant whose contracts exceed its financing needs a site with power now |
| Nebius | Amsterdam-headquartered, Nasdaq-listed; Microsoft ($17.4bn, New Jersey) and Meta contracts | £1.7bn UK programme announced 8 June 2026; 22 MW at Kao Harlow on ten years, hosting its cloud and the Token Factory inference service; three UK clusters, reported at 65 MW by 2027; also Ark Longcross | Listed, with hyperscaler take-or-pay behind it; takes fitted halls, not shells | The best-funded tenant for a fitted hall in Britain; a second-pass call, not a first |
| CoreWeave | Nasdaq-listed US neocloud, the sector's bellwether | Docklands (Global Switch), Crawley (Digital Realty), Scotland (DataVita); c.£2.5bn UK commitment; "leases rather than builds" for speed | Debt $35bn at 30 June 2026 and c.$50bn (c.£38bn) by October; shares fell c.15% in the week of 14 October as 2031 bonds yielded above 16% and credit default swaps implied high default odds; backlog $104bn (c.£78bn); Nvidia committed to buy unsold capacity to April 2032; its $8.5bn facility was rated investment grade on the strength of the contracts behind it | A $100bn order book has not settled the credit question. Its cost of capital is a guide to the pricing of every neocloud lease |
| Civo | Stevenage cloud provider, founded 2015, founder-led; THG took a minority stake in 2021 (c.£1.4m); no venture round found | 40 UK edge sites planned at c.1 GW combined; first 8 MW in Hertfordshire rising to 38 MW; five more sites of 150 MW secured in Lancashire, Greater Manchester, London and Oxfordshire; "inference at the edge rather than training overseas"; hosted at Kao today | Financing for the 1 GW programme is not disclosed; it is the first question to ask | The closest match to our size and thesis, and the thinnest public balance sheet on the list. A natural tenant if a backstop or a partner stands behind it |
| Radiant (Ori) | Brookfield's AI cloud unit, formed by merging with UK neocloud Ori in February 2026 at a reported $1.3bn (c.£1bn) valuation; part of a $10bn Brookfield AI infrastructure fund with Nvidia among the backers | Ori's first UK region at Kao Harlow; Ori had £42.5m of net assets at end-2024 and c.$100m of vendor lease finance for its GPUs | Aimed at sovereign governments, enterprises and telecoms on long contracts, on Nvidia's DSX design | Brookfield money behind a UK operator is a covenant a lender can accept |
| Fluidstack | Neocloud; headquarters moved from London to New York, December 2025 | None current; left a €10bn French project to focus on US gigawatt sites with Anthropic and Google | c.$750m raised at $7bn, April 2026; reported borrowing capacity of up to $10bn from Macquarie and others, undisclosed by the company; Google backstops its leases at two US sites | The template for the backstop structure, not a UK tenant |
| Lambda | US GPU cloud | No UK site found | $926m term loan B rated Baa2, September 2026, the first investment-grade syndicated loan to a private neocloud; c.$1.5bn Nvidia lease-back | Shows GPU debt going mainstream |
| DataVita | Scottish operator | Lanarkshire AI Growth Zone, up to 500 MW; CoreWeave's Scottish host | $406m (c.£305m) financing, August 2026 | The Growth Zone model: too big and too far for us; a reference |
| The hyperscalers' own regions | Microsoft, Google (£5bn UK), Amazon | Own campuses and leased halls; also the main buyers of neocloud capacity (Microsoft c.$33bn of neocloud contracts) | Investment grade | Not a tenant for a 10 MW shell; often the credit behind one |
| Sovereign compute | The state as operator | Isambard-AI, Bristol: 5,444 H100s, eleventh in the world in November 2025; Dawn at Cambridge, a six-fold upgrade for £36m; the AI Research Resource to grow twenty-fold by 2030 under a £1bn roadmap; a £500m Sovereign AI Unit; a c.£250m AIRR cloud-compute contract tendered in 2026 for a prime to subcontract to several cloud providers | Public money, slow procurement | Demand our tenants can sell into; not a tenant |
| Layer of money | Who provides it | Evidence, 2026 | What it depends on |
|---|---|---|---|
| Take-or-pay contracts | Hyperscalers and labs | Microsoft c.$33bn across neoclouds; Nscale's $43.8bn and $44.6bn agreements; Nebius $17.4bn; CoreWeave's $104bn backlog | Delivery on time. Most are conditional on the capacity existing, which depends on power |
| Venture and public equity | Funds, Nvidia, the market | Nscale c.£1.5bn Series C at c.£11bn and an IPO; Fluidstack $750m at $7bn; Nvidia stakes in CoreWeave, Nebius, Nscale | Sentiment. The October 2026 sell-off repriced the layer in a week |
| GPU-backed debt | Private credit, now banks | Sector estimate above $20bn; CoreWeave's $8.5bn delayed-draw facility rated investment grade in March 2026; Lambda's $926m Baa2 term loan in September; Fluidstack's reported $10bn capacity | Contracted cash flows and the chips' resale value. Lenders lend against the contract, then the collateral |
| Vendor and lease finance | Equipment lessors, Nvidia | Ori's c.$100m from a lessor; Lambda's $1.5bn Nvidia lease-back | The lessor's view of residual value |
| Vendor backstop | Nvidia | From 1 July 2026 Nvidia rents back unused capacity from partner neoclouds at a fixed rate, giving lenders a utilisation floor; its commitment to CoreWeave runs to April 2032; reports of up to $125bn of backstop within a $500bn financing platform | Nvidia's own balance sheet and its interest in keeping buyers solvent. Critics call it circular |
| Customer backstop | Google, so far | Lease guarantees at TeraWulf and Cipher in return for warrants over the landlord (chapter 5) | The end customer needing the capacity enough to carry the operator's credit risk |
The money follows the contract. A neocloud with a signed hyperscaler agreement can borrow; one without cannot, whatever its chips are worth. Maturities are also short. Analysts describe a refinancing wall in 2026 to 2028, as GPU loans fall due before the contracts behind them have paid out. A lease we sign in 2027 puts its tenant inside that window.
Our arithmetic from published prices: c.1,000 H100-class GPUs in a megawatt at c.£26k installed; rental at $1.6 to $4.2 an hour; 70% utilisation; UK commercial power at c.£0.19 to £0.24 per kWh with PUE 1.2. The right-hand panel indexes the on-demand H100 price to its 2023 peak and overlays straight-line book value at three and six years. Vendor indices, not audited figures.
The return on a megawatt of chips depends on rental price, utilisation and depreciation. The rental price fell about 75% from the 2023 peak to 2025 and has since risen: the one-year H100 contract index was up 38% between October 2025 and March 2026, and several first-party list prices rose again in the autumn. Utilisation decides how much of that price is earned. 81% of enterprises report their GPUs busy half the time or less, one vendor claims about 5% in practice, and UK Power Networks sees data centres draw only 30 to 40% of the capacity they hold. Depreciation is disputed. The hyperscalers book servers over five and a half to six years; some neoclouds use three. A well-known short-seller claims the industry has understated depreciation by c.$176bn for 2026 to 2028. The defence is that older chips move from training to inference and keep earning; CoreWeave has said expiring 2022-vintage H100 contracts re-booked at 95% of the original price.
A megawatt of chips must earn back c.£26m in three to six years while paying c.£2m to £2.5m a year for power and £0.75m to £1.7m for the hall. At today's prices and 70% utilisation it does, with margin to spare. At 30% utilisation, or at the 2025 trough price, it does not. The hall rent is the smallest number in the stack. A tenant in trouble therefore stops paying the landlord last and resumes first, because the chips cannot run without the hall's power.
Layer 4. How a GPU owner finds a buyer, who the buyers are, what sits between them, and the credit structures that have started to stand behind the operator's lease. This layer decides whether our tenant's rent is a bankable cash flow. Chapter 5 of From power to answer.
Basis. Market study, no returns. Contract values are as reported, with sterling in brackets at £1 = $1.33; where sources conflict, both figures are given. "Our arithmetic" marks a figure we have derived. Sources in section 5.8.
Take-or-pay contracts with hyperscalers and labs; direct sales to enterprises and the state; marketplaces and brokers; and inference platforms that rent capacity and resell it by the token.
Microsoft has committed c.$60bn (c.£45bn) across neoclouds; Meta, OpenAI and Anthropic tens of billions more. In Britain the state buys through Crown Hosting, G-Cloud 15 and a £250m research-compute contract.
Google guarantees Fluidstack's leases for warrants over the landlord. Nvidia guarantees up to $860m of Nscale's rent to a Texas landlord for $60m of warrants, and rents back unused capacity. Nothing like it in Britain yet.
In the money-flow diagram the rent is the smallest flow. The credit support behind the lease is what a lender prices. Ask every bidder what credit support stands behind them.
| Route | Who buys | Contract | Share of the market | What it means for the operator's credit |
|---|---|---|---|---|
| Take-or-pay | Hyperscalers and frontier labs | Three to fifteen years, paid whether or not the cluster is used, often with prepayments, conditional on delivery | The bulk by value: CoreWeave's $104bn backlog, Nscale's $103bn of contracted value | Turns revenue into a receivable a lender will finance. Concentration is the price |
| Direct enterprise and sovereign | Banks, pharma, media, universities, the public sector | Reserved capacity by the month or year; public frameworks | Growing; the UK's sovereign programme is one of the largest public buyers in Europe | Diversified but slower to sign and smaller per deal |
| Marketplaces and brokers | Developers, start-ups, anyone with a burst | By the hour; resale of unused reserved capacity | Small by value, large by count; SF Compute, Nvidia's Lepton, Vast.ai, Shadeform | A utilisation top-up, not a covenant |
| Inference platforms | Application companies that want tokens, not GPUs | Per million tokens or per GPU-minute; the platform rents capacity from operators and resells it | Together AI c.$1.15bn of bookings; Fireworks above $1bn annualised; Baseten c.$600m to $1bn | A large, fast-growing wholesale buyer of neocloud capacity, with venture money behind it |
| Buyer | What they have committed, as reported | In Britain | Read for us |
|---|---|---|---|
| Microsoft | c.$60bn (c.£45bn) across CoreWeave, Nebius ($17.4bn to $19.4bn, New Jersey), Nscale (up to $43.8bn, conditional), IREN ($9.7bn, five years, 20% prepaid) and Lambda (undisclosed, multi-billion); booked as operating cost, not capex | Left Nscale's Loughton site in October 2026 for want of power while remaining Nscale's largest customer; own UK regions | The largest buyer of neocloud capacity in the world, and the one that walked away from a UK site because the grid was late |
| Meta | CoreWeave $14.2bn (September 2025) and a reported c.$21bn expansion to December 2032 (April 2026); Nebius c.$27bn with c.$12bn in the first five years | No UK neocloud deal found | Sets the scale of a single take-or-pay |
| OpenAI | CoreWeave $22.4bn in 2025 across three agreements; Oracle and Stargate; Stargate UK with Nscale, Nvidia and Arm (September 2025), reported paused in 2026 | Stargate UK's status is unclear in the public record | A lab that signs with neoclouds, and whose UK plans depend on Nscale delivering power |
| Anthropic | Nscale up to $44.6bn (conditional); CoreWeave multi-year from April 2026, undisclosed, analysts $4bn to $7bn over five years; Lambda multi-year; US sites with Fluidstack | Via Nscale's UK contracts, if delivered | Conditional on capacity existing; the same dependency on power |
| Buys through Fluidstack and backstops its leases (TeraWulf $1.8bn rising to $3.2bn; Cipher $1.4bn; the Texas joint venture $1.3bn); £5bn UK commitment | Own UK regions | Originator of the backstop structure we want | |
| The UK public sector | The AI Research Resource growing twenty-fold by 2030 under a £1bn roadmap; a c.£250m cloud-compute contract tendered in 2026 for a prime to buy from several providers; the £500m Sovereign AI Unit granting GPU hours; Crown Hosting (Ark's joint venture with the Cabinet Office) winning departmental awards; G-Cloud 15 live from 6 August 2026 with AI listings; the MoD's £180m Digital Decision Accelerators framework with an edge compute lot | All of it | Demand that must be served onshore by operators who can prove where the data sits. Our tenants' route to it is Crown Hosting, G-Cloud and the AIRR prime |
| Inference platforms | Together AI ($800m raised at $8.3bn, July 2026), Fireworks ($1.5bn at $17.5bn), Baseten ($1.5bn at c.$13bn, June 2026); all rent capacity and resell it | Serve UK developers from wherever the capacity sits; UK data residency is a selling point they need | A wholesale buyer of our tenant's hours, growing faster than the hyperscalers |
| Who | What they are | How they make money | UK relevance |
|---|---|---|---|
| SF Compute | A real-time market for H100 and H200 clusters, from one node for an hour to thousands for years; owns no GPUs; $40m Series A at $300m, December 2025 | A fee per trade, reported at c.10%; customers reselling unused capacity recovered c.25% on average (company figure, September 2026) | Lets a UK operator sell spare hours and lets a buyer avoid a long contract. It trades hours, not megawatts |
| Nvidia DGX Cloud Lepton | Nvidia's marketplace routing developers to partner clouds; launched May 2025 with CoreWeave, Crusoe, Lambda, Nebius, Nscale and others; European additions include Mistral, Fluidstack, Scaleway and Together; AWS and Azure joining; Nvidia has folded its own DGX Cloud back to internal use and pushed Lepton instead | No published rate card; providers bill at their own rates through Nvidia | Nscale and Nebius are partners. A channel through which a UK cluster reaches global developers, controlled by the chipmaker |
| Vast.ai | Peer-to-peer market; hosts list machines, renters bid; H100 at c.$2.13 an hour on the community tier, October 2026 | Commission on rentals | The price floor for an hour of H100; unreliable hosts cost 20 to 40% more in practice |
| Shadeform | Aggregator with one console across more than twenty clouds including Lambda, Nebius and Crusoe; charges the buyer no fee | Paid by the providers | How an enterprise buys without a procurement team |
| Inference platforms (Together, Fireworks, Baseten) | Rent GPU capacity wholesale, run models, sell tokens | Margin between the GPU-hour and the token | The fastest-growing wholesale buyer of neocloud hours |
| The AIRR prime | The winner of the £250m research-compute contract, expected to subcontract to several cloud providers | A managed-service margin | The one UK intermediary that buys at scale for the state |
| Property agents | CBRE, JLL and the rest (chapter 0) | Fees on leases and sales | Place shells and halls with operators; do not trade compute |
None of the marketplaces buys megawatts. They matter to us only through our tenant's utilisation. A tenant that can sell idle hours into SF Compute or Lepton loses less in a bad quarter.
| Site | Lease | Backstop | Google's consideration | Mechanics |
|---|---|---|---|---|
| TeraWulf, Lake Mariner, New York | c.200 MW to Fluidstack, ten years plus two five-year options, c.$3.7bn initial term | $1.8bn (c.£1.35bn), later raised to $3.2bn (c.£2.4bn) | Warrants reported at c.8% of TeraWulf, later increased | On a Fluidstack payment default or insolvency, Google may pay the termination fee or pay the rent due and assume the lease. It is not a guarantee of the landlord's own debt. The landlord then borrows against the guarantee |
| Cipher Mining, Barber Lake, Texas | 168 MW IT to Fluidstack | $1.4bn (c.£1.05bn) | Warrants for c.5.4% of Cipher | |
| TeraWulf and Fluidstack joint venture, Texas | 168 MW, 25 years, c.$9.5bn | $1.3bn (c.£1bn) | Further warrants |
Nscale's US subsidiary signed a ten-year triple-net lease with Ionic Digital for the Cedarvale facility in Ward County, Texas: 234 MW and about $2bn (c.£1.5bn) of contracted rent, reported at $65 per kW a month. On 14 October 2025 Nscale issued Nvidia warrants over up to 9,476,700 preferred shares, worth $60m (c.£45m) at an exercise price of a cent, and in return Nvidia agreed to guarantee up to $860.34m (c.£650m) of Nscale's obligations under the lease, reported as the first five years' rent, with further "default warrants" that become exercisable if Nscale defaults on a lease Nvidia has guaranteed. All of this is in Nscale's prospectus. It is the clearest precedent for a landlord of a young operator. The chip supplier stood behind the rent, and the landlord could borrow against it.
From 1 July 2026 Nvidia rents back unused capacity from partner neoclouds at a fixed rate, which gives their lenders a utilisation floor; its commitment to buy CoreWeave's unsold capacity runs to April 2032; reports put the programme at up to $125bn within a $500bn financing platform. This protects the operator's revenue rather than the landlord's rent directly, but a tenant with a revenue floor is better placed to pay its rent.
No European or UK backstop of either kind was found. CBRE reports a different response. Capacity sold to neoclouds in Europe rose from 133 MW in the first nine months of 2024 to 414 MW in the same period of 2025, and to 420 MW in the first half of 2026 against 89 MW a year earlier, with 57% of the 2025 volume in the Nordics; and operators are "implementing measures to manage the additional risk", chiefly higher rents to offset build costs. Lawyers in the US note the structures are already evolving from full lease guarantees towards residual-value guarantees, where the customer promises the landlord a floor value at the end rather than every payment along the way.
Our arithmetic for a 10 MW shell let at £750k a MW to an operator running c.10,000 H100-class GPUs: gross revenue £70m to £200m a year at 70% utilisation on the October 2026 price range; power c.£20m to £25m a year passed through at PUE 1.2; kit c.£260m once; rent £7.5m. The dashed arrows are the three structures in section 5.4.
The operator's largest outgoings are its chips and its electricity; its rent to us is a few percent of its revenue. Its credit therefore depends on the end customer's take-or-pay commitment, and on whether that customer or the chipmaker provides credit support to the landlord or the lender. A tenant with a named off-taker and a backstop is a different credit from the same tenant without them, in the same building, paying the same rent.
Layers 5 and 6. Who runs models in Britain and who uses them, what a request needs in milliseconds, how far from London a site can sit, which rules pull inference onshore, and what a token is worth. Chapter 6 of From power to answer.
Basis. Market study, no returns. Adoption figures are official statistics where available (ONS, Ofcom, DSIT) and company-stated where not. The latency arithmetic is ours. Sources in section 6.8.
54% of UK adults used AI in 2026 (Ofcom), 79% of 16 to 24s; 35% of businesses with ten or more staff use it (ONS, June 2026), but only 10% of those extensively. OpenAI's first permanent London office is sized for 544 staff.
A voice agent has to answer in under a second; the model takes 150 to 300 ms of that and the network 50 to 150. Every hop adds 5 to 50 ms. Light in fibre crosses Britain in about 4 ms.
From a Kent site, 59% of the people in Britain's large urban areas sit within 2 ms one way and 92% within 4 ms. Latency argues for Britain over Virginia, not for Kent over Slough. The exceptions are listed in 6.3.
No UK rule forces inference onshore, but the public sector, the NHS and regulated finance buy as if one did, and the Treasury has started designating cloud providers as critical. A UK-owned landlord with firm power answers part of a tenant's sovereignty question.
At the top of the chain a user sends a request to a model and waits for the answer. What they buy is measured in tokens, roughly three-quarters of a word each. What they notice is latency: the time to the first token and the pace of the rest. Every layer below the user is there to make that wait short and that token cheap. Google alone says it processed 3.2 quadrillion tokens in a month by May 2026, seven times the year before and 330 times the year before that; its APIs run at about 19 billion tokens a minute. Those are company figures, unaudited, but the direction is not in doubt.
| Kind of request | What "fast enough" means | Of which the model | Of which the network | Where the compute can be |
|---|---|---|---|---|
| Chat, search, writing, code | First token in under a second; a page in a few seconds | Most of it | Tens of ms, unnoticed | Anywhere in Europe; a US region is c.70 ms away and still tolerable |
| Voice agents, call centres | Reply in 500 to 800 ms end to end; past a second it feels broken | 150 to 300 ms first token | 50 to 150 ms across speech-to-text, model and speech, so each leg must be short | In the country, on the call path; tail latency (the slowest 1%) is what breaks it |
| Agents calling tools in loops | Each step tens to hundreds of ms, dozens of steps | Most of it | Multiplied by the number of steps | Near the data and the tools it calls |
| Mobile networks (AI-RAN), vehicles, robotics, trading | Milliseconds, deterministic | Small models | 1 to 10 ms round trip, or it does not work | In the metro, within c.100 km, or on the device |
| Batch: documents, images, overnight analysis | Minutes to hours | All of it | Irrelevant | Wherever power is cheapest; Scandinavia and Scotland win |
Budgets from vendor and practitioner sources (Nvidia, Telnyx, Ultravox, 2026); they differ at the margin but agree on the ranges. Network legs from the same sources and our arithmetic at 5 µs per km of fibre.
| Who | Scale, 2026 | Source | What they buy |
|---|---|---|---|
| Adults | 54% used AI (Ofcom, April 2026); 59% had used generative AI (DSIT survey, Nov 2025 to Mar 2026); 29.6m people used AI tools in July 2026 (UKOM); ChatGPT took 76% of UK time on AI tools | Ofcom, DSIT, IAB UK via UKOM | Consumer subscriptions and free use, served from the labs' own regions, mostly abroad |
| Businesses | 35% of firms with ten or more staff use AI, from 12% in late 2023; 49% of those with 250 or more; only 10% of adopters use it extensively, averaging 1.6 tools; 58% in information and communication; 55% of employees use AI for work | ONS, June 2026 | Enterprise subscriptions, APIs, and increasingly private deployments for regulated data |
| The labs in London | OpenAI's first permanent office, 88,500 sq ft at King's Cross for 544 staff by 2027 (April 2026), days after pausing Stargate UK; Anthropic space for c.800; Google DeepMind's home; AI firms took 661,068 sq ft of London offices in the first half of 2026, more than all of 2025 | Knight Frank, CoStar, press | People, not compute: the models are served from their own clouds, with a UK data-residency option from OpenAI under a government memorandum |
| UK model and product firms | Wayve (robotaxis live in London with Uber from 3 September 2026, under 20 cars, a safety driver aboard), Synthesia, ElevenLabs, Stability, PolyAI, Quantexa, Darktrace and the rest | Press | Training abroad; inference wherever their customers are; the vehicle case runs on the car |
| The NHS | £30m for AI diagnostics in 2026, £20m of it to put a chest X-ray tool in every English trust by 2029; a £900m AI framework for 2027 to 2035 with radiology among eight lots | DHSC, NHS England | Models that run against patient data, bought through frameworks; hosting allowed offshore since 2018 guidance, but supplier standards increasingly say "operated within the UK" |
| Government and defence | The Ministry of Justice's OpenAI deal; the compute roadmap's warning of a 5 GW UK compute gap by 2030 without intervention; the MoD's edge compute lot; AI-RAN trials on EE's live network in Birmingham | gov.uk, MoD, BT | Sovereign-labelled capacity, slowly |
| Regulated finance | AWS, Google, Microsoft and Oracle designated critical third parties from 13 July 2026; a single incident and third-party reporting framework from March 2026; the Treasury Committee pressing for AI providers to be designated next | HM Treasury, FCA, PRA | Resilience and auditability first; a named UK site is a comfort |
Our arithmetic. Dots are the 45 largest urban areas of Great Britain, c.33m people, sized by population. Rings are one-way fibre latency from a site at Ramsgate, Kent, at 5 microseconds per kilometre over a route 1.4 times the straight-line distance; double them for a round trip. Within 1 ms: 33% of those people (London). Within 2 ms: 59%, to Birmingham and Southampton. Within 4 ms: 92%, to Manchester, Leeds and Cardiff. Glasgow and Edinburgh sit at about 5 ms.
A Kent site reaches every English city in under 4 ms one way. A Virginia region is about 35 ms away; Amsterdam and Frankfurt are 3 to 5 ms. Latency therefore argues for Britain over abroad, not for one British town over another. For chat, agents and documents, Kent, Slough and Manchester are indistinguishable to the user. The exceptions are metro-scale. Mobile networks, vehicles, robotics and voice at scale want their compute within a millisecond or two, which is a circle of 100 to 150 km around the people, and for 59% of Britain's urban population a Kent site is inside that circle. Residential measurements agree: Edinburgh to London on an ordinary broadband line is about 14 ms round trip, London to Amsterdam about 6, London to Frankfurt about 9.
The map does not show Kent's subsea landings. The cables that join Britain to the Continent land on its coast: EXA's Margate to Ostend route opened in 2025, and a new system is planned for Dumpton Gap by Broadstairs, a landing station used before. A site in east Kent is as close to Brussels and Amsterdam as it is to Birmingham. That matters to a tenant selling into Europe from a British address.
| Rule or habit | What it says | Effect on where compute sits |
|---|---|---|
| UK GDPR, Data Protection Act 2018, Data (Use and Access) Act 2025 | Lawful transfer abroad with safeguards; no residency mandate | Permissive in law; the burden of proof sits with the exporter |
| Government cloud guidance | No policy prevents a department storing or processing data in any particular country, but it must weigh the implications; there is no formal UK sovereign cloud policy (Pinsent Masons); a national cloud strategy has been promised | Permissive; departments increasingly choose UK anyway |
| NHS offshoring guidance (2018) and supplier standards | Public cloud, including offshore, is allowed after a risk assessment; some NHS England supplier standards require every component of a solution to be operated within the UK | Mixed; the newer standards point onshore |
| Critical third parties regime (HM Treasury, FCA, PRA), from 13 July 2026 | AWS, Google, Microsoft and Oracle designated; regulators to assess AI and cloud providers for further designation; unified incident reporting from March 2026 | Not residency, but resilience: regulated firms must show where their critical services run and how they fail over |
| The labs' own moves | OpenAI offers UK data residency under its government memorandum and signed the Ministry of Justice; the sovereign AI programme grants GPU hours on Isambard | The buyers' preference is being met commercially before it is legislated |
| The US CLOUD Act argument | Vendors (Civo and others) sell UK-owned, UK-incorporated hosting as the only way data stays under UK law | A marketing position with legal weight; it favours UK-owned operators and landlords |
As with the credit support behind leases in chapter 5, buyers are moving ahead of the rules. No statute makes a bank or a hospital keep its inference in Britain; most of them choose to anyway.
| Measure | Figure | Source |
|---|---|---|
| Fall in token prices, 2020 to 2026 | c.600-fold | arXiv 2603.28576, 2026 |
| GPT-4 at launch, input, per million tokens | $30 | OpenAI pricing, 2023, via press |
| GPT-5, input and output, per million | $1.25 and $10 | OpenAI pricing via press (secondary) |
| Economy-tier price for comparable quality | $0.10 per million | arXiv, Gemini Flash example |
| Blended index low | $0.97 per million, 31 Aug 2026 | Silicon Data |
| Frontier prices versus March 2023 | down 84%; but up 72% year on year in September 2026 | BenchLM index |
| Enterprise spend per million tokens | c.$10 to c.$2.50 in a year | Ramp data via press |
| Google tokens a month | 9.7 trillion (2024), 480 trillion (2025), 3.2 quadrillion (May 2026) | Google I/O, company-stated |
The price of a token has fallen by two orders of magnitude while the number of tokens has risen by more. The hour of compute underneath them got dearer in 2026 (chapter 4). The industry calls this the Jevons effect: cheaper inference leads to more of it. For the layer above us it means thin margins and constant repricing. For the layers below it means demand for GPU-hours keeps rising even as the price of their output falls. The operators who run inference cheapest per token, near their users and with power they already have, keep the work.
Thread A. The chain's finance in one place: who funds each layer, what their money costs, where the debt is sized, and what a lender will and will not lend on, from Ofgem's allowed returns to a GPU loan at ten per cent. Chapter 7 of From power to answer.
Basis. Market study, no returns. Costs of debt and allowed returns are as published; rates quoted in the currency of the deal. The description of our own layer is of structure, not outcome. "Our arithmetic" is marked. Sources in section 7.8.
Ofgem's early view for ED3 allows a 6.08% real return on equity at 60% gearing and a debt allowance of c.5.5% to 6.2% nominal. Engie paid a c.50% premium to UKPN's regulated asset base, implying a cost of equity of about 4.3%.
Property and infrastructure debt against rent: Virtus's £2.45bn from thirteen banks, Yondr's £532m AA-rated securitisation, Pulsant's £187m. Prime UK data centre yields 5.5% to 6.5%.
A GPU loan costs SOFR plus 2.25% with a hyperscaler contract behind it and SOFR plus 5.50% without; CoreWeave's unsecured notes pay 9.75% and its bonds yielded 16% in October. The difference is the absence of a buyer's contract.
Our debt is sized on capacity rent from a tenant whose own debt is priced on its contracts. Lease terms that let a property lender see through to those contracts are worth more to us than a point of rent.
Debt shares are typical structures by layer, drawn from the sources in this chapter; no single company is depicted. Costs as published in 2026. Leverage falls and the cost of money rises from the regulated grid to the venture-funded application.
| Layer | Who provides the money | What it costs, as published | What the lender lends on | What the lender will not lend on |
|---|---|---|---|---|
| 0 · Grid | Regulated utilities with infrastructure owners behind them: Engie (UKPN, £10.5bn equity value, May 2026), National Grid, Iberdrola, Berkshire Hathaway Energy, SSE. Reinforcement is funded by the DNO and recovered from all users | ED3 early view: cost of equity 6.08% CPIH-real at the midpoint (range 5.10% to 7.05%), notional gearing 60%, debt allowance c.5.50% rising to 6.19% nominal over 2028 to 2033; transaction premiums of c.50% to the asset base imply investors accept c.4.3% | The regulated asset base and the price control. The cheapest capital in the chain, by design | Anything outside the allowance: a customer's sole-use works are paid by the customer |
| 1 · Powered site | Property equity and property debt. In our structure, development debt at purchase, refinanced on the rent once the lease is signed, with debt sized on capacity rent alone and never on revenue share; three gates (the DNO's confirmation of the connection, the operator agreement, funding) before capital is committed | Term debt c.6% to 7% in 2026 sterling; prime UK data centre yields 5.5% to 6.5% (Savills, H1 2026); a US powered shell at a 5.0% cap rate against 6.5% for turnkey (Loudoun, 2026) | Firm rent from a creditworthy tenant on a long lease, the re-let value of the building, interest cover of 1.25x or more, loan-to-value of 50% to 60%, and a firm connection in writing | Revenue share, turnover top-ups, uncontracted capacity, a connection that is Indicated rather than Confirmed, or a tenant whose rent it cannot see through to a contract |
| 2 · Fitted hall | Infrastructure equity (Antin at Pulsant, I Squared at nLighten with more than $500m committed, Macquarie's 40% of Virtus, Infratil and L&G at Kao, Elliott at Ark with TPG in talks at c.$5bn, Brookfield's $10bn AI fund, BlackRock's £500m with Gravity Edge, L&G's new €600m digital fund, ICG's €3.15bn); bank clubs; securitisation; private credit | Virtus £2.45bn from thirteen banks led by BNP Paribas, Crédit Agricole, Société Générale and Standard Chartered, September 2026, with £1.2bn of green capex facilities; Yondr £532m of term notes against two Slough halls let to a hyperscaler, rated AA by Fitch, March 2026; Pulsant £187m over five years, October 2025; nLighten £85m led by Rivage, secured on nine UK sites of 10 MW rising to 20 MW, March 2026; Echelon €1.7bn from Morgan Stanley; Maincubes €1.8bn from twelve lenders; Segro and Pure publish a 9 to 10% net yield on cost | Contracted kW with hyperscalers and large enterprises, DSCR, loan-to-cost on development, the operator's track record, ESG criteria increasingly written into the margin | Speculative halls without pre-lets at scale; neocloud tenants without credit support, for which operators charge more rent instead |
| 3 · Compute | Venture and public equity (Nscale's c.£1.5bn Series C and IPO; Fluidstack's $750m; Nvidia's stakes); GPU-backed loans in bankruptcy-remote vehicles; vendor leases; unsecured bonds | One borrower's history shows the range. CoreWeave's first GPU loan in 2023 cost c.15%; its second in 2024 SOFR plus 6.00% (11.3%); its fourth in March 2026, $8.5bn against Meta's contracts, SOFR plus 2.25% floating or 5.9% fixed, rated A3; its fifth in May 2026, without that contract quality, SOFR plus 4.50% (8.0%, Ba2); its sixth SOFR plus 5.50% (10.4% to maturity); its unsecured notes 9.75%; its bonds above 16% in the week of 14 October. Elsewhere: Lambda SOFR plus 3.00% (6.6%, Baa2); Nebius SOFR plus 2.50% (6.1%); IREN's Microsoft-backed facility SOFR plus 2.25% (5.9%, rated A); Nscale's Ward County facility SOFR plus 2.375% (6.05%, Baa1) behind Nvidia's guarantee | Contracted cash flows from a named customer, ring-fenced in a special-purpose vehicle, with the chips as secondary collateral amortised over three to four years; a vendor or customer backstop where one exists | Spot or on-demand revenue; chips older than a generation; a borrower's corporate credit on its own; the same company borrowed at 5.9% and 10.4% in the same year |
| 4 · Buyer | Hyperscaler balance sheets and investment-grade bonds; neocloud contracts sit in operating costs, not capex, which is part of their appeal | Amazon, Microsoft, Alphabet and Meta guided c.$725bn of capital spending for 2026, up c.77% on 2025; Alphabet raised its range to $195bn to $205bn in July; Moody's puts the wider group at $785bn in 2026 and close to $1tn in 2027 | Their own shareholders and bondholders lend on cash flow from advertising, cloud and software; the AI spend is the use of funds, not the security | The buyers are the credit the rest of the chain borrows against; they borrow against nothing in it |
| 5 · Model and app | Venture and growth equity; little or no debt | Fireworks $1.5bn at $17.5bn; Baseten $1.5bn at c.$13bn; Together $800m at $8.3bn; the three at c.$1bn of annual revenue each; OpenAI and Anthropic in the tens of billions | Growth, not collateral | There is no debt at this layer; equity carries the risk |
Rules two and three meet at our lease. The property lender asks who our tenant's customer is, because the tenant's ability to pay rent in year eight depends on its contract book and its own lenders' patience. A lease that gives the landlord sight of the tenant's contracts, a deposit or guarantee where the covenant is thin, a short cure period and a clean re-let right is a lease a property lender will advance more against. The credit support behind the lease, set out in chapter 5, therefore matters to our layer even though we never fund a GPU.
| Instrument | Rate, as published | Who, when |
|---|---|---|
| Allowed cost of equity, distribution networks (CPIH-real, early view) | 6.08% | Ofgem ED3 methodology, 21 May 2026 |
| Allowed cost of debt, distribution networks (nominal, average 2028 to 2033) | 5.86% | Ofgem ED3, same |
| Implied cost of equity from UKPN and other network transactions | c.4.3% | Ofgem ED3 market-to-asset ratio analysis |
| Prime UK data centre yield | 5.5% to 6.5% | Savills Spotlight, H1 2026 |
| Powered shell and turnkey cap rates, Northern Virginia | 5.0% and 6.5% | Loudoun County guidelines, 2026 |
| Fully fitted development, net yield on cost | 9% to 10% | Segro and Pure, Park Royal |
| Data centre securitisation, UK, rated AA | coupon not published | Yondr, £532m, March 2026 |
| GPU loan with a hyperscaler contract, investment grade | SOFR + 2.25% (c.5.9%) | CoreWeave DDTL 4.0, March 2026; IREN–Microsoft facility |
| GPU loan with a chipmaker's guarantee | SOFR + 2.375% (c.6.05%), Baa1 | Nscale, Ward County, 2026 |
| GPU loan, sub-investment grade | SOFR + 4.50% to 5.50% (8.0% to 10.4%) | CoreWeave DDTL 5.0 and 6.0, 2026 |
| Neocloud unsecured notes | 9.75% coupon | CoreWeave, April 2026 |
| Neocloud bonds in a bad week | above 16% yield | CoreWeave 2031 notes, mid-October 2026 |
| First GPU loan ever made at scale | c.15% | CoreWeave, 2023 |
The grid borrows at about six because the regulator guarantees its revenue. A building borrows at six or seven because a lease is a contract and the building has another use. A fitted hall borrows at a little more because the fit-out has one use. The chips borrow at six when a hyperscaler has signed and at ten or sixteen when it has not. At every layer the rate falls when a buyer's commitment stands behind the cash flow.
The money that is old is also moving. Infrastructure funds that used to buy towers and fibre now buy halls: Antin, I Squared, Macquarie, Infratil, Brookfield, Elliott, and the new L&G and ICG funds. Their cost of capital sits between the property lender's and the venture fund's. Their appetite is for platforms of many sites, and a regional edge operator is one.
Thread B. The documents that carry a megawatt from the substation to the user: the connection agreement, the planning consent and the rules that come with it, the operator lease clause by clause, the credit support behind the lease, the power contract, and the data obligations that follow the tenant in. Chapter 8 of From power to answer.
Basis. Market study, not legal advice. Clauses are heads for discussion, drawn from published law-firm guidance and the Edge method's own lease checklist; the solicitors draft. Regulatory positions are as published to 31 October 2026 and several are still moving. Sources in section 8.9.
A connection agreement names a customer and a capacity. Bilateral terms now survive a change of occupier, and capacity cannot be cut without the customer's agreement. Keep the agreement in the building's name and let the tenant take the supply.
Data centres have no use class; a shed may already be lawful, an office is not. They can opt into the national regime since January 2026, are critical national infrastructure since 2024, and may in time be required to supply waste heat to a network.
Triple net, 10 to 15 years, rent per MW of firm supply, indexed. Landlord scope stops at the intake switchgear; tenant scope starts there. Yield-up is the most negotiated clause in the market. Under our form the tenant leaves the hall fit-out and removes the compute.
Two parties who do not sign the lease will read it closely: the bank that sizes debt on the rent, and the operator who takes the hall after this one. Draft with both in mind.
| Document | Parties | What it fixes | Where it goes wrong |
|---|---|---|---|
| Connection agreement and connection offer | DNO and the customer (owner or occupier) | The agreed supply in MVA, the point of supply, firm or non-firm, the sole-use works, milestones | Agreement in a departed occupier's name; capacity de-energised and reviewed; "firm" undefined |
| Planning permission and conditions | Local planning authority, or the Secretary of State under the national regime | The lawful use, hours, noise at the boundary, generators and fuel, heat rejection, landscaping | Use not lawful for compute; a noise condition the dry coolers cannot meet; a residential neighbour |
| Agreement for lease and fit-out guide | Landlord and tenant | What the landlord builds, what the tenant may install, the technical protocol, the long-stop | Scope creep across the intake; a long-stop the DNO cannot meet |
| Operator lease | Landlord, tenant, guarantor | Rent, term, scope, operations, alterations, assignment, default, yield-up (section 8.4) | Rent that is not rent; a yield-up that leaves the landlord a chiller |
| Credit support | Guarantor, off-taker or chipmaker, landlord, lender | Who pays if the tenant does not (section 8.5) | A guarantee of the wrong thing, for the wrong period, from an entity that can walk |
| Supply contract and metering | Tenant and electricity supplier; DNO for the MPAN | Who buys the power, at what price, through whose meter | Power through the landlord's books; a pass-through that turns into a trading business |
| Facility agreement and direct agreement | Landlord and property lender; tenant acknowledges | Debt sized on rent; lender's step-in and cure rights; no lease variation without consent | A lease the bank was not shown |
| Data and security schedule | Tenant with its customers; landlord for the building | UK GDPR and the 2025 Act, ISO 27001, breach procedure, who may enter | A landlord promising data obligations it cannot perform |
| Instrument | Position at October 2026 | For a 10 MW conversion |
|---|---|---|
| Use class | None. Authorities treat data centres as B8 storage, sui generis, or occasionally Class E; a parliamentary answer in 2026 says the class "will depend on the individual circumstances", and office to data centre "will generally" need permission. A London committee in February 2026 approved a data centre as B8 on a warehouse site; a change to or from sui generis always needs permission | A shed or print works may already be lawful; a call centre or office is not. Pre-application advice or a lawful development certificate per site, before exchange |
| National regime (NSIP) | Since 8 January 2026 a data centre may ask the Secretary of State for a section 35 direction to be consented nationally; no size threshold is set; a national policy statement is in preparation | Irrelevant at our size, but it tells councils what Whitehall wants |
| Critical National Infrastructure | Designated September 2024; "Critical National Priority" status for grid access under consideration in 2026 | A line in the planning statement and the tenant's sovereignty case |
| Planning and Infrastructure Act 2025 | Royal Assent 18 December 2025; the powers behind the strategic-demand prioritisation of chapter 1 | Watch for the distribution-level process |
| Noise | Conditions set separately for commercial and residential receivers; dry coolers are the loudest plant and run at about 87 dB close to; acoustic reports are standard | Screen for residential neighbours before buying; put the yard on the far side |
| Heat network zoning | England's zoning regime names data centres as heat sources; no duty to supply yet, but the regulations "expressly envisage" one; government is "looking at how waste heat from data centres can be used" | A future obligation on the tenant's cooling; reserve the right to connect in the lease |
| Business rates | 2026 list from 1 April 2026: data centre rateable values up 16% in London and 22% in the South East (Knight Frank); a new multiplier of 50.8p for values above £500,000, which covers about 90% of data centres; the VOA values modern facilities on a "rentals plus" basis | The tenant's cost under a triple-net lease; a 10 MW site will cross the £500,000 line |
| Fire and batteries | Building Safety Act 2022 governs; lithium UPS batteries bring thermal-runaway risk; UK practice borrows the US standard NFPA 855 (separate battery rooms above 600 kWh) | Tenant's fit-out; the lease should require compliance with a named standard |
| Energy performance | MEES applies to non-domestic lettings; data centre halls are often argued out of EPC scope; the position varies | Check the EPC position per building before marketing |
Heads for a powered-shell operator lease, drawn from the Edge method's lease checklist, Hogan Lovells' note on UK data centre leases (30 September 2025), BCLP's note on shell-and-core structures (23 October 2025) and Gowling WLG's note on colocation agreements (16 April 2025). Teal markers are the clauses the landlord should lead; grey the ones the tenant will. Solicitors draft; this is the commercial brief.
BCLP reports that leases are "almost always triple net", that deposits of six to twelve months' rent and parent guarantees are typical for smaller tenants, and that the yield-up clause is "one of the most heavily negotiated", with most developers requiring tenants to strip the fit-out back to shell. Our position on yield-up is the reverse. The hall fit-out is what the next operator wants, so the tenant leaves it and removes the compute. Hogan Lovells says the lease must state who maintains the "core infrastructure, such as power and cooling systems". In a fitted hall that is the landlord; in our shell it is the tenant, and the lease must say so without ambiguity because the lender's engineer will read it. Gowling WLG notes that the operator "does not own, provide or manage" the customer's equipment, and that the agreement must give the operator rights if equipment is not removed at the end. The same right belongs in our lease against the tenant's compute.
| Instrument | What it does | Precedent | Our ask |
|---|---|---|---|
| Rent deposit | Cash held against arrears; six to twelve months typical for smaller tenants | BCLP, UK market | Only where a covenant needs support; substantial tenants are not asked for a fixed deposit |
| Parent company guarantee | The tenant's parent stands behind the lease | Standard | Always, where the tenant is a site company |
| Rent guarantee from a third party | A chipmaker or off-taker guarantees the rent for a period | Nvidia guaranteed up to $860m of Nscale's rent to its Texas landlord for $60m of warrants (chapter 5) | Ask every bidder; decide beforehand what we give |
| Assume-or-pay backstop | On tenant default, the off-taker pays the termination fee or takes the lease | Google at TeraWulf and Cipher | The preferred form: it gives the building a second tenant on day one |
| Residual value guarantee | A floor on the asset's value at the end rather than every payment along the way | Emerging in the US, per Vinson & Elkins | Acceptable for a lender; weaker for us than assume-or-pay |
| Direct agreement | Lender's right to notice and to cure the tenant's default; tenant's acknowledgment | Standard in financed leases | Required by any lender; draft it at the start |
This chapter draws the eight before it into one set of conclusions: where we sit on the chain, what we need from the layers around us, who we lease to and what we ask of them, what we offer in return, and what we do in the next ninety days. Chapter 9 of From power to answer.
Basis. Everything here rests on the evidence in chapters 1 to 8. Market study, no returns. For discussion between the partners.
We own the building and the connection and lease them per MW of firm supply. Our scope ends at the intake switchgear. Above it the cost of capital doubles and the asset wears out in three years; below it, at the grid, the revenue is guaranteed by the state.
We do not sell proximity to London. Latency puts the compute in Britain; sovereignty and grid access decide where in Britain. A 10 MW building with its supply in hand sits outside every queue, fee and milestone the regulator has written since 2025.
The tenant is a neocloud or a regional colocation operator; the credit is its customer. We underwrite the contract book, ask what its GPU debt costs, and ask who stands behind the lease.
Neither signs the lease, but both read it: the lender sizes debt on the rent, and the next operator takes the hall after this one. Yield-up leaves the hall in place; power never passes through our books; the connection stays with the building.
| Chapter | What it found | What follows for us |
|---|---|---|
| 1 · Grid | The demand queue stood at 96 GW at transmission and 29 GW at distribution by June 2025; 11 to 13 GW can connect before 2030. Every reform since bites on large, new, speculative applications and none on a building that already holds its supply. 1,029 primaries publish 10 MW spare today; UKPN holds 251 of them | Buy a building with an agreed connection, not one with an application pending. Confirm the agreed supply, the point of supply and survival on change of occupier in writing before exchange. Kent and London are the right DNO |
| 2 · Powered site | The market prices a connection at c.£0.7m to £1.2m per grid MW in the London hub. The listed landlords are moving up to fitted halls at 50 MW+; the exchange owner sells to housebuilders; nobody does 5 to 15 MW in existing buildings at scale. Our rent is c.43% of a fitted London rate for a quarter of the capital | Buy at building prices and lease at power prices. Say whether a megawatt is grid or IT load. Open talks with TT Group on exchanges with real MVA. Put the land premium per MW on every appraisal |
| 3 · Fitted hall | Of a c.£9m London hall the landlord's share is £0.5m to £1.3m; the lessee's is £4m to £9m before a chip. Racks went from 16 to 27 kW in a year and AI racks run 120 to 230 kW; liquid cooling makes the building matter less and the yard matter more. Regional operators are consolidating with fresh debt | Define our scope as ending at the intake switchgear, in plant terms, in a schedule to the lease. Design for the yard and the slab. Ask PUE and density first. Pitch the regional operators in their own numbers |
| 4 · Compute | A megawatt of chips costs c.£26m and must earn it back in three to six years while the hourly price swings by a factor of four. Money follows the contract; loans fall due in 2026 to 2028 before contracts pay out. No neocloud bankruptcy yet, but Gartner expects most to lose independence by 2030. Nscale's own prospectus sets out the layer's risks | Underwrite the contract book, not the brand. Prefer tenants whose debt or customer is investment grade. Deposit or guarantee through the refinancing window. Write the re-let right for a chip-owner's exit |
| 5 · Capacity sale | Five buyers hold most of the take-or-pay value; the state is a real buyer in Britain. Marketplaces trade hours, not megawatts. Google backstops Fluidstack's leases for warrants; Nvidia guarantees $860m of Nscale's rent for $60m of warrants and rents back unused capacity. Europe has none of this and charges neoclouds more rent instead | Ask in the first meeting who stands behind the lease. Decide beforehand what we offer in return. Keep the rent unchanged and take the guarantee. A named off-taker is worth more than a well-known tenant |
| 6 · Model, app and user | Half the country and a third of firms use AI; the labs have moved to London; the NHS, finance and government buy as if an onshore rule existed, and none does yet. From Kent, 59% of Britain's urban population is within 2 ms and 92% within 4 ms. Tokens got 600 times cheaper and volumes rose faster | Sell the building as compute in Britain, with power, available this decade. Name latency only to the metro-latency tenants. Sovereignty and Kent's coastal position are features we can offer as landlord. Token deflation is the tenant's risk, not ours |
| 7 · Money | The cost of money rises with every layer: 6% at the grid, 5 to 7% against rent, 6% to 16% for chips depending on whether a hyperscaler has signed. Property lenders lend on rent and re-let value; GPU lenders lend on contracts. Hyperscaler capex is c.$725bn in 2026 and heading for a trillion | Stay at the building's cost of capital. Size debt on rent only. Write the lease so a property lender can size debt on it. Ask bidders what their GPU debt costs. Watch for the first UK powered-shell securitisation |
| 8 · Paper | Bilateral connection terms now survive a change of occupier and capacity cannot be cut without consent; data centres have no use class and get consented case by case; the market's yield-up strips the hall and ours keeps it; deposits of six to twelve months are typical for small tenants; the data duties belong to the tenant | Seven rules: the connection stays with the building; planning per site before exchange; rent only, no revenue share; scope ends at the intake; yield-up leaves the hall; credit support in a schedule; power never on our books |
The list of 31 October stands, re-ordered on credit and with one addition. The first five remain the first five calls; only their order has changed.
| Rank | Who | Why, after the study | The one question for them |
|---|---|---|---|
| 1 | Nscale, with BT | The strongest demand in Britain and the clearest need for power this decade: $103bn of conditional contracts, a flagship site delayed to the 2030s, an anchor tenant lost in October. The Nvidia rent guarantee at its Texas site is the precedent we would ask for. Through the BT partnership it is the natural operator for the exchange channel | Will Nvidia or Microsoft guarantee the rent on a UK site the way they did at Ward County? |
| 2 | Civo | Still the closest match in size and thesis: 40 sites at c.8 MW for sovereign inference, build-or-lease unstated. Second rather than first because its 1 GW programme has no disclosed financing; a backstop or a partner would move it back up | Who funds the 40 sites, and will they stand behind a lease? |
| 3 | Radiant (Ori) | New to the top five. Brookfield's $10bn AI fund behind a UK operator, Nvidia in the fund, sovereign and enterprise contracts as the model. The kind of covenant chapters 4 and 7 point to | Would Radiant take a UK shell rather than a Kao hall, and on what term? |
| 4 | Pulsant | Buys sites of our size with a £187m facility; retrofitting for density; Antin behind it. The colocation route: better covenant, more re-lettable hall, lower rent appetite | What does a 10 MW shell at £750k a MW do to their hall economics? |
| 5 | nLighten | I Squared's $500m and an £85m private-credit facility secured on nine UK sites of 10 MW rising to 20 MW: a lender has already priced our asset class for them | Would their lenders extend the ring-fence to a leased shell? |
| 6 | Latos | A 40-site model that needs sites; funding to be tested before a lease | Who are the investors? |
| 7 | Nebius | £1.7bn in Britain, hyperscaler contracts, but a fitted-hall habit at 22 MW+ | Is there a shell in the 65 MW? |
| 8 | Gravity Edge (BlackRock) | The closest strategy to ours, one layer up, with £500m. Partner or competitor; worth knowing which | Would they fit out a Yeats shell rather than buy a hall? |
| 9 | TT Group | Not a tenant; the counterparty for 4,600 exchanges with power and fibre that it has so far sold for housing | Which exited exchanges hold more than 2 MVA? |
| 10 | Microsoft, Google, the AIRR prime | Not tenants; the credit behind them and the demand our tenants sell into | Which neocloud carries your UK sovereign work, and would you stand behind its lease? |
CoreWeave, Fluidstack, Lambda, Yondr, Ark and the London campus operators remain references, not targets, for the reasons in chapters 3 and 4.
| # | Question | Chapter | Why it decides |
|---|---|---|---|
| 1 | Who is your end customer for this capacity, and will they, or your chipmaker, stand behind the lease? | 5 | Identifies the credit support behind the lease, which decides what debt the building carries |
| 2 | What is your contracted value, your largest customer's share, and how much is conditional on delivery? | 4 | Nscale disclosed all three; we hold a private bidder to the same |
| 3 | What does your GPU debt cost, and who lent it? | 7 | SOFR plus 2.25% has a hyperscaler behind it; plus 5.50% does not |
| 4 | What density and cooling do you run, and what do you need at the intake? | 3 | Fixes where our scope ends; liquid cooling changes nothing outside the intake |
| 5 | What PUE do you design to? | 3 | Decides how much IT load our megawatt carries, and what our rent is worth to them per kW |
| 6 | When must the power be energised, and what does a six-month delay cost you? | 1 | Tests the premium on a connection in hand |
| 7 | Whole 10 MW or phased, and at what binding minimum? | 8 | Phasing shifts vacancy to us unless the dates bind |
| 8 | How many UK sites in three years, and who finds them? | 2 | Turns a letting into a pipeline |
| 9 | What leaves with you at the end, and what stays? | 8 | Our yield-up keeps the hall in place; raise it early |
| 10 | Who else have you leased from, and may we speak to them? | 4 | Conduct and covenant |
The American landlords paid for their backstops in warrants. We have no listed equity. Three options remain, and we recommend trying them in this order.
Each of these needs a conversation rather than further desk research.
Chapters 0 to 8 of this study, each with its own source list; the operator and broker target list of 31 October 2026; the Edge method and its lease checklist.
One card per player. Eight deep cards cover the study's eight questions; the rest are short. UK only, with the American and European names that explain a structure. Facts as published to 31 October 2026, sterling in brackets at £1 = $1.33.
Basis. Market study, no returns. Ownership and figures are from company announcements, filings and trade press cited in the chapters; where a fact could not be confirmed the card says so. Nobody on these cards has been approached.
| What it is | The distribution network operator for London, the South East and the East of England: three of the fourteen licences, c.8.3m homes and businesses |
|---|---|
| What it is, as a company | Owned by Engie since 7 May 2026, bought from CK Infrastructure, Power Assets and CK Asset at a £10.5bn equity value, a premium of c.50% to the regulated asset base |
| What it does | Connects, reinforces and operates the network under Ofgem's RIIO-ED2 price control (to March 2028) and the ED3 methodology now being set |
| Who runs it | Engie, an energy group rather than a financial holder; a director has said data centres on its network draw only 30 to 40% of their agreed capacity |
| How it makes money | Allowed revenue on the asset base; ED3 early view 6.08% real cost of equity at 60% gearing; reinforcement for demand funded by the DNO and recovered from all users |
| Why now | 125 GW of demand offers in seven months; new 5 MVA application rules from 1 June 2026; Ofgem's Curate, Plan and Connect reforms |
| What it means for us | Our DNO holds 251 of the 1,029 primaries with 10 MW spare and 178 of the 536 that hold to 2030. Its written confirmation of spare capacity is the first gate. Chapter 1 |
| What it is | FTSE 100 industrial REIT; owner of the Slough Trading Estate, Europe's largest data centre hub |
|---|---|
| What it holds | A power bank of 3.0 GVA across European availability zones (July 2026), 1.4 GVA of it to lease within seven years |
| What it does | Pivoting from powered shells to fully fitted halls in joint ventures with Pure DC: Park Royal (56 MW IT, c.£1bn, 70 MVA, ready 2029) and Paris. Still signs shells where asked: Slough, 50 MVA, pre-let March 2026 with the customer contracting power directly |
| Who runs it | A listed board; development capex guided at £450m to £550m for 2026 |
| How it makes money | Rent and development profit; publishes a 9 to 10% net yield on cost for the fitted scheme |
| Why now | Hyperscaler and neocloud demand; its own land with power |
| What it means for us | The reference landlord; moving up the stack and starting at 50 MVA. Its Slough structure (landlord holds the connection, tenant contracts the power) is the one we would use. Chapter 2 |
| What it is | UK campus operator; Harlow, Stockport (40 MW consented), Manchester (£350m, due 2026) |
|---|---|
| What it is, as a company | Infratil 53%, Legal & General Capital 32%, Goldacre NOÉ 15% (2023 split) |
| What it does | Builds and operates fitted halls; the landlord of choice for neoclouds in Britain: Nebius (22 MW, ten years), Ori, Civo |
| Who runs it | Infrastructure owners; chaired from Goldacre |
| How it makes money | £ per kW a month on fitted capacity |
| Why now | Neocloud take-up of European capacity rose from 133 MW to 414 MW in a year |
| What it means for us | Will not lease a Kent shell; knows every tenant on our list and what they pay. Chapter 3 |
| What it is | Regional edge operator, 14 UK sites (platformEDGE) |
|---|---|
| What it is, as a company | Antin Infrastructure Partners since 2021; revenue c.£126m and EBITDA c.£24m per a data vendor, year unstated; £187m five-year facilities refreshed October 2025 |
| What it does | Colocation to enterprises and the public sector; bought two SCC sites (Birmingham c.2 MW, Fareham c.3 MW) in 2025; 1.2 MW AI-ready hall at Milton Keynes and £1m into Birmingham for inference in 2026 |
| Who runs it | Infrastructure-fund ownership; customer racks up from c.4 kW to 10 to 20 kW |
| How it makes money | Retail and wholesale colocation; small AI-ready increments |
| Why now | Density is forcing refits; fresh debt for acquisitions |
| What it means for us | Buys sites of our size; the colocation route to a better covenant. Fourth call. Chapters 3 and 9 |
| What it is | UK neocloud founded 2024; Nvidia holds over 5%; S-1 filed 18 September 2026 for a NYSE listing |
|---|---|
| What it is, as a company | H1 2026 revenue $140.6m (c.£106m), net loss $1.02bn (c.£770m, $457m of it currency); $103.4bn of active and contracted value over c.461,000 GPUs; Microsoft up to $43.8bn and Anthropic up to $44.6bn, conditional on delivery; largest customer 52% of revenue; "has not yet obtained binding commitments for the financing" those contracts need |
| What it does | Owns and operates AI data centres; Loughton (50 to 90 MW) grid-delayed to the 2030s and lost Microsoft as anchor on 18 October 2026; three BT sites, 14 MW; Stargate UK with OpenAI; US site at Ward County, Texas, with a $860m Nvidia rent guarantee |
| Who runs it | A founder-led team with Nvidia, Microsoft and OpenAI relationships; c.£1.5bn Series C at c.£11bn |
| How it makes money | Take-or-pay contracts with hyperscalers and labs; sovereign pitch via BT |
| Why now | Contracts far ahead of financed, powered capacity |
| What it means for us | First call. It needs power this decade, and in Texas its chipmaker has guaranteed its rent. Chapters 4, 5 and 9 |
| What it is | Stevenage cloud provider founded 2015; hosted at Kao today |
|---|---|
| What it is, as a company | Founder-led; THG took a minority stake (c.£1.4m) in 2021; no venture round or project financing found |
| What it does | 40 UK edge sites planned at c.8 MW each for sovereign inference, c.1 GW combined; first site Hertfordshire (8 MW rising to 38); five more sites of 150 MW secured in Lancashire, Greater Manchester, London and Oxfordshire; Vera Rubin-ready, liquid cooled; build-or-lease not stated |
| Who runs it | Its founders |
| How it makes money | Cloud and GPU services sold on UK-owned, UK-incorporated sovereignty |
| Why now | "Inference at the edge rather than training overseas" |
| What it means for us | Closest to us in size and thesis; the weakest public balance sheet on the list. Second call, moving to first if a backstop or partner appears. Chapters 4 and 9 |
| What it is | Amsterdam-headquartered, Nasdaq-listed neocloud |
|---|---|
| What it is, as a company | Microsoft ($17.4bn to $19.4bn, New Jersey) and Meta (c.$27bn) contracts; borrows at SOFR plus 2.50% |
| What it does | £1.7bn UK programme (8 June 2026): 22 MW at Kao Harlow on ten years hosting its cloud and the Token Factory inference service; three UK clusters reported at 65 MW by 2027; also at Ark Longcross |
| Who runs it | A listed board; a Lepton partner |
| How it makes money | Take-or-pay and on-demand GPU capacity; inference by the token |
| Why now | UK sovereignty demand and the government's action plan |
| What it means for us | Best-funded fitted-hall tenant in Britain; takes halls, not shells. Second pass. Chapters 4 and 9 |
| What it is | The largest buyer of neocloud capacity in the world and the credit behind Nscale, Nebius, IREN and Lambda |
|---|---|
| What it is, as a company | c.$60bn (c.£45bn) of neocloud contracts booked as operating cost; 2026 capex guided at c.$190bn |
| What it does in Britain | Own regions; a supercomputer building with Nscale in its UK plans; left Nscale's Loughton site on 18 October 2026 for want of power while remaining Nscale's largest customer; designated a critical third party to UK finance from 13 July 2026 |
| Who runs it | n/a |
| How it makes money | Cloud, software, advertising; AI capacity is a use of funds |
| Why now | Capacity scarcity; it buys from anyone who can energise |
| What it means for us | Not a 10 MW tenant. The credit support to ask for behind one. Chapters 5 and 9 |
| Who | What | Read for us |
|---|---|---|
| NESO | National Energy System Operator, public since October 2024; runs the transmission queue; 96 GW of demand at June 2025; 11 to 13 GW connectable before 2030; to be directed by government on strategic demand | Not our counterparty at 10 MW unless the grid supply point binds |
| National Grid Electricity Distribution | Midlands, South Wales, South West; c.8m customers; National Grid plc since 2021 (£7.8bn) | Most industrial floorspace; no 2030 forecast in its published data |
| SSEN Distribution | Southern England and North Scotland; SSE plc; c.3.1m southern customers | Borders UKPN's South East; no 2030 forecast |
| Northern Powergrid | North East and Yorkshire; Berkshire Hathaway Energy; 3.9m customers | Yorkshire second for primaries with 10 MW spare |
| SP Energy Networks | Central Scotland and Merseyside, Cheshire, North Wales; Iberdrola; c.3.5m customers (Indicated) | Most spare capacity in Britain, least demand near it |
| Electricity North West | North West; Iberdrola 88% since 2025 (£2.1bn), Kansai-led 12%; c.2.4m connections | Same owner as SPEN |
| Ofgem | Regulator; ED3 methodology decided 21 May 2026; Curate consultation closed 16 September 2026 with a decision due by year end | Its 40 MW fee threshold sits above our size |
| Who | What | Read for us |
|---|---|---|
| Tritax Big Box | Manor Farm, Heathrow: 74 acres for an initial £70m plus 21% of phase-one profit; 107 MW (147 with phase two) consented after judicial review; powered shell subject to pre-let; 50% joint venture with an unnamed generator for two substation connections | What a listed landlord pays for powered land and needs before it builds |
| Harworth Group | Pure-play powered land; Skelton Grange, Leeds, two plots to Microsoft for £106m; c.0.8 GW of further connections; up to six hyperscale sites; second-site exclusivity August 2026 | The purest powered-land seller; buyers are hyperscalers |
| TT Group (Telereal Trillium) | Bought c.6,700 BT properties in 2001 for £2.38bn; owns nearly all c.5,600 Openreach exchanges, c.4,600 closing from 2025 into the early 2030s; main lease to 2031; exited buildings sold for housing; pilot exits slipped to November 2026 | The exchange counterparty; open the conversation on exchanges with real MVA |
| BT Group and Openreach | Leaves 4,600 exchanges, keeps c.1,000; Nscale partner on three sites, 14 MW; AI-RAN trials on EE's live network in Birmingham | A FTSE counterparty on any exchange site |
| Stellanor (DWS) | Eight Redcentric data centres, EV up to £127m, completed May 2026; £3.1m to £5.5m per MW derived | A UK price for small sites with power |
| The US miners | TeraWulf, Cipher, Applied Digital, Core Scientific: powered sites leased turnkey to neoclouds at c.$1.5m to $2.3m per MW a year, fit-out $8m to $10m per MW, Google backstops behind Fluidstack | Precedent, not UK fact |
| Cogent and I Squared | Converted Sprint switch sites asked at $10m to $17m per MW; ten sold to I Squared for $225m, $4.25m per MW, for an inference platform | US precedent for exchange conversion, four years ahead of the UK |
| Who | What | Read for us |
|---|---|---|
| Ark Data Centres | Elliott-owned; TPG reported in talks at c.$5bn (c.£3.8bn), late October 2026; 27 facilities; Crown Hosting joint venture with the Cabinet Office; £807m Longcross expansion for Nebius | The public-sector channel; a sale would set a new price for UK halls |
| nLighten | I Squared's European edge platform with more than $500m committed; owns Proximity (ten UK sites); £100m UK programme; £85m Rivage-led facility secured on nine sites of 10 MW rising to 20 MW; Bristol refit | Fifth call; a lender has priced our asset class for them |
| Latos Data Centres | Founder-led; Cardiff, three buildings, 90 MVA, under construction; Stockton £100m approved; 40 sites by 2030; investors not disclosed | Sixth; funding to be tested |
| Datum Datacentres | Farnborough and Manchester; 1 MW halls; ownership not confirmed online | Too small alone |
| Yondr | Slough 100 MW campus; £532m green securitisation rated AA, March 2026 | Shows the bond market lends on let halls |
| Virtus | ST Telemedia with Macquarie at 40%; 18 UK sites, 300 MW+; £2.45bn from thirteen banks, September 2026 | Largest UK operator; builds its own |
| Green Mountain | Azrieli; LON-East, Romford; a neocloud took 14 MW in September 2026 | Demand proof at our size |
| Gravity Edge | BlackRock and DGP; Camberley to 20 MW; 5 to 20 MW sites with under-used capacity; £500m committed | Closest strategy to ours, one layer up |
| Equinix, Digital Realty, Global Switch, Telehouse, Vantage | The London campus operators; CoreWeave's UK landlords; Global Switch's owners have tried to sell since 2021; Vantage 223 MW in the UK | References for turnkey rent, not tenants |
| Who | What | Read for us |
|---|---|---|
| Radiant (Ori) | Brookfield's AI cloud unit, formed with UK neocloud Ori in February 2026 at a reported $1.3bn; part of a $10bn Brookfield fund with Nvidia among backers; Ori's first UK region at Kao; sovereign, enterprise and telecom contracts on Nvidia's DSX design | Third call; the covenant quality the funding case needs |
| CoreWeave UK | Docklands, Crawley, DataVita in Scotland; c.£2.5bn UK commitment; leases rather than builds; c.$50bn of debt, bonds above 16% in mid-October, $104bn backlog, Nvidia commitment to April 2032 | The bellwether; watch its cost of capital |
| Fluidstack | Headquarters moved to New York, December 2025; left a €10bn French project; $750m at $7bn; Google-backstopped US leases | Structure reference only |
| Lambda | $926m term loan rated Baa2 at SOFR plus 3.00%, September 2026; $1.5bn Nvidia lease-back; no UK site found | GPU debt going mainstream |
| DataVita | Lanarkshire AI Growth Zone, up to 500 MW; $406m financing, August 2026; CoreWeave's Scottish host | The Growth Zone model; too big and too far |
| Isambard-AI and the AIRR | 5,444 H100s at Bristol; twenty-fold expansion by 2030 under a £1bn roadmap; £500m Sovereign AI Unit; c.£250m cloud-compute contract tendered | Demand for our tenants, not a tenant |
| Who | What | Read for us |
|---|---|---|
| £5bn UK programme; backstops Fluidstack's leases at TeraWulf ($1.8bn rising to $3.2bn), Cipher ($1.4bn) and a Texas joint venture ($1.3bn) for warrants | Originator of the lease-backstop structure we want | |
| OpenAI | $22.4bn with CoreWeave in 2025; Stargate UK with Nscale, reported paused; first permanent London office for 544 staff | UK plans depend on Nscale delivering power |
| Anthropic | Nscale up to $44.6bn conditional; CoreWeave multi-year; London office for c.800 | Same dependency |
| Meta | CoreWeave $14.2bn plus a reported $21bn; Nebius c.$27bn | Sets the scale of one take-or-pay |
| Nvidia | Equity in CoreWeave, Nebius, Nscale; rents back unused capacity from 1 July 2026; guarantees up to $860m of Nscale's rent at Ward County for $60m of warrants | The chipmaker as guarantor |
| SF Compute | Market for H100 and H200 clusters by the hour; $40m at $300m; c.10% fee; resale recovers c.25% | Trades hours, not megawatts |
| Nvidia DGX Cloud Lepton | Marketplace routing developers to partner clouds including Nscale, Nebius, Fluidstack, Scaleway, Mistral; no rate card | A channel our tenant's cluster can sell through |
| Vast.ai, Shadeform | Peer-to-peer market at c.$2.13 an hour; aggregator across twenty clouds at no buyer fee | The price floor; the easiest way to buy hours |
| Together AI, Fireworks, Baseten | Inference platforms at c.$1bn of annual revenue each; rent capacity and sell tokens | Wholesale buyers of our tenant's hours |
| Crown Commercial Service, Crown Hosting, the AIRR prime, the MoD | G-Cloud 15 live from 6 August 2026; Crown Hosting awards; a c.£250m research-compute prime; the MoD's £180m framework with an edge compute lot | The state as buyer; our tenants' route to it |
| Who | Role |
|---|---|
| CBRE, JLL | Retained-agent candidates on a cluster; CBRE writes the UK and European outlooks used throughout |
| Cushman & Wakefield, Knight Frank, Savills, Avison Young | Market soundings; Savills' H1 2026 Spotlight and Knight Frank's rates note are cited |
| DC Byte, datacenterHawk, Structure Research, DCD | Who is leasing what, where, at what MW |
| BCLP, Hogan Lovells, Gowling WLG, Ashurst | The names on UK shell-and-core, lease and colocation guidance |
From power to answer · bound edition · draft of 31 Oct 2026 · For discussion. Each chapter keeps its own source list.