Yeats Edge · From power to answer · The UK chain, bound edition · 31 Oct 2026 · Draft, for discussion
From power to answer · the UK chain · draft, for discussion
Download PDF
Yeats Edge · A study of the UK chain, from grid to user

From power to answer

How a British building with spare power becomes a paid AI request: who does each job between the two, how they make money, who stands behind whom, and where we sit.

Draft of 31 October 2026 · For discussion · Market study, no returns · Figures as published, sterling at October 2026 rates · Download the PDF to read offline

THE CHAIN, WITH OUR POSITION MARKED · WHAT WE NEED FROM EACH LAYERLAYER 0GridWrittenconfirmation: agreedMVA, firm, point ofsupply, surviving achange of occupierLAYER 1Powered siteOur position. Buy atbuilding prices;scope ends at theintake switchgear;debt sized on rentonlyLAYER 2Fitted hallA tenant that fitsout and sells kW;PUE and densitydeclared; fit-outstays at the endLAYER 3ComputeA tenant whosecontracts we cansee; the cost of itsGPU debt shows itscreditLAYER 4Capacity saleThe credit supportbehind the lease:who stands behindit, and in what formLAYER 5Model and appSovereignty wordingin the pack; latencycited only for thetenants it matterstoLAYER 6UserIn Britain, withpower, this decadeRead left to right: the DNO's confirmation, our building, the tenant, the tenant's customer, the user. Our position does not change; the rest is what we ask of each layer.
THE STUDY IN EIGHT NUMBERS1,029primary substations with 10 MWspare today; 536 hold to 203011 to 13 GWof demand can connect before 2030,against 125 GW asked£0.7m to £1.2mthe market's price for one grid MWin the London hub43%our rent against a fitted Londonhall, for a quarter of the capital£26mof chips in a megawatt; three tosix years of life5.9% or 16%a neocloud's cost of debt, with orwithout a hyperscaler's signature59%of urban Britain within 2 ms oneway of a Kent site$725bnthe four big buyers' capitalspending in 2026

ContentsTen chapters and the cards

Chapter 0

From power to answer

How a British building with spare power becomes a paid AI request, who does each job between the two, how they make money, and where we sit. Chapter zero maps the chain and sets out how the rest will be researched.

In shortWe sell power and a building. Our tenant sells the compute.
7
layers from substation to screen
2
threads: money and paper
8
questions asked of every layer
1
seat, and it never moves

For discussion. This is a market study, not a model. It carries no returns. Rent, where it appears, is £750k per MW of firm supply a year. Every figure is labelled by source and, where a third party quoted dollars or euros, converted to sterling at October 2026 rates. Nothing here has been shared outside the partners.

The chain, in shortSeven layers, two threads, our position

Seven layers
Grid to user

Firm power at a substation becomes a powered site, a fitted hall, a rack of compute, a sold contract, a model behind an API, and finally an answer on someone's screen.

Two threads
Money and paper

Who finances each layer and at what cost, and which contract hands the asset to the next layer. Both run the full length of the chain and get their own chapters.

Our position
Layer 1

We own the building and the connection and lease it to a layer 2 or layer 3 operator. We do not own the compute. Layers 3 to 6 matter to us in so far as they decide whether our tenant is still paying rent in year eight.

The gap in the UK
5 to 15 MW, now

Hyperscale campuses run at 50 MW and up and wait years for grid. Sovereign and edge inference runs at 5 to 15 MW a site and wants power this decade. That band is where our buildings fit.

0.1 · The mapFrom a substation to a screen

Read left to right. Each box is a layer with its own owners and its own economics. The label on each arrow is the contract that moves the asset to the next layer. The two bands beneath are the money and paper threads, which run the length of the chain.

LAYER 0 Grid Firm capacity at a primary substation DNOs · NESO LAYER 1 · US Powered site Building + confirmed MW Yeats Edge LAYER 2 Fitted hall Cooling, UPS, generators, racks, fibre Colo operators LAYER 3 Compute GPUs, network, software stack Neoclouds LAYER 4 Capacity sale Off-take deals, marketplaces, direct sales Hyperscalers LAYER 5 Model + app The model, the API, the product Labs · platforms LAYER 6 User A request that needs an answer now UK people, firms connectionagreement operatorlease colocontract reservedcapacity take-or-payor GPU-hour API tokens,subscriptions THE CONTRACT THAT MOVES IT ON UNIT OF SALE MVA agreed £ per MW a year £ per kW a month £ per GPU-hour £ per cluster-year £ per million tokens £ per seat WHAT BREAKS HERE Reinforcement, queue Capacity lost on change Density outruns cooling GPU obsolescence Spot price collapse Model gets cheaper Latency THREAD A · MONEY DNO charges → property debt sized on rent → fit-out capex → GPU-backed loans → hyperscaler take-or-pay → venture and revenue → the user's card THREAD B · PAPER Connection offer → planning, Ofgem thresholds → lease: refresh, re-let rights → backstop or guarantee → sovereignty, procurement rules → terms of service The chain for one UK site. Layers 2 and 3 are often the same company when a neocloud fits out its own hall. Our tenant is layer 2 or layer 3; the credit behind our tenant usually sits in layer 4.
#LayerWho holds it in the UK todayWhere the money comes fromWhat goes wrong
0GridUK Power Networks and the other DNOs; NESO for transmissionRegulated revenue; connection charges paid by the applicantReinforcement cost and queue time; capacity oversubscribed; agreed supply lost when an occupier leaves
1Powered siteYeats Edge; Segro-type developers; Telereal's exchange estate; owners of ex-industrial supplyProperty equity and debt sized on rentPower priced into the purchase; tenant default; fallback use lost
2Fitted hallKao, Ark, Pulsant, nLighten, Latos, Datum, Yondr, the London campus operatorsInfrastructure equity, project debt, green bondsDensity outruns cooling; fit-out stranded by a tenant's exit
3ComputeNscale, Civo, Nebius, CoreWeave, Ori, the hyperscalers' own clustersVenture equity, GPU-backed debt, vendor finance, Nvidia itselfGPUs lose value in three to five years; a lab walks away; power never arrives
4Capacity saleMicrosoft, Google, OpenAI, Anthropic, Meta as buyers; SF Compute and Nvidia Lepton as markets; BT and Crown Hosting as channelsHyperscaler balance sheets; take-or-pay contracts; marketplace feesSpot GPU prices fall; off-taker renegotiates; concentration in one buyer
5Model and appLabs and API platforms; UK AI firms; enterprises; the public sector via G-CloudVenture, subscriptions, enterprise contracts, public procurementInference gets cheaper per token faster than demand grows
6UserPeople and firms in the UK who need an answer in under a few hundred millisecondsTheir own spendThey do not care where the compute is, unless it is slow or abroad

Holders named are examples from public sources, to be verified in the chapters. The highlighted row is our position.

0.2 · The questionsEight questions, asked of every layer

Each chapter answers the same eight questions in the same order, so layers can be compared like for like. The answers to the last question are collected in chapter 9.

#QuestionWhat it produces
1What is it?The asset and the unit it is sold in
2Who are the UK players?A named list, tiered
3What are they?Ownership, scale, funding, age
4What do they do?The service and the customer
5Who runs them?Background of the leadership, by role not name
6How do they make money?Pricing, margins, capital intensity, where debt sits
7Why now?The force pushing them: power scarcity, sovereignty, latency, cheap or dear capital
8What does it mean for us?One paragraph: a tenant, a risk, a term to ask for, or a thing to avoid

0.3 · The chaptersNine chapters and an appendix of cards

ChTitleBriefThe visual
0The mapThis documentThe chain infographic above
1GridHow UK distribution capacity is allocated, who the DNOs are, what the queue and the 2030 forecasts mean, Ofgem's thresholds, where power is actually spareGB map of spare capacity at 5 and 10 MW, from power.yeats.com
2Powered siteWho else owns buildings with power: Segro, Telereal, industrial landlords, the US miner precedent; what a powered shell lets for; how our position comparesRent stack per MW across layers 1 to 3
3Fitted hallThe UK colocation and regional edge operators; what a fit-out costs and who pays; what £ per kW per month buysAnatomy of one MW of hall: landlord scope against lessee scope
4ComputeThe neoclouds and sovereign providers in Britain; how they are funded; what a GPU earns and loses; who has already failedLife of a GPU: cost, earnings and value over five years
5Capacity saleHyperscaler off-take, backstops, marketplaces, public-sector channels; what sits between a GPU owner and a buyerWho pays whom: the money flow behind one 10 MW lease
6Model, app and userUK inference demand: who runs models here, why latency and sovereignty pull compute onshore, and how far from London it needs to beLatency rings around UK population from candidate sites
7MoneyFinance for the full chain in one place: cost of capital by layer, where debt is sized, what a lender will and will not lend onCapital stack by layer
8PaperThe contracts: connection offer, lease and its clauses, backstop, power pass-through, planning, sovereignty rulesOne lease on one page, clause by clause
9What it means for usWhere we sit, who we lease to, what we ask for, what we never do; the target list, revisedThe ask list, and the chain with our position marked
ACardsOne card per player: deep cards for eight, short cards for the restA card template, repeated

0.4 · The playersEight deep, the rest on cards

UK only, and spread across the chain rather than clustered in one layer. The deep eight are the firms whose behaviour sets the terms we will be offered. The cards cover everyone else a tenant, lender or broker might mention. The seed list is the operator and broker target list of 31 October; this study will revise it.

Deep eight

LayerFirmWhy deep
0UK Power NetworksOur DNO. Its connection process, queue and forecasts decide what a Kent or London site can hold
1SegroThe UK's largest industrial landlord now building powered shells to order; the closest thing to a competitor in our position
2Kao DataLandlord of choice for neoclouds in Britain; hosts Nebius, Ori and Civo; shows what fitted halls lease for and on what terms
2PulsantThe regional edge consolidator; buys sites of our size with fresh debt
3NscaleThe UK neocloud: BT, Microsoft and OpenAI relationships, grid-delayed at Loughton, IPO filed. Its delays show what a site with confirmed power is worth
3CivoForty edge sites planned at about 8 MW each; the clearest statement of UK inference demand at our size
3NebiusThe international neocloud scaling fastest in Britain; shows how a well-funded operator chooses between a shell and a hall
4Microsoft UKThe buyer behind Nscale and Nebius; its UK commitments and its exits set the credit behind our tenants

Cards, by layer

LayerFirms
0NESO; National Grid Electricity Distribution; SSEN; Northern Powergrid; Electricity North West; SP Energy Networks; Ofgem (as rule-setter)
1Telereal Trillium and Openreach; BT Group as counterparty; the US miner precedent (TeraWulf, Cipher, Applied Digital) as a structure, not a UK player
2Ark and Crown Hosting; Latos; nLighten and Proximity; Datum; Yondr; Green Mountain; Equinix, Digital Realty, Global Switch and Telehouse
3CoreWeave UK; Ori; DataVita; Fluidstack (as structure); Lambda and Sesterce (watch); the hyperscalers' own UK regions
4Google UK; OpenAI and Stargate UK; Anthropic; Meta; SF Compute; Nvidia DGX Cloud Lepton; Crown Commercial Service and G-Cloud
5 and 6UK model and app firms that buy inference (to be identified in chapter 6); API platforms such as Together, Baseten and Fireworks; Cloudflare and Akamai at the network edge; Isambard-AI and the UK sovereign programme
MoneyGPU and data-centre lenders active in the UK (to be identified in chapter 7); the green ABS and infrastructure funds behind the operators
IntermediariesCBRE, JLL, Cushman & Wakefield, Knight Frank, Savills, Avison Young; DC Byte, datacenterHawk, Structure Research

0.5 · MethodOnline only, labelled, with the gaps stated

0.6 · Carried forwardWhat we already know, to be tested

0.7 · OpenTo settle before chapter 1

  1. Title. "From power to answer" is the working title. Alternatives: "The chain", "Who sells the compute".
  2. Voltron. The earlier book names Voltron as the proposed anchor tenant. This study can treat Voltron as one layer 3 player among several, or leave it out and keep the piece purely market. We suggest one card.
  3. Length. Twenty-five to thirty pages of story plus the cards, with one infographic per chapter. If that is too long for the readers, the chapter 9 summary and the map can stand alone.
Chapter 1

Grid

Layer 0. Where firm power comes from, who allocates it, why the queue broke in 2025, what the regulator and the government are doing about it, and where in Britain the capacity actually is. Chapter 1 of From power to answer.

In shortThe connection queue has broken. The reforms punish large new applications and leave an existing supply alone.
125 GW
of demand offers by June 2025
11 to 13 GW
connectable before 2030
1,029
primaries with 10 MW spare
251
of them on UKPN's network
THE QUEUE AGAINST WHAT CAN CONNECT · GIGAWATTSDemand queue, transmission, Jun 202596 GWWaiting at distribution, Jun 202529 GWConnectable before 203013 GWUK data centres live today1.8 GWSources: DESNZ strategic-demand consultation (Mar 2026); NESO queue results (Dec 2025); Savills (Jun 2026). Roughly one megawatt in ten that has applied can connect this decade.

Basis. Market study, no returns. Capacity figures are the network operators' own published headroom, marked Indicated unless a connection agreement is cited. Dollar figures converted at October 2026 rates. Sources in section 1.9.

Chapter 1, in shortThe queue broke; the reforms favour small connections that are ready to build

What it is
Firm capacity at a primary substation

Six private groups run the fourteen distribution licences. They connect anything up to tens of MW; above that NESO and the transmission owners are involved.

What broke
A 125 GW demand queue

Demand applications rose from 41 GW to 125 GW in seven months to June 2025, 460% at transmission alone. About 140 data centres, c.50 GW, sit in the transmission queue; only 11 to 13 GW of demand can connect before 2030.

The fix
Evidence, a fee and a priority list

From 1 June 2026 any demand connection of 5 MVA or more must prove land, authority and a programme. Ofgem proposes a commitment fee for data centres above 40 MW, and government will prioritise named strategic projects.

For us
Buildings with a supply already agreed

A building that already holds an agreed supply sits outside the queue. 1,029 primary substations publish 10 MW or more spare today; 536 still do on the 2030 forecast. Those are the areas we search.

1.1 · What it isThe asset is an agreed supply, not a wire

Every building in Britain is connected to a distribution network at low or high voltage. What matters for compute is not the connection but the agreed supply capacity written into the connection agreement: the MVA the network operator has promised to deliver, firm, at that point of supply. A building's physical substation might be rated at 2 MVA while its agreement says 1 MVA; the agreement governs. Anything above the agreement needs a new application, and that application joins the queue.

The network has four tiers between a building and the national grid. Headroom at any one of them can bind.

TierWhat it isTypical voltageWho owns itWhat binds here
Local substationThe transformer that feeds a street or an estate11 kV to 400 VDNOTransformer rating; usually the cheapest thing to upgrade
Primary substationThe 33/11 kV site that feeds a town or a district; c.4,300 in GB33 kV to 11 kVDNOFirm capacity (one transformer out) against peak demand plus accepted offers. This is the tier our power map reads
Bulk supply pointFeeds several primaries132 kV to 33 kVDNOTransformer and circuit ratings; reinforcement takes years
Grid supply pointWhere the DNO meets the transmission network400/275 kV to 132 kVTransmission owner, operated by NESOTransmission impact; anything large enough to matter here needs a NESO assessment

A 10 MW demand connection normally lands at a primary at 11 kV or 33 kV. Whether it needs a transmission assessment depends on the headroom at the grid supply point above it, not on a fixed MW threshold.

1.2 · WhoSix groups, fourteen licences, one system operator

Distribution is a regulated monopoly by area. The licences were privatised in 1990 and have changed hands many times since; two changed in the last two years. The regulatory settlement is the same for all six and matters more than the owner, but the owner shows whose capital is behind the reinforcement programme.

GroupLicence areasOwner (2026)ScaleNote for us
UK Power NetworksLondon, South East, East of EnglandEngie, since 7 May 2026 (bought from CK Infrastructure, Power Assets and CK Asset at a £10.5bn equity value)c.8.3m homes and businessesOur DNO. Kent, London and Essex are all UKPN. A UKPN director has said data centres on its network draw only 30 to 40% of their agreed capacity on average
National Grid Electricity DistributionEast Midlands, West Midlands, South Wales, South WestNational Grid plc (bought Western Power Distribution from PPL for £7.8bn, 2021)c.8m customers; the largest DNOPublishes the most complete capacity data; the Midlands hold the most industrial floorspace
SSEN DistributionSouthern England, North ScotlandSSE plc (the 25% Ontario Teachers' stake is in SSEN Transmission, not distribution)c.3.1m customers in the south; the north is sparseSouthern England borders UKPN's South East; no 2030 forecast in its published data
Northern PowergridNorth East, YorkshireBerkshire Hathaway Energy3.9m customersYorkshire has the second-largest count of primaries with 10 MW spare
SP Energy NetworksCentral and Southern Scotland; Merseyside, Cheshire and North WalesIberdrola (ScottishPower)c.3.5m customers (Indicated)Central Scotland publishes the most spare capacity of any area, and has the least demand to use it
Electricity North WestNorth WestIberdrola 88% (completed 2025, £2.1bn), Kansai-led consortium 12%c.2.4m connections, 5m peopleNow the same owner as SPEN; two of the six groups are Iberdrola

Above them all sits NESO, the National Energy System Operator, publicly owned since October 2024. It runs the transmission queue, assesses large demand for transmission impact, and is now being directed by government on which demand projects go first. Ofgem sets the price controls (RIIO-ED2 runs April 2023 to March 2028 with £22.2bn of allowed spend; ED3 from April 2028 is being designed now) and writes the connection rules.

1.3 · What they doHow a connection happens, and what it costs

  1. Budget estimate. A desk exercise with no site visit. For 1 MVA and above a DNO must return it within 20 working days under the guaranteed standards.
  2. Application and formal offer. For high-voltage work the standard is 65 working days to a quotation. Since 1 June 2026 any application of 5 MVA or more must carry a letter of authority, heads of terms if the applicant does not own the site, a site plan, a single-line diagram where the kit could disturb the network, and a preliminary programme with a credible connection date. "As soon as possible" is no longer accepted.
  3. Acceptance and milestones. Offers are open for a fixed period (ENWL's is 180 days; UKPN's should be checked). Acceptance starts the milestone clock. Where the connection date is within five years UKPN works the milestones forward from acceptance.
  4. Charges. Since the Access reforms of April 2023 a demand customer pays for the sole-use assets to its site and nothing towards reinforcement of the shared network, unless the project trips the high-cost threshold of £1,720 per kVA or is deemed speculative. Reinforcement is funded by the DNO and recovered from all users through use-of-system charges. In effect, a demand customer in Britain does not pay for the shared network it triggers.
  5. Energisation. The physical works. The binding constraint in 2026 is plant: transformer and switchgear lead times have lengthened, in places doubling, and now set the programme.

Cost. A 10 MW connection therefore costs mostly the sole-use works: the cable from the primary, the intake switchgear and metering. On a site that already holds the capacity, there is no connection cost at all, only the intake. The landlord scope in our model carries the intake and the network operator's charge; the biggest variable is whether the supply needs raising.

1.4 · What brokeThe queue, in numbers

MeasureFigureDate and source
Transmission demand queue96 GWEnd June 2025, when the queue closed; up 460% in six months (DESNZ, Mar 2026)
Waiting at distribution29 GWSame date and source
Total demand offers, Nov 2024 to Jun 202541 GW to 125 GWOfgem, reported by law-firm briefings 2026
Data centres in the transmission queuec.140 projects, c.50 GWNESO Call for Input, 2025
Data centre queue by Ofgem's countc.315 projects, c.73 GWOfgem Curate consultation, Jul 2026; 99% of that capacity is in projects above 40 MW
Demand that can connect before 203011 to 13 GWNESO queue results, Dec 2025 (DCD says 13; Savills and Slaughter and May say 11); a further c.86 GW between 2030 and 2035
London data centres live and queuedc.760 MW live, 8 GW+ queuedGLA figures via press, 2026; another count puts live at 1,050 MW
Data centres applying for gas insteadc.117 casesOfgem Connect update, Jun 2026: operators seeking gas generation to run before the grid arrives
Wait for a new 50 MW data centre connectionc.7 yearsBurges Salmon, 2026; against c.4 in Northern Virginia and c.8 in Dublin

Nscale's Loughton campus is the example. Planned at 50 MW rising to 90 MW, it lost its anchor customer in October 2026 when Microsoft withdrew, and is now reported for the 2030s. The constraint was 90 MW of new connection in Essex, not the building.

1.5 · How it is being fixedOfgem, government and the networks

Ofgem: Curate, Plan, Connect

Government: strategic demand

The DESNZ consultation of March 2026 (closed 15 April; summary updated 28 October 2026) uses the Planning and Infrastructure Act 2025 to: tighten queue entry for data centres across transmission and distribution together; designate a list of strategic demand projects, including AI Growth Zones, to which NESO must reallocate capacity freed when others leave the queue and for which it may reserve capacity ahead of need; and, later, align data centre connections to a national data centre strategy. A Connections Accelerator Service has run since December 2025 for a small number of named projects. Distribution-connected projects are not yet inside the prioritisation rules; the paper says a parallel process will be designed "as soon as possible".

The networks: 5 MVA and above

The ENA's minimum information requirements for demand of 5 MVA and above took effect on 1 June 2026 across all DNOs: letter of authority, heads of terms, site plan, single-line diagram and a dated programme. The rule is aimed at speculators holding capacity on land they do not control. It also means an application in our name needs the site under contract first.

Effect. Each of these measures falls hardest on large, speculative, new-build connections. None of them touches a building that already holds an agreed supply. The reforms widen the gap between a 90 MW application and a 5 MW building whose capacity is already agreed.

1.6 · Why nowWhy the DNOs will reinforce, and why not fast enough

The DNOs are regulated to a revenue allowance, so they reinforce when Ofgem lets them. ED2 allowed £22.2bn across the six groups for 2023 to 2028. The National Infrastructure Commission put the distribution need at £37bn to £50bn to 2050, at least double current annual allowances, and Ofgem's ED3 methodology decision of May 2026 moves to a build-and-flex model with the regional plans as the demand reference and a higher allowed return on equity. National Grid's chief executive said in 2024 that data centre demand would rise six-fold in ten years. The funding is in place or planned; the constraints are plant and people, and reinforcement at a bulk supply point still takes years.

Meanwhile the DNOs' own 2030 forecasts show headroom falling at 1,820 of the 2,940 primaries that publish one, as heat pumps, vehicles and housing take the slack. Headroom published today may not be there in four years.

1.7 · Where the power isPrimaries with 10 MW or more to spare

Our own schedule reads the published headroom at 4,277 primary substations across the fourteen areas and tests it against each operator's 2030 forecast where one exists. The map and table below count primaries with 10 MW or more spare, the size that matters to us.

10 MW+ spare today, still 10 MW+ on the DNO 2030 forecast10 MW+ today, forecast to fall below 10 MW by 203010 MW+ today, no 2030 forecast publishedDot size shows MW spare. Box marks London. 1,029 primary substations.
AreaDNOPrimaries5 MW+ spare10 MW+of which hold to 203020 MW+Published headroom, MW
Central and Southern ScotlandSPEN389305211141124,011
YorkshireNorthern Powergrid36317511875112,271
East of EnglandUKPN4422679368213,241
LondonUKPN1061028869473,208
Southern EnglandSSEN42415380no forecast172,103
South EastUKPN2331557041202,045
North EastNorthern Powergrid179106664881,338
Merseyside, Cheshire and North WalesSPEN335123604081,729
West MidlandsNGED2128757mostly no forecast291,622
North WestENWL368151522851,724
East MidlandsNGED367104481341,288
South WestNGED305724575990
North ScotlandSSEN3605721no forecast0762
South WalesNGED194532045858
Great Britain4,2771,9101,02953619227,190

power.yeats.com, read 31 Oct 2026, from each DNO's published capacity data and long-term development statement. "Hold to 2030" counts primaries whose own operator's forecast keeps 10 MW or more spare; 209 of the 1,029 publish no forecast. All figures Indicated: a verdict band is never a DNO confirmation.

UKPN's three areas hold 251 of the 1,029 primaries with 10 MW spare, and 178 of the 536 that hold to 2030. For this size of load our DNO is the best placed in the country. Central Scotland has the most spare capacity and the least demand to use it, which is why the AI Growth Zone went to Lanarkshire. The Midlands have the most industrial floorspace but publish no 2030 forecast, so a building there is harder to underwrite than a weaker one in Kent.

1.8 · What it means for usBuy the agreement, not the application

1.9 · Sources

Chapter 2

Powered site

Layer 1, our position in the chain. What a powered site is and the three forms it is sold in, who else holds one in Britain, what the market pays for power on land and in a building, what the American conversions show, and where our rent sits. Chapter 2 of From power to answer.

In shortBuy at building prices. Lease at power prices.
£0.7m to £1.2m
the price of one grid MW, London hub
3.0 GVA
Segro's power bank
4,600
exchanges leaving BT's use
43%
our rent against a fitted hall
WHAT A MEGAWATT COSTS AT EACH STEP · £M PER MWPower alone: land with a connection, London hubLinklaters, Jul 2026£0.7–1.2mPower alone, northern UKLinklaters, Jul 2026£0.17–0.6mOur building, works and connection, all inEdge model£4mConverted sites sold, UK and USRedcentric, Cogent, Loudoun£3.1–5.5mFitted hall, LondonOfgem basis; Segro and Pure£9.5–17.9mThe chips on topc.1,000 H100-class GPUs£26m

Basis. Market study, no returns. Rent is £750k per MW of firm supply a year; cost £4.0m per MW all in. Third-party figures are quoted as published, with sterling in brackets at October 2026 rates (£1 = $1.33 = €1.18). "Derived" means our arithmetic from a published total. Sources in section 2.7.

Chapter 2, in shortPower has a market price, and we buy it as a building

What it is
Land or a building with a firm supply

Sold three ways: powered land, powered shell, or fitted hall. We sell the powered shell in an existing building. The operator funds the kit.

What power is worth
c.£0.7m to £1.2m per grid MW

In London and the other big European hubs, land with a connection carries that premium per megawatt (Linklaters, Jul 2026). Savills puts data-centre-ready land at £8m to £15m an acre against £4.5m to £6m for ordinary industrial.

Who else
Segro, Tritax, Harworth, TT Group

The listed landlords are moving up the stack to fitted halls at 50 to 150 MW. The owner of the 4,600 closing exchanges has so far sold them for housing. Nobody is doing 5 to 15 MW in existing buildings at scale.

Our rent, in context
About 43% of a fitted London hall

£750k a MW is £62.50 per kW a month, against CBRE's £145 for fitted London capacity. The operator funds the hall and the kit; we fund the building and the connection.

2.1 · What it isThree products, one scarce input

A powered site is land or a building with a firm electricity supply already agreed with the network operator. The industry sells it in three forms, and the form decides who funds what and what the rent is called.

FormWhat the landlord providesWhat the occupier providesHow it is pricedWho sells it in Britain
Powered landA site with a connection agreement, usually sold freeholdEverything above ground£ per acre, or £ per MW of agreed capacityHarworth, Segro (selected plots), landowners near substations, hyperscalers buying
Powered shellA secure building, intake switchgear and metering at the point of supply, the connectionInternal distribution, generators, UPS, cooling, racks, fibre fit-out, the compute£ per MW of firm supply a year, indexed, 10 to 15 yearsSegro (Slough), Tritax (Manor Farm, planned), Yeats Edge in existing buildings
Fitted hall (turnkey, wholesale)All of the above plus cooling, UPS, generators and often fibreRacks and compute£ per kW of IT load a monthSegro with Pure DC, Kao, Ark, Yondr, the London campus operators (chapter 3)

Grid MW and IT MW are different numbers. A fitted hall quotes IT load, the power the racks draw. A powered shell quotes the agreed supply at the intake, which must also run cooling, losses and reserve. The gap is the operator's efficiency: a well-run liquid-cooled hall turns roughly 1 MW of supply into 0.8 MW of IT load; an old air-cooled one, less. Our rent is per MW of firm supply. Each comparison below states its basis. UK Power Networks has observed that data centres on its network draw on average only 30 to 40% of the capacity they hold. Operators therefore guard their agreements, and a building with a large, under-used agreement is worth looking at.

2.2 · WhoThe holders of power in Britain

WhoWhat they areWhat they holdWhat they do with itRead for us
SegroFTSE 100 industrial REIT; Slough Trading EstateA "power bank" of 3.0 GVA across European availability zones (July 2026), 1.4 GVA of it to lease within seven yearsMoving from powered shells to fully fitted halls in joint ventures with Pure DC: Park Royal (56 MW IT, c.£1bn, 70 MVA incoming, ready 2029) and a second in Paris. Still signs shells where a customer wants one: Slough, 50 MVA, pre-let March 2026 with the customer contracting the power directlyThe reference landlord. Its move up the stack leaves the shell product to others, and its scale starts at 50 MVA
Tritax Big BoxFTSE 250 logistics REITManor Farm, 74 acres by Heathrow, bought January 2025 for an initial £70m plus 21% of phase-one profit to the vendor107 MW phase one (147 MW with phase two), consented after a judicial review, to be built as a powered shell subject to a pre-let; a 50% joint venture with an unnamed European generator secures connections to two substationsShows what a listed landlord pays for powered land and that it needs a pre-let before it builds
Harworth GroupListed regenerator, now a pure-play powered land and logistics specialistAbout 0.8 GW of further connections beyond Skelton Grange; up to six hyperscale sites, all freehold or under optionSold two plots at Skelton Grange, Leeds, to Microsoft for £106m (resolution to grant April 2026); exclusivity on a second site to an unnamed provider, August 2026The purest powered-land seller in Britain. Its buyers are hyperscalers, not neoclouds
TT Group (Telereal Trillium)Private property group; bought c.6,700 BT properties in 2001 for £2.38bnNearly all of Openreach's c.5,600 exchanges, c.4,600 of which close from 2025 into the early 2030s; the main lease runs to 2031Exited exchanges and offices sold so far have gone to housing; no data-centre reuse found, no marketing programme announced; first exits (Deddington 2025) done, next pilots slipped to November 2026The counterparty for the exchange channel. Slow, small per site, and not yet pricing the power
Stellanor (DWS)Infrastructure fund platformEight Redcentric data centres, bought October 2025, completed May 2026Enterprise value up to £127m for "41 MW", of which 23 MW is secured grid: £3.1m to £5.5m per MW derivedA UK price for existing small sites with power
Gravity Edge (BlackRock, DGP)Edge platformCamberley enterprise data centre, September 2025, expandable to 20 MWMore than £100m including modernisation; strategy is 5 to 20 MW sites with under-used capacityThe closest strategy to ours in Britain, at the fitted-hall layer and with institutional money behind it
The hyperscalers as buyersMicrosoft, Google, AmazonBuying powered land outright where it exists (Microsoft at Skelton Grange; Google's £5bn UK programme)Build their own hallsThey set the top of the land market and will not lease a 10 MW building
Yeats EdgeSponsor-developerA national screen of c.80,000 buildings against published headroom; two seed sites under appraisalBuys existing buildings whose connection agreement already holds the capacity, does the landlord works, leases as a powered shell at £750k a MWThe gap: 5 to 15 MW, existing buildings, this decade

2.3 · How they make moneyWhat the market pays for power

Land

EvidenceFigureSourceWhat it says
London industrial land£4.5m to £6m an acreSavills, reported April 2026The data-centre premium on an acre is £3.5m to £9m in London. At the rule-of-thumb half to one acre per MW, that is the price of the connection
London land suitable for a data centre£8m to £15m an acreSavills, same
Powered land, FLAPD hubs (Frankfurt, London, Amsterdam, Paris, Dublin)€0.8m to €1.4m per grid MW (c.£0.7m to £1.2m)Linklaters, 8 July 2026The market value of a megawatt of agreed supply before any building; the cleanest figure in the table
Powered land, northern UK€0.2m to €0.7m per grid MW (c.£0.17m to £0.6m)Linklaters, samePower is worth a third as much where the users are not
Northern Virginia, for comparisonc.$4m an acre entitled without power; $6m+ withUS trade press, 2026The same premium exists in the deepest market in the world
Manor Farm, Heathrow£70m initial for 74 acres (c.£0.95m an acre) plus 21% of phase-one profitTritax RNS, January 2025Bought before the connection was secured; the power came afterwards through the generator joint venture
Skelton Grange, Leeds£106m for two plots to MicrosoftHarworth, 2025 to 2026A hyperscaler paying for powered land in the north

Buildings with power, sold

DealWhere, whenMWPricePer MW, derived
Stellanor buys Redcentric's eight sitesUK, May 202641 MW; 23 MW secured gridEV up to £127m£3.1m to £5.5m
Gravity Edge buys CamberleySurrey, Sep 2025to 20 MWmore than £100m with modernisationabove £5m at 20 MW
I Squared buys ten Cogent data centres (converted Sprint switch sites) for an inference platformUS, May 2026c.53 MW$225m (c.£170m)$4.25m (c.£3.2m)
Cogent's asking prices, six converted sitesUS, Feb 20253.9 to 8.1 MW each$44m to $140m asked$10m to $17m asked; a letter of intent later fell over on vendor finance
Loudoun net-lease hyperscale campusVirginia, Dec 2025160 MW$555m$3.47m (c.£2.6m); powered-shell cap rate 5.0%, turnkey 6.5% in the county's 2026 guidelines

Our model carries £4.0m per MW all in (£2.5m building, £1.5m works). It sits inside the range paid for converted and edge stock in Britain and America. The Cogent asking prices show what a seller tries for when the site is already fitted and running.

Powered shells and fitted halls, leased

LeaseFormMW, termContracted valuePer MW a year, derived
Yeats Edge, our modelPowered shell, existing buildingper MW of firm supply, 10 to 15 years, indexedn/a£750k
Segro, Slough pre-letPowered shell, new build50 MVAnot disclosedn/d
TeraWulf to Fluidstack, Lake Mariner, New YorkTurnkey, landlord-built on a former coal site; modified gross; Google backstopc.200 MW, 10 years + two 5-year options$3.7bn initial term ($8.7bn with extensions)c.$1.85m (c.£1.4m); landlord cost $8m to $10m per critical MW; expected site margin c.85%
TeraWulf and Fluidstack joint venture, TexasTurnkey, 51% TeraWulf; Google backstop168 MW, 25 yearsc.$9.5bnc.$2.26m (c.£1.7m)
Applied Digital to CoreWeave, North DakotaTurnkey, landlord-built250 MW rising to 400 MW, 15 yearsc.$7bn rising to c.$11bnc.$1.85m (c.£1.4m)
Core Scientific to CoreWeave, 70 MW expansionModified site70 MW, 12 years$1.225bnc.$1.46m (c.£1.1m)
London fitted capacity, 20 MW+Fitted hallper kWup to £145 per kW, up 12% in a yearc.£1.74m if per month, on IT load
Segro and Pure, Park RoyalFitted hall, c.£17.9m per MW to build56 MW IT"9 to 10% net yield on cost" as publishedc.£1.6m to £1.8m net

The American figures are contract revenue over critical IT load and may bundle power pass-through and services; they are turnkey, not shell. They are precedent, not UK fact. The CBRE figure is a capacity price whose period is not stated in the release; per month is the industry convention.

CAPITAL PER MW, WHO FUNDS WHATPowered building, our model£4m£2.5m building + £1.5m works; connection in handUS converted site, turnkey (TeraWulf)£6–7.5m$8–10m per critical MW, Aug 2025London fitted hall, Ofgem's assumption£9.5mOfgem data-centre capex basis, Sep 2026London fitted hall, Segro and Pure£17.9mc.£1bn for 56 MW IT, Park RoyalGPUs and kit, the operator's layer£26mc.£26m per MW on top of any hallINCOME PER MW A YEARPowered building, our model£0.75m a year£750k per MW of firm supplyUS converted site, turnkey (TeraWulf)£1.39m a year$3.7bn over 200 MW and 10 yearsLondon fitted hall, net (Segro and Pure)£1.6–1.8m a year9–10% net yield on cost, as publishedLondon fitted hall, gross (CBRE)£1.74m a yearup to £145 per kW, 20 MW+, per-month basis assumed

Capital per MW and income per MW a year across the first three layers, from the figures above. Our position carries the smallest capital for the smallest rent; the fitted layer is two to four times both; the compute layer is another £26m per MW, funded by the operator. Sterling at October 2026 rates; US and CBRE figures on the bases stated in the tables.

2.4 · The American conversionsMines, switch sites and exchanges, converted

The nearest precedent for buying power as a building is the United States in 2024 and 2025, where bitcoin miners, telecoms carriers and infrastructure funds turned existing powered sites into AI capacity faster than new capacity could be built.

  1. The miner conversion. TeraWulf, Cipher, Applied Digital and Core Scientific owned sites with hundreds of megawatts of agreed supply, bought for mining when power was the only thing that mattered. They leased them on 10 to 25 year terms to neoclouds (Fluidstack, CoreWeave) at turnkey rents of roughly $1.5m to $2.3m per MW a year, funding the fit-out themselves at $8m to $10m per critical MW. In the Fluidstack cases Google guaranteed the tenant's lease in return for warrants over the landlord. The land and the power were bought at one price and leased at another.
  2. The switch-site conversion. Cogent inherited Sprint's long-haul network and with it switch buildings with power and fibre in nine metros. It fitted six and asked $10m to $17m per MW for them; a buyer walked away wanting more than half the price on vendor finance; I Squared then bought ten for $225m, $4.25m per MW, to seed an inference and edge platform. The asking price and the price achieved were far apart, and the eventual buyer was an infrastructure fund assembling a platform of 5 to 8 MW sites. It is the closest precedent for the Openreach exchanges.
  3. The carrier sale-and-leaseback. AT&T sold 74 central offices for $850m and leased them back; Ziply is converting about 200 to colocation; Verizon is fitting some for inference. Telefónica in Spain has turned closed copper exchanges into 1 to 2 MW edge nodes, 100 planned, with a €93m EU grant; FiberCop in Italy plans about 100. The telecom model is many 1 to 2 MW nodes, below our 5 to 15 MW target.

The counter-evidence. Savills' view is that retrofits are "less compelling than occupiers expect because the critical cost sits in M&E". That holds for a fitted hall, where the building is a small part of £9.5m to £18m per MW. It does not hold for a powered shell, where the landlord provides the building and the connection and the tenant funds the M&E. Our model depends on keeping that split between landlord and tenant.

2.5 · Why nowWhy a connection in hand is worth more each year

2.6 · What it means for usBuy at building prices, lease at power prices

2.7 · Sources

Chapter 3

Fitted hall

Layer 2. What a fitted data hall is and what it is sold in, who runs them in Britain and who owns those firms, what a megawatt of hall costs and who pays for each piece, how dense the racks are getting, and why the regional operators are the tenants to court. Chapter 3 of From power to answer.

In shortLandlord scope stops at the intake switchgear. Everything inside it belongs to the tenant.
1,803 MW
live in the UK, 91% in London
8%
vacancy; 96% of 2026 completions sold
£145
per kW, London 20 MW+, up 12%
£0.5m to £1.3m
the landlord's share of a £9m hall
RACK DENSITY · KW PER RACK4 kW2019 rackair27 kWAverage rack, 2026air45 kWAir cooling ceilingrear-door130 kWBlackwell NVL72liquid230 kWVera Rubin NVL72liquid600 kWNext (Kyber)liquidSources: AFCOM 2026 via Encor; Schneider Electric 2026; Pulsant; Nvidia specifications as reported. Above about 50 kW the heat is carried away in liquid rather than air.

Basis. Market study, no returns. Rent is £750k per MW of firm supply a year. Costs are "indicative" where derived from published shares of a whole-hall figure, and converted at £1 = $1.33. Sources in section 3.8.

Chapter 3, in shortThe hall carries the capital and the risk; we lease to it and stop at the intake

What it is
Cooled, backed-up kilowatts

A fitted hall sells IT load by the kW a month with power passed through at cost. London capacity at 20 MW+ is up to £145 per kW, up 12% in a year. The UK has 1,803 MW live, 91% of it in London, 8% vacant.

Who
Campus operators and regional edge

Virtus, Equinix, Digital Realty, Vantage, Ark, Kao, Global Switch, Telehouse and Yondr run the big London halls. Pulsant, nLighten, Latos and Datum run 1 to 5 MW sites in the regions, and are buying sites.

What a MW costs
c.£9m fitted, £26m with compute

Of a c.£9m London hall, the landlord's share is £0.5m to £1.3m: the connection, the intake and the building. Everything beyond the intake is the lessee's, and liquid cooling adds £1m to £2.5m more.

For us
Lease to the operator; stop at the intake

A regional operator leasing our shell at £750k a MW and selling kW at the London rate has margin. The split at the intake switchgear keeps us a landlord. Density is the lessee's problem.

3.1 · What it isKilowatts, with everything that keeps them on

A fitted hall is a powered site with the critical plant installed: the distribution and transformers beyond the intake, uninterruptible power supplies, standby generators, cooling, fire suppression, monitoring, carrier fibre and the racks themselves. The product is not space but conditioned, backed-up IT load, sold by the kilowatt per month with the electricity recharged at cost.

TermWhat it meansWhy it matters to the money
Wholesale colocationWhole halls or suites, 1 MW and up, 10 to 15 year terms, to hyperscalers, neoclouds and large enterprises1,163 MW of the UK's live capacity. Priced per kW; the customer brings its own racks and often its own operations team
Retail colocationRacks or cages, 3 to 5 year terms, to enterprises and service providers347 MW of live capacity. Higher price per kW, higher churn, more management
Power pass-throughElectricity billed to the customer at cost on metered consumption, "plus E"The energy bill usually exceeds the base rent. It must never reach the landlord
PUE, power usage effectivenessTotal power drawn divided by IT power. 1.2 is good; 1.5 is oldEvery 0.1 of PUE is a 10% difference in the customer's energy bill and in how much IT load one MW of supply can carry
DensitykW per rackDecides whether air cooling will do and how many racks fit in a megawatt. See section 3.5
AvailabilityThe uptime promised, typically 99.99% or better, backed by service creditsThe generators, UPS and concurrent maintainability exist to meet it; most of the hall's capital goes on this

3.2 · WhoTwo tiers of operator in Britain

The campus operators run the London halls that hyperscalers and neoclouds lease at scale. The regional edge operators run 1 to 5 MW sites in the cities where enterprises and the public sector sit. The campus tier builds its own halls; the regional tier buys existing sites. Ownership is given where it could be confirmed from public sources.

Campus and wholesale operators

OperatorOwnerUK footprintWho sits in their hallsRead for us
VirtusST Telemedia Global Data Centres (Singapore)Largest UK operator by capacity in the 2025 portfolio reports; London5 at Slough estimated at c.90 MWHyperscalers, large enterpriseBuilds its own campuses at 50 MW+; not a shell tenant
EquinixNYSE-listed REITSlough and Docklands campuses; bought the undeveloped 85-acre DC01UK site in HertfordshireInterconnection, enterprise, cloud on-rampsReference for retail pricing; builds its own
Digital RealtyNYSE-listed REITCrawley (LGW15 and 16, 24 MW across the campus) and London; CoreWeave's first UK landlordNeoclouds, cloud, enterpriseShows a neocloud will take fitted space from a REIT on day one for speed
Global SwitchJiangsu Shagang Group with Avic Trust; sale attempts since 2021 stalled on priceLondon East and North, Docklands; CoreWeave's second UK siteCarriers, cloud, neocloudsA legacy Docklands position with Chinese ownership that some customers screen out
TelehouseKDDI (Japan)Docklands; North Two at c.73 MW (secondary estimate)Carriers and the London internet exchangeFibre density no other UK site matches
VantageDigitalBridge and Silver Lake-backed, US223 MW across 2.6m sq ft in the UK; Cardiff campus (£254m raised)HyperscalersWholesale at 50 MW+ per building
Ark Data CentresElliott Investment Management; TPG reported in talks to buy at c.$5bn (c.£3.8bn), late October 2026; Crown Hosting joint venture with the Cabinet Office27 UK and Belgian facilities; Cody Park and Longcross; £807m Longcross expansion for Nebius; 25 MVA "AI power hub" in SurreyGovernment via Crown Hosting; NebiusThe public-sector channel, and a sale that will reprice UK halls
Kao DataInfratil 53%, Legal & General Capital 32%, Goldacre NOÉ 15% (2023 split)Harlow campus; Stockport 40 MW consented; Manchester £350m due 2026Nebius (22 MW, ten years), Ori, CivoThe neocloud landlord of choice; it knows every tenant on our list
YondrDigitalBridge-backedSlough 100 MW campus; first 10 MW live April 2025; £532m green securitisation February 2026HyperscalersShows the debt market will lend against fitted halls
CyrusOne, Colt DCS, Green MountainKKR and GIP; Fidelity; AzrieliIver Heath 90 MW planned; Hayes; LON-East Romford, where a neocloud took 14 MW in September 2026Hyperscale, enterprise, neocloudSecondary references

Regional edge operators

OperatorOwnerFootprintWhat they have done latelyRead for us
PulsantAntin Infrastructure Partners (since 2021)14 UK sites, platformEDGE; revenue c.£126m and EBITDA c.£24m in the latest figures a data vendor lists, year unstatedBought two SCC sites (Birmingham c.2 MW, Fareham c.3 MW) in 2025; £187m facility refreshed October 2025 for acquisitions; 1.2 MW AI-ready hall at Milton Keynes, £1m into Birmingham for inference; customer racks up from c.4 kW to 10 to 20 kWBuys sites of our size with fresh debt and is retrofitting for density
nLightenI Squared Capital, with more than $500m (c.£375m) of committed equity; owns Proximity Data Centres in the UK (bought 2023, price undisclosed)Ten UK edge sites from Proximity plus Europe£100m UK programme; £85m financing led by Rivage, March 2026; Bristol refit for AI density, June 2026Pitches inference at the edge; acquisitive in the regions
Latos Data CentresFounder-led; investors not disclosed onlineCardiff: three buildings, 90 MVA, under construction; Stockton-on-Tees £100m approved; East Manchester applicationTargets 40 sites by 2030 with modular edge for AIA pipeline model that needs sites; funding to be tested
Datum DatacentresOwnership not confirmed onlineFarnborough; two Manchester sites1 MW hall expansionsToo small to take 10 MW alone
Gravity EdgeBlackRock and DGPCamberley, to 20 MWStrategy of 5 to 20 MW sites with under-used capacity (chapter 2)Closest strategy to ours, one layer up

3.3 · How they make moneyThe hall's economics

MeasureFigureSource and date
UK live capacity1,803 MW; London 1,637 MW (91%)Savills, June 2026
Of which wholesale / retail1,163 MW / 347 MWSavills, same
Vacancy8% UK, 7% London (27% in 2016)Savills Q1 2026; CBRE sees London at 5.9% by year end
Take-up217 MW in 2025; 19 MW in Q1 2026Savills; CBRE expects London above 200 MW in 2026
Under construction, UK242 MW; c.66 MW completing in 2026, 96% pre-soldSavills, June 2026
Price, London 20 MW+ new capacityup to £145 per kW, up 12% in a yearCBRE Q1 2026; providers raised prices at least 10% for buyers of 10 MW+ to cover build costs, and are raising indexation rather than headline rates
Build cost, London, air-cooled cloud hall$12.0 per W (c.£9m per MW)Turner & Townsend 2025–26 index; AI premium 7 to 10% (US data)
Build cost, Ofgem's planning assumption£9.5m per MWOfgem, via Linklaters, September 2026
Build cost, fully fitted, Segro and Purec.£17.9m per MW; "9 to 10% net yield on cost"Segro RNS, 2025
Site margin on a turnkey leasec.85% NOI margin expectedTeraWulf, Lake Mariner, August 2025 (US precedent)
Retrofit for liquid coolingc.$2m per MW against $11m+ greenfieldSTL Partners, May 2026; a contrary view calls dense retrofits "reconstruction, not incremental retrofit"

A London hall costs £9m to £18m a megawatt to fit and earns up to £1.7m a megawatt a year gross at the CBRE rate, with power passed through. The operator's margin is the gap between that rent and its cost of capital. The margin is wide while vacancy is 7% and every completing megawatt is pre-sold. The risk sits in the plant, which is bespoke to a density and a cooling method that change every two years. A hall fitted for 10 kW racks in 2022 is being refitted for 100 kW racks in 2026.

3.4 · AnatomyOne megawatt of hall, and who pays for each piece

The figure below splits a fitted megawatt into its parts, with the landlord's items in teal and the lessee's in grey. The landlord's figures are from our own scope table; the lessee's are derived from the published shares of a c.£9m London hall (electrical 40 to 45%, cooling about 20%) and the cooling-method ranges quoted in 2026, so they are indicative and will vary by site.

ONE MEGAWATT OF FITTED HALL · £M PER MW · WHO FUNDS ITLANDLORDLESSEEOPERATORGrid connection, intake switchgear, metering£0.1–0.6mNetwork operator's charge plus the intake; nil where the agreement already holds the capacityBuilding: security, making good, welfare, base fire£0.35–0.7mFence, CCTV, access control, refurbishment to a presentable standard, surveys, feesHV and LV distribution, transformers beyond the intake£0.8–1.2mDerived from electrical at 40–45% of a c.£9m London hallUPS and batteries£0.8–1.2mSame basisGenerators and fuel£1–1.5mSame basis; standby for the full IT loadCooling plant: air£1.1–1.5mc.$1.5–2m per MW; ceiling c.30–50 kW a rackCooling plant: liquid (instead of air)£2.3–3.9mc.$3–5.2m per MW; needed above c.50 kW a rackData-hall fire, BMS, inside security, fibre fit-out£0.4–0.6mSuppression, monitoring, carrier entriesRacks, PDUs, containment, floor strengthening£0.3–0.5mTen to forty racks per MW depending on densityCompute: GPUs, network, softwarec.£26m, off the scaleThe operator's layer; never the landlord'sLandlord, our scope: c.£0.5m to £1.3m per MW (model carries £1.5m)Lessee, the hall with air cooling: c.£4.4m to £6.5m; with liquid cooling: c.£5.6m to £8.9mWhole fitted hall, for reference: Turner & Townsend London c.£9m (air-cooled cloud); Ofgem assumes £9.5m; Segro and Pure c.£17.9m all in
Landlord provides (our scope)Lessee provides
The connection: network operator's charge, intake switchgear and metering at the point of supplyHV and LV distribution and transformers beyond the intake
Security: fence, gates, CCTV, access controlUPS and batteries; generators and fuel
Making good and refurbishment to a presentable standardCooling plant, air or liquid; dry coolers, pipework, CDUs
Welfare: toilets, kitchen, officesData-hall fire suppression, BMS, inside security
Base-building fire compliance; asbestos and surveys; planningFloor strengthening for racks; fibre fit-out and carrier entries
Fees and contingencyRacks, PDUs, containment, and the compute itself

The split at the intake switchgear defines our scope. On the landlord's side, c.£0.5m to £1.3m per MW with £1.5m carried; on the lessee's, £4m to £9m before a single GPU. The lease must set out where the split falls, in terms a lender's engineer can check.

Space is not the constraint. One megawatt at today's average density of 27 kW a rack is about 37 racks; at AI densities of 120 to 230 kW it is five to eight. With coolers, a megawatt needs roughly 650 sq ft. A 10 MW tenant needs about 6,500 sq ft of a building that may have 60,000.

3.5 · DensityRacks are now denser than air-cooled rooms were built for

WhatkW a rackCoolingSource
Average rack, 2026 survey27 (16 a year earlier)AirAFCOM 2026, via tenant advisory
Pulsant's customers10 to 20 (from c.4)Air, rear-door exchangersPulsant, 2026
Air cooling, practical ceiling30 to 50Rear-door heat exchangers at the top of the rangeSeveral 2026 sources
Nvidia GB200 NVL72c.120 to 132Direct-to-chip liquid2025–26 specifications, figures vary
Nvidia Vera Rubin NVL72c.190 to 230LiquidSchneider Electric, May 2026
Inference, by model sizeunder 20 to 140Air to liquidSchneider Electric, July 2026

The cooling decision belongs to the lessee. Whether a hall is air or liquid follows from the tenant's hardware, and it is their £1m to £4m a megawatt, not ours. Liquid cooling at the chip also makes the building less important. The heat is captured in a loop and rejected outside through dry coolers, so the room no longer has to move large volumes of air. An ordinary industrial shell with floor strength, a yard for coolers and a firm supply is a better host for a 2026 rack than a 2015 data hall built for air.

3.6 · Why nowConsolidation, density and a seller's market

3.7 · What it means for usThe fitted layer is our tenant, and its numbers are our reference

3.8 · Sources

Chapter 4

Compute

Layer 3. The firms that own the chips: who they are in Britain, how they are funded, what a GPU earns and loses over its life, who stands behind them, and who has already stumbled. Our tenant sits in this layer. The question for us is whether it will still be paying in year eight. Chapter 4 of From power to answer.

In shortThe tenant's chips wear out in three to six years. We underwrite its contracts, not its brand.
£26m
of chips per megawatt
$2.6 to $4.2
an H100-hour, October 2026
$50bn
CoreWeave's debt; bonds above 16%
80%
of neoclouds to lose independence by 2030, Gartner
NSCALE'S PROSPECTUS IN EIGHT NUMBERS · S-1, 18 SEP 2026$140.6mrevenue, H1 2026$1.02bnnet loss, H1 2026$103.4bncontracted value461,000GPUs active or contracted52%revenue from one customernot yetbinding financing for the contracts2030spower at Loughton, per UKPN$860mof its rent Nvidia guarantees in Texas

Basis. Market study, no returns. Company figures are as filed or announced, with sterling in brackets at £1 = $1.33. "Our arithmetic" is marked where we have derived a per-MW or per-GPU figure from a published total. Sources in section 4.8.

Chapter 4, in shortGreat contracts, thin balance sheets, and a chip that halves in price

What it is
GPU-hours, sold forward

A megawatt of H100-class compute costs c.£26m to buy and earns c.£7m to £20m a year gross at 70% busy, depending on a rental price that fell from c.$8 an hour in 2023 to c.$2 in 2025 and sits at $2.6 to $4.2 today.

Who, in Britain
Nscale, Nebius, CoreWeave, Civo, Radiant

One is filing to list on $140m of half-year revenue and a $1bn loss; one has £1.7bn committed here; one has $50bn of debt and bonds yielding 16%; one is founder-owned with a 1 GW plan; one is Brookfield's.

How they are funded
Contracts first, chips as collateral

Hyperscaler take-or-pay contracts, GPU-backed loans now rated investment grade, vendor leases, and Nvidia renting back unused capacity. A refinancing wall sits in 2026 to 2028.

For us
Underwrite the customer, not the tenant

A neocloud's credit is its contract book and whoever stands behind it. Our lease should test both: customer concentration, any backstop, whether the financing is in place, and a re-let right if it is not.

4.1 · What it isThe unit is a GPU-hour, and the asset wears out

A compute operator buys accelerators, racks them in a hall, and sells their time: by the hour on demand, by the month reserved, or by the year and the cluster under a take-or-pay contract with a hyperscaler or a lab. The unit of sale is a GPU-hour; the unit of capacity is still a megawatt, because the chips are bought to fill a power budget.

GenerationRackPower a rackGPUs a MW, our arithmeticRental, on demand, Oct 2026
Hopper H100 / H200 (2023–25)8-GPU servers, air or rear-door cooledc.10 to 40 kWc.800 to 1,000 at c.1 to 1.2 kW a GPU all in$2.6 to $4.2 an hour median; $1.6 on the SF Compute market; $7 to $12 at hyperscalers
Blackwell GB200 NVL72 (2025–26)72 GPUs, liquid cooledc.120 to 132 kWc.550c.$8 median; $2 to $6 by tier and term
Vera Rubin NVL72 (2026–27)72 GPUs, liquidc.190 to 230 kWc.330 to 380$9.50 median for B300, Rubin not yet quoted

Rental figures from the Uvik index of 7 October 2026 and the IntuitionLabs comparison, both vendor-maintained; treat as indicative. Each generation puts fewer, dearer chips in a megawatt and asks the hall for liquid cooling.

4.2 · WhoThe compute operators in Britain

WhoWhat they areIn BritainMoney and risk, as publishedRead for us
NscaleUK neocloud, founded 2024, Nvidia holds over 5%; filed an S-1 on 18 September 2026 to list on the NYSELoughton 50 to 90 MW, grid-delayed to the 2030s, lost Microsoft as anchor 18 October 2026 and says it is looking at other power; three BT sites, 14 MW; Stargate UK with OpenAI; sovereign pitchH1 2026 revenue $140.6m (c.£106m), net loss $1.02bn (c.£770m), of which $457m currency; $103.4bn (c.£78bn) of active and contracted value over c.461,000 GPUs; Microsoft up to $43.8bn, Anthropic up to $44.6bn, both conditional on delivery; largest customer 52% of revenue; "has not yet obtained binding commitments for the financing" of the GPUs and sites those contracts needThe strongest demand in Britain; its prospectus also sets out the layer's risk more clearly than any other source. A tenant whose contracts exceed its financing needs a site with power now
NebiusAmsterdam-headquartered, Nasdaq-listed; Microsoft ($17.4bn, New Jersey) and Meta contracts£1.7bn UK programme announced 8 June 2026; 22 MW at Kao Harlow on ten years, hosting its cloud and the Token Factory inference service; three UK clusters, reported at 65 MW by 2027; also Ark LongcrossListed, with hyperscaler take-or-pay behind it; takes fitted halls, not shellsThe best-funded tenant for a fitted hall in Britain; a second-pass call, not a first
CoreWeaveNasdaq-listed US neocloud, the sector's bellwetherDocklands (Global Switch), Crawley (Digital Realty), Scotland (DataVita); c.£2.5bn UK commitment; "leases rather than builds" for speedDebt $35bn at 30 June 2026 and c.$50bn (c.£38bn) by October; shares fell c.15% in the week of 14 October as 2031 bonds yielded above 16% and credit default swaps implied high default odds; backlog $104bn (c.£78bn); Nvidia committed to buy unsold capacity to April 2032; its $8.5bn facility was rated investment grade on the strength of the contracts behind itA $100bn order book has not settled the credit question. Its cost of capital is a guide to the pricing of every neocloud lease
CivoStevenage cloud provider, founded 2015, founder-led; THG took a minority stake in 2021 (c.£1.4m); no venture round found40 UK edge sites planned at c.1 GW combined; first 8 MW in Hertfordshire rising to 38 MW; five more sites of 150 MW secured in Lancashire, Greater Manchester, London and Oxfordshire; "inference at the edge rather than training overseas"; hosted at Kao todayFinancing for the 1 GW programme is not disclosed; it is the first question to askThe closest match to our size and thesis, and the thinnest public balance sheet on the list. A natural tenant if a backstop or a partner stands behind it
Radiant (Ori)Brookfield's AI cloud unit, formed by merging with UK neocloud Ori in February 2026 at a reported $1.3bn (c.£1bn) valuation; part of a $10bn Brookfield AI infrastructure fund with Nvidia among the backersOri's first UK region at Kao Harlow; Ori had £42.5m of net assets at end-2024 and c.$100m of vendor lease finance for its GPUsAimed at sovereign governments, enterprises and telecoms on long contracts, on Nvidia's DSX designBrookfield money behind a UK operator is a covenant a lender can accept
FluidstackNeocloud; headquarters moved from London to New York, December 2025None current; left a €10bn French project to focus on US gigawatt sites with Anthropic and Googlec.$750m raised at $7bn, April 2026; reported borrowing capacity of up to $10bn from Macquarie and others, undisclosed by the company; Google backstops its leases at two US sitesThe template for the backstop structure, not a UK tenant
LambdaUS GPU cloudNo UK site found$926m term loan B rated Baa2, September 2026, the first investment-grade syndicated loan to a private neocloud; c.$1.5bn Nvidia lease-backShows GPU debt going mainstream
DataVitaScottish operatorLanarkshire AI Growth Zone, up to 500 MW; CoreWeave's Scottish host$406m (c.£305m) financing, August 2026The Growth Zone model: too big and too far for us; a reference
The hyperscalers' own regionsMicrosoft, Google (£5bn UK), AmazonOwn campuses and leased halls; also the main buyers of neocloud capacity (Microsoft c.$33bn of neocloud contracts)Investment gradeNot a tenant for a 10 MW shell; often the credit behind one
Sovereign computeThe state as operatorIsambard-AI, Bristol: 5,444 H100s, eleventh in the world in November 2025; Dawn at Cambridge, a six-fold upgrade for £36m; the AI Research Resource to grow twenty-fold by 2030 under a £1bn roadmap; a £500m Sovereign AI Unit; a c.£250m AIRR cloud-compute contract tendered in 2026 for a prime to subcontract to several cloud providersPublic money, slow procurementDemand our tenants can sell into; not a tenant

4.3 · How they are fundedThe capital stack of a GPU

Layer of moneyWho provides itEvidence, 2026What it depends on
Take-or-pay contractsHyperscalers and labsMicrosoft c.$33bn across neoclouds; Nscale's $43.8bn and $44.6bn agreements; Nebius $17.4bn; CoreWeave's $104bn backlogDelivery on time. Most are conditional on the capacity existing, which depends on power
Venture and public equityFunds, Nvidia, the marketNscale c.£1.5bn Series C at c.£11bn and an IPO; Fluidstack $750m at $7bn; Nvidia stakes in CoreWeave, Nebius, NscaleSentiment. The October 2026 sell-off repriced the layer in a week
GPU-backed debtPrivate credit, now banksSector estimate above $20bn; CoreWeave's $8.5bn delayed-draw facility rated investment grade in March 2026; Lambda's $926m Baa2 term loan in September; Fluidstack's reported $10bn capacityContracted cash flows and the chips' resale value. Lenders lend against the contract, then the collateral
Vendor and lease financeEquipment lessors, NvidiaOri's c.$100m from a lessor; Lambda's $1.5bn Nvidia lease-backThe lessor's view of residual value
Vendor backstopNvidiaFrom 1 July 2026 Nvidia rents back unused capacity from partner neoclouds at a fixed rate, giving lenders a utilisation floor; its commitment to CoreWeave runs to April 2032; reports of up to $125bn of backstop within a $500bn financing platformNvidia's own balance sheet and its interest in keeping buyers solvent. Critics call it circular
Customer backstopGoogle, so farLease guarantees at TeraWulf and Cipher in return for warrants over the landlord (chapter 5)The end customer needing the capacity enough to carry the operator's credit risk

The money follows the contract. A neocloud with a signed hyperscaler agreement can borrow; one without cannot, whatever its chips are worth. Maturities are also short. Analysts describe a refinancing wall in 2026 to 2028, as GPU loans fall due before the contracts behind them have paid out. A lease we sign in 2027 puts its tenant inside that window.

4.4 · Life of a GPUWhat a megawatt of chips costs, earns and is worth

ONE MEGAWATT OF H100-CLASS COMPUTE · £M · OUR ARITHMETICKit: c.1,000 GPUs, servers, network£26mc.£26m, bought once; three to six years of lifeGross rental a year at 70% busy£7–20m$1.6 to $4.2 a GPU-hour (Oct 2026 range)Electricity a year, PUE 1.2£2–2.5mc.10.5 GWh at c.£0.19 to £0.24 per kWhHall: fitted at the London rate£1.7mup to £145 per kW a monthHall: our shell plus own fit-out£0.75m£750k a MW, plus £5m to £9m of kit oncePayback on the kit before power, hall and people:1.3 to 3.7 years. After them, 2 to 8 years, or never at 30% busy.WHAT AN H100 IS WORTH · 2023 TO 2028 · INDEX, 2023 = 100202320242025202620272028050100book value, three-year lifebook value, six-year lifehourly rental price, on demandOct 2026: $2.6 to $4.2 an hour,against c.$8 at the 2023 peak

Our arithmetic from published prices: c.1,000 H100-class GPUs in a megawatt at c.£26k installed; rental at $1.6 to $4.2 an hour; 70% utilisation; UK commercial power at c.£0.19 to £0.24 per kWh with PUE 1.2. The right-hand panel indexes the on-demand H100 price to its 2023 peak and overlays straight-line book value at three and six years. Vendor indices, not audited figures.

The return on a megawatt of chips depends on rental price, utilisation and depreciation. The rental price fell about 75% from the 2023 peak to 2025 and has since risen: the one-year H100 contract index was up 38% between October 2025 and March 2026, and several first-party list prices rose again in the autumn. Utilisation decides how much of that price is earned. 81% of enterprises report their GPUs busy half the time or less, one vendor claims about 5% in practice, and UK Power Networks sees data centres draw only 30 to 40% of the capacity they hold. Depreciation is disputed. The hyperscalers book servers over five and a half to six years; some neoclouds use three. A well-known short-seller claims the industry has understated depreciation by c.$176bn for 2026 to 2028. The defence is that older chips move from training to inference and keep earning; CoreWeave has said expiring 2022-vintage H100 contracts re-booked at 95% of the original price.

A megawatt of chips must earn back c.£26m in three to six years while paying c.£2m to £2.5m a year for power and £0.75m to £1.7m for the hall. At today's prices and 70% utilisation it does, with margin to spare. At 30% utilisation, or at the 2025 trough price, it does not. The hall rent is the smallest number in the stack. A tenant in trouble therefore stops paying the landlord last and resumes first, because the chips cannot run without the hall's power.

4.5 · Who has stumbledConsolidation, not yet collapse

4.6 · Why nowWhy the chips still come to Britain

4.7 · What it means for usWill they still be paying in year eight?

4.8 · Sources

Chapter 5

Capacity sale

Layer 4. How a GPU owner finds a buyer, who the buyers are, what sits between them, and the credit structures that have started to stand behind the operator's lease. This layer decides whether our tenant's rent is a bankable cash flow. Chapter 5 of From power to answer.

In shortBuyers have begun to guarantee operators' leases. Ask every bidder who stands behind theirs.
$60bn
Microsoft's neocloud contracts
$860m
of Nscale's rent Nvidia guarantees
414 MW
sold to neoclouds in Europe, 9M 2025, from 133
£250m
the state's research-compute contract
THREE FORMS OF CREDIT SUPPORT BEHIND AN OPERATORA · The customer backstops the leaseGoogle and Fluidstack, 2025On default, Google pays the fee or assumesthe lease. Three US sites, $1.8bn to $3.2bn,$1.4bn, $1.3bn. Paid for in warrants overthe landlord.B · The chipmaker guarantees the rentNvidia, Nscale and Ionic, 2025Nvidia guarantees up to $860m of Nscale'srent on a 234 MW Texas lease for $60m ofwarrants; more warrants if Nscale defaults.C · The chipmaker rents back the capacityNvidia, from 1 July 2026Unused capacity rented back at a fixed rate:a utilisation floor lenders can see.CoreWeave's cover runs to April 2032.None of the three has been seen in Europe. CBRE: European operators charge neoclouds higher rent instead.

Basis. Market study, no returns. Contract values are as reported, with sterling in brackets at £1 = $1.33; where sources conflict, both figures are given. "Our arithmetic" marks a figure we have derived. Sources in section 5.8.

Chapter 5, in shortBuyers have begun to guarantee operators' leases

What it is
Four routes to a buyer

Take-or-pay contracts with hyperscalers and labs; direct sales to enterprises and the state; marketplaces and brokers; and inference platforms that rent capacity and resell it by the token.

Who buys
Five companies, mostly

Microsoft has committed c.$60bn (c.£45bn) across neoclouds; Meta, OpenAI and Anthropic tens of billions more. In Britain the state buys through Crown Hosting, G-Cloud 15 and a £250m research-compute contract.

The structures
Backstops, guarantees, rent-backs

Google guarantees Fluidstack's leases for warrants over the landlord. Nvidia guarantees up to $860m of Nscale's rent to a Texas landlord for $60m of warrants, and rents back unused capacity. Nothing like it in Britain yet.

For us
Ask for the credit support

In the money-flow diagram the rent is the smallest flow. The credit support behind the lease is what a lender prices. Ask every bidder what credit support stands behind them.

5.1 · What it isFour ways to sell a megawatt of chips

RouteWho buysContractShare of the marketWhat it means for the operator's credit
Take-or-payHyperscalers and frontier labsThree to fifteen years, paid whether or not the cluster is used, often with prepayments, conditional on deliveryThe bulk by value: CoreWeave's $104bn backlog, Nscale's $103bn of contracted valueTurns revenue into a receivable a lender will finance. Concentration is the price
Direct enterprise and sovereignBanks, pharma, media, universities, the public sectorReserved capacity by the month or year; public frameworksGrowing; the UK's sovereign programme is one of the largest public buyers in EuropeDiversified but slower to sign and smaller per deal
Marketplaces and brokersDevelopers, start-ups, anyone with a burstBy the hour; resale of unused reserved capacitySmall by value, large by count; SF Compute, Nvidia's Lepton, Vast.ai, ShadeformA utilisation top-up, not a covenant
Inference platformsApplication companies that want tokens, not GPUsPer million tokens or per GPU-minute; the platform rents capacity from operators and resells itTogether AI c.$1.15bn of bookings; Fireworks above $1bn annualised; Baseten c.$600m to $1bnA large, fast-growing wholesale buyer of neocloud capacity, with venture money behind it

5.2 · WhoThe buyers

BuyerWhat they have committed, as reportedIn BritainRead for us
Microsoftc.$60bn (c.£45bn) across CoreWeave, Nebius ($17.4bn to $19.4bn, New Jersey), Nscale (up to $43.8bn, conditional), IREN ($9.7bn, five years, 20% prepaid) and Lambda (undisclosed, multi-billion); booked as operating cost, not capexLeft Nscale's Loughton site in October 2026 for want of power while remaining Nscale's largest customer; own UK regionsThe largest buyer of neocloud capacity in the world, and the one that walked away from a UK site because the grid was late
MetaCoreWeave $14.2bn (September 2025) and a reported c.$21bn expansion to December 2032 (April 2026); Nebius c.$27bn with c.$12bn in the first five yearsNo UK neocloud deal foundSets the scale of a single take-or-pay
OpenAICoreWeave $22.4bn in 2025 across three agreements; Oracle and Stargate; Stargate UK with Nscale, Nvidia and Arm (September 2025), reported paused in 2026Stargate UK's status is unclear in the public recordA lab that signs with neoclouds, and whose UK plans depend on Nscale delivering power
AnthropicNscale up to $44.6bn (conditional); CoreWeave multi-year from April 2026, undisclosed, analysts $4bn to $7bn over five years; Lambda multi-year; US sites with FluidstackVia Nscale's UK contracts, if deliveredConditional on capacity existing; the same dependency on power
GoogleBuys through Fluidstack and backstops its leases (TeraWulf $1.8bn rising to $3.2bn; Cipher $1.4bn; the Texas joint venture $1.3bn); £5bn UK commitmentOwn UK regionsOriginator of the backstop structure we want
The UK public sectorThe AI Research Resource growing twenty-fold by 2030 under a £1bn roadmap; a c.£250m cloud-compute contract tendered in 2026 for a prime to buy from several providers; the £500m Sovereign AI Unit granting GPU hours; Crown Hosting (Ark's joint venture with the Cabinet Office) winning departmental awards; G-Cloud 15 live from 6 August 2026 with AI listings; the MoD's £180m Digital Decision Accelerators framework with an edge compute lotAll of itDemand that must be served onshore by operators who can prove where the data sits. Our tenants' route to it is Crown Hosting, G-Cloud and the AIRR prime
Inference platformsTogether AI ($800m raised at $8.3bn, July 2026), Fireworks ($1.5bn at $17.5bn), Baseten ($1.5bn at c.$13bn, June 2026); all rent capacity and resell itServe UK developers from wherever the capacity sits; UK data residency is a selling point they needA wholesale buyer of our tenant's hours, growing faster than the hyperscalers

5.3 · The intermediariesWhat sits between a GPU owner and a buyer

WhoWhat they areHow they make moneyUK relevance
SF ComputeA real-time market for H100 and H200 clusters, from one node for an hour to thousands for years; owns no GPUs; $40m Series A at $300m, December 2025A fee per trade, reported at c.10%; customers reselling unused capacity recovered c.25% on average (company figure, September 2026)Lets a UK operator sell spare hours and lets a buyer avoid a long contract. It trades hours, not megawatts
Nvidia DGX Cloud LeptonNvidia's marketplace routing developers to partner clouds; launched May 2025 with CoreWeave, Crusoe, Lambda, Nebius, Nscale and others; European additions include Mistral, Fluidstack, Scaleway and Together; AWS and Azure joining; Nvidia has folded its own DGX Cloud back to internal use and pushed Lepton insteadNo published rate card; providers bill at their own rates through NvidiaNscale and Nebius are partners. A channel through which a UK cluster reaches global developers, controlled by the chipmaker
Vast.aiPeer-to-peer market; hosts list machines, renters bid; H100 at c.$2.13 an hour on the community tier, October 2026Commission on rentalsThe price floor for an hour of H100; unreliable hosts cost 20 to 40% more in practice
ShadeformAggregator with one console across more than twenty clouds including Lambda, Nebius and Crusoe; charges the buyer no feePaid by the providersHow an enterprise buys without a procurement team
Inference platforms (Together, Fireworks, Baseten)Rent GPU capacity wholesale, run models, sell tokensMargin between the GPU-hour and the tokenThe fastest-growing wholesale buyer of neocloud hours
The AIRR primeThe winner of the £250m research-compute contract, expected to subcontract to several cloud providersA managed-service marginThe one UK intermediary that buys at scale for the state
Property agentsCBRE, JLL and the rest (chapter 0)Fees on leases and salesPlace shells and halls with operators; do not trade compute

None of the marketplaces buys megawatts. They matter to us only through our tenant's utilisation. A tenant that can sell idle hours into SF Compute or Lepton loses less in a bad quarter.

5.4 · The backstopsThree structures that put a strong name behind a weak one

A. The customer backstops the lease: Google and Fluidstack, 2025

SiteLeaseBackstopGoogle's considerationMechanics
TeraWulf, Lake Mariner, New Yorkc.200 MW to Fluidstack, ten years plus two five-year options, c.$3.7bn initial term$1.8bn (c.£1.35bn), later raised to $3.2bn (c.£2.4bn)Warrants reported at c.8% of TeraWulf, later increasedOn a Fluidstack payment default or insolvency, Google may pay the termination fee or pay the rent due and assume the lease. It is not a guarantee of the landlord's own debt. The landlord then borrows against the guarantee
Cipher Mining, Barber Lake, Texas168 MW IT to Fluidstack$1.4bn (c.£1.05bn)Warrants for c.5.4% of Cipher
TeraWulf and Fluidstack joint venture, Texas168 MW, 25 years, c.$9.5bn$1.3bn (c.£1bn)Further warrants

B. The chipmaker guarantees the rent: Nvidia, Nscale and Ionic Digital, October 2025

Nscale's US subsidiary signed a ten-year triple-net lease with Ionic Digital for the Cedarvale facility in Ward County, Texas: 234 MW and about $2bn (c.£1.5bn) of contracted rent, reported at $65 per kW a month. On 14 October 2025 Nscale issued Nvidia warrants over up to 9,476,700 preferred shares, worth $60m (c.£45m) at an exercise price of a cent, and in return Nvidia agreed to guarantee up to $860.34m (c.£650m) of Nscale's obligations under the lease, reported as the first five years' rent, with further "default warrants" that become exercisable if Nscale defaults on a lease Nvidia has guaranteed. All of this is in Nscale's prospectus. It is the clearest precedent for a landlord of a young operator. The chip supplier stood behind the rent, and the landlord could borrow against it.

C. The chipmaker rents back the capacity: Nvidia, July 2026

From 1 July 2026 Nvidia rents back unused capacity from partner neoclouds at a fixed rate, which gives their lenders a utilisation floor; its commitment to buy CoreWeave's unsold capacity runs to April 2032; reports put the programme at up to $125bn within a $500bn financing platform. This protects the operator's revenue rather than the landlord's rent directly, but a tenant with a revenue floor is better placed to pay its rent.

What Europe has instead

No European or UK backstop of either kind was found. CBRE reports a different response. Capacity sold to neoclouds in Europe rose from 133 MW in the first nine months of 2024 to 414 MW in the same period of 2025, and to 420 MW in the first half of 2026 against 89 MW a year earlier, with 57% of the 2025 volume in the Nordics; and operators are "implementing measures to manage the additional risk", chiefly higher rents to offset build costs. Lawyers in the US note the structures are already evolving from full lease guarantees towards residual-value guarantees, where the customer promises the landlord a floor value at the end rather than every payment along the way.

5.5 · The money flowWho pays whom behind one 10 MW lease

WHO PAYS WHOM BEHIND ONE 10 MW LEASE · £ A YEAR · OUR ARITHMETICEnd customerHyperscaler, lab, enterprise,public sector, or a marketplaceBuys GPU-hours, forwardOperator (layer 3)The neocloud or colo tenantOwns the chips, runs the hallGross £70m to £200m at 70% busyYeats Edge (layer 1)Owns the building andthe 10 MW connectionRent £7.5m a yearChipmakerNvidia: equity stakes, rentsback unused capacity (Jul 2026),guarantees rent for warrantsGPU lenderPrivate credit, banks, lessorsLends on the contract, thenthe chips: c.£260m of kitProperty lenderLends to Yeats against therent, 10 to 15 years; wantsa credit behind the tenantElectricityPassed through at cost:c.£20m to £25m a year at PUE 1.2take-or-pay, £ per cluster-yearrent, £750k per MWdebt servicepower at costinterest and principalrent-back floorrent guarantee to the landlord (Nvidia, Nscale and Ionic, 2025)lease backstop: on default, pay the fee or assume the lease (Google and Fluidstack, 2025)warrants over the landlordin return for the backstopSolid arrows are cash in the ordinary course. Dashed arrows are the credit support that turns a young operator into a bankable tenant. The rent is the smallest flow on the page.

Our arithmetic for a 10 MW shell let at £750k a MW to an operator running c.10,000 H100-class GPUs: gross revenue £70m to £200m a year at 70% utilisation on the October 2026 price range; power c.£20m to £25m a year passed through at PUE 1.2; kit c.£260m once; rent £7.5m. The dashed arrows are the three structures in section 5.4.

The operator's largest outgoings are its chips and its electricity; its rent to us is a few percent of its revenue. Its credit therefore depends on the end customer's take-or-pay commitment, and on whether that customer or the chipmaker provides credit support to the landlord or the lender. A tenant with a named off-taker and a backstop is a different credit from the same tenant without them, in the same building, paying the same rent.

5.6 · Why nowWhy the buyers are starting to stand behind the operators

5.7 · What it means for usLease to the tenant, underwrite the buyer

5.8 · Sources

Chapter 6

Model, app and user

Layers 5 and 6. Who runs models in Britain and who uses them, what a request needs in milliseconds, how far from London a site can sit, which rules pull inference onshore, and what a token is worth. Chapter 6 of From power to answer.

In shortLatency puts the compute in Britain. Power and sovereignty decide where in Britain.
54%
of adults use AI
59%
of urban Britain within 2 ms of Kent
500 to 800 ms
a voice agent's whole budget
600×
cheaper tokens since 2020
WHO USES IT, AND HOW MUCH54%of UK adults used AI, 2026 (Ofcom)79%of 16 to 24s35%of firms with 10+ staff (ONS, Jun 2026)10%of adopters use it extensively29.6mpeople used AI tools in July 2026544OpenAI staff planned for King's Cross3.2 quadrilliontokens a month at Google, May 2026600×fall in token prices since 2020

Basis. Market study, no returns. Adoption figures are official statistics where available (ONS, Ofcom, DSIT) and company-stated where not. The latency arithmetic is ours. Sources in section 6.8.

Chapter 6, in shortLatency puts the compute in Britain; sovereignty and power decide where in Britain

Who uses it
Half the country, a third of firms

54% of UK adults used AI in 2026 (Ofcom), 79% of 16 to 24s; 35% of businesses with ten or more staff use it (ONS, June 2026), but only 10% of those extensively. OpenAI's first permanent London office is sized for 544 staff.

What a request needs
A budget of 500 to 800 ms

A voice agent has to answer in under a second; the model takes 150 to 300 ms of that and the network 50 to 150. Every hop adds 5 to 50 ms. Light in fibre crosses Britain in about 4 ms.

How far from London
Anywhere in Britain, for most work

From a Kent site, 59% of the people in Britain's large urban areas sit within 2 ms one way and 92% within 4 ms. Latency argues for Britain over Virginia, not for Kent over Slough. The exceptions are listed in 6.3.

For us
Sell power and sovereignty, not distance

No UK rule forces inference onshore, but the public sector, the NHS and regulated finance buy as if one did, and the Treasury has started designating cloud providers as critical. A UK-owned landlord with firm power answers part of a tenant's sovereignty question.

6.1 · What it isA request, a budget and a token

At the top of the chain a user sends a request to a model and waits for the answer. What they buy is measured in tokens, roughly three-quarters of a word each. What they notice is latency: the time to the first token and the pace of the rest. Every layer below the user is there to make that wait short and that token cheap. Google alone says it processed 3.2 quadrillion tokens in a month by May 2026, seven times the year before and 330 times the year before that; its APIs run at about 19 billion tokens a minute. Those are company figures, unaudited, but the direction is not in doubt.

Kind of requestWhat "fast enough" meansOf which the modelOf which the networkWhere the compute can be
Chat, search, writing, codeFirst token in under a second; a page in a few secondsMost of itTens of ms, unnoticedAnywhere in Europe; a US region is c.70 ms away and still tolerable
Voice agents, call centresReply in 500 to 800 ms end to end; past a second it feels broken150 to 300 ms first token50 to 150 ms across speech-to-text, model and speech, so each leg must be shortIn the country, on the call path; tail latency (the slowest 1%) is what breaks it
Agents calling tools in loopsEach step tens to hundreds of ms, dozens of stepsMost of itMultiplied by the number of stepsNear the data and the tools it calls
Mobile networks (AI-RAN), vehicles, robotics, tradingMilliseconds, deterministicSmall models1 to 10 ms round trip, or it does not workIn the metro, within c.100 km, or on the device
Batch: documents, images, overnight analysisMinutes to hoursAll of itIrrelevantWherever power is cheapest; Scandinavia and Scotland win

Budgets from vendor and practitioner sources (Nvidia, Telnyx, Ultravox, 2026); they differ at the margin but agree on the ranges. Network legs from the same sources and our arithmetic at 5 µs per km of fibre.

6.2 · WhoThe users and the model-makers in Britain

WhoScale, 2026SourceWhat they buy
Adults54% used AI (Ofcom, April 2026); 59% had used generative AI (DSIT survey, Nov 2025 to Mar 2026); 29.6m people used AI tools in July 2026 (UKOM); ChatGPT took 76% of UK time on AI toolsOfcom, DSIT, IAB UK via UKOMConsumer subscriptions and free use, served from the labs' own regions, mostly abroad
Businesses35% of firms with ten or more staff use AI, from 12% in late 2023; 49% of those with 250 or more; only 10% of adopters use it extensively, averaging 1.6 tools; 58% in information and communication; 55% of employees use AI for workONS, June 2026Enterprise subscriptions, APIs, and increasingly private deployments for regulated data
The labs in LondonOpenAI's first permanent office, 88,500 sq ft at King's Cross for 544 staff by 2027 (April 2026), days after pausing Stargate UK; Anthropic space for c.800; Google DeepMind's home; AI firms took 661,068 sq ft of London offices in the first half of 2026, more than all of 2025Knight Frank, CoStar, pressPeople, not compute: the models are served from their own clouds, with a UK data-residency option from OpenAI under a government memorandum
UK model and product firmsWayve (robotaxis live in London with Uber from 3 September 2026, under 20 cars, a safety driver aboard), Synthesia, ElevenLabs, Stability, PolyAI, Quantexa, Darktrace and the restPressTraining abroad; inference wherever their customers are; the vehicle case runs on the car
The NHS£30m for AI diagnostics in 2026, £20m of it to put a chest X-ray tool in every English trust by 2029; a £900m AI framework for 2027 to 2035 with radiology among eight lotsDHSC, NHS EnglandModels that run against patient data, bought through frameworks; hosting allowed offshore since 2018 guidance, but supplier standards increasingly say "operated within the UK"
Government and defenceThe Ministry of Justice's OpenAI deal; the compute roadmap's warning of a 5 GW UK compute gap by 2030 without intervention; the MoD's edge compute lot; AI-RAN trials on EE's live network in Birminghamgov.uk, MoD, BTSovereign-labelled capacity, slowly
Regulated financeAWS, Google, Microsoft and Oracle designated critical third parties from 13 July 2026; a single incident and third-party reporting framework from March 2026; the Treasury Committee pressing for AI providers to be designated nextHM Treasury, FCA, PRAResilience and auditability first; a named UK site is a comfort

6.3 · How far from LondonThe rings

Kent siteUrban area within 2 ms one way of the site (size = population)Urban area beyond 2 msRings: one-way fibre latency at 5 µs per km over a route 1.4 times the straight line.1 ms · 33% of people2 ms · 59% of people4 ms · 92% of people

Our arithmetic. Dots are the 45 largest urban areas of Great Britain, c.33m people, sized by population. Rings are one-way fibre latency from a site at Ramsgate, Kent, at 5 microseconds per kilometre over a route 1.4 times the straight-line distance; double them for a round trip. Within 1 ms: 33% of those people (London). Within 2 ms: 59%, to Birmingham and Southampton. Within 4 ms: 92%, to Manchester, Leeds and Cardiff. Glasgow and Edinburgh sit at about 5 ms.

A Kent site reaches every English city in under 4 ms one way. A Virginia region is about 35 ms away; Amsterdam and Frankfurt are 3 to 5 ms. Latency therefore argues for Britain over abroad, not for one British town over another. For chat, agents and documents, Kent, Slough and Manchester are indistinguishable to the user. The exceptions are metro-scale. Mobile networks, vehicles, robotics and voice at scale want their compute within a millisecond or two, which is a circle of 100 to 150 km around the people, and for 59% of Britain's urban population a Kent site is inside that circle. Residential measurements agree: Edinburgh to London on an ordinary broadband line is about 14 ms round trip, London to Amsterdam about 6, London to Frankfurt about 9.

The map does not show Kent's subsea landings. The cables that join Britain to the Continent land on its coast: EXA's Margate to Ostend route opened in 2025, and a new system is planned for Dumpton Gap by Broadstairs, a landing station used before. A site in east Kent is as close to Brussels and Amsterdam as it is to Birmingham. That matters to a tenant selling into Europe from a British address.

6.4 · SovereigntyThe rules, and what buyers do in practice

Rule or habitWhat it saysEffect on where compute sits
UK GDPR, Data Protection Act 2018, Data (Use and Access) Act 2025Lawful transfer abroad with safeguards; no residency mandatePermissive in law; the burden of proof sits with the exporter
Government cloud guidanceNo policy prevents a department storing or processing data in any particular country, but it must weigh the implications; there is no formal UK sovereign cloud policy (Pinsent Masons); a national cloud strategy has been promisedPermissive; departments increasingly choose UK anyway
NHS offshoring guidance (2018) and supplier standardsPublic cloud, including offshore, is allowed after a risk assessment; some NHS England supplier standards require every component of a solution to be operated within the UKMixed; the newer standards point onshore
Critical third parties regime (HM Treasury, FCA, PRA), from 13 July 2026AWS, Google, Microsoft and Oracle designated; regulators to assess AI and cloud providers for further designation; unified incident reporting from March 2026Not residency, but resilience: regulated firms must show where their critical services run and how they fail over
The labs' own movesOpenAI offers UK data residency under its government memorandum and signed the Ministry of Justice; the sovereign AI programme grants GPU hours on IsambardThe buyers' preference is being met commercially before it is legislated
The US CLOUD Act argumentVendors (Civo and others) sell UK-owned, UK-incorporated hosting as the only way data stays under UK lawA marketing position with legal weight; it favours UK-owned operators and landlords

As with the credit support behind leases in chapter 5, buyers are moving ahead of the rules. No statute makes a bank or a hospital keep its inference in Britain; most of them choose to anyway.

6.5 · What a token is worthDeflation at the top, inflation underneath

MeasureFigureSource
Fall in token prices, 2020 to 2026c.600-foldarXiv 2603.28576, 2026
GPT-4 at launch, input, per million tokens$30OpenAI pricing, 2023, via press
GPT-5, input and output, per million$1.25 and $10OpenAI pricing via press (secondary)
Economy-tier price for comparable quality$0.10 per millionarXiv, Gemini Flash example
Blended index low$0.97 per million, 31 Aug 2026Silicon Data
Frontier prices versus March 2023down 84%; but up 72% year on year in September 2026BenchLM index
Enterprise spend per million tokensc.$10 to c.$2.50 in a yearRamp data via press
Google tokens a month9.7 trillion (2024), 480 trillion (2025), 3.2 quadrillion (May 2026)Google I/O, company-stated

The price of a token has fallen by two orders of magnitude while the number of tokens has risen by more. The hour of compute underneath them got dearer in 2026 (chapter 4). The industry calls this the Jevons effect: cheaper inference leads to more of it. For the layer above us it means thin margins and constant repricing. For the layers below it means demand for GPU-hours keeps rising even as the price of their output falls. The operators who run inference cheapest per token, near their users and with power they already have, keep the work.

6.6 · Why nowWhy the users are pulling the compute towards them

6.7 · What it means for usSell power, sovereignty and timing, not distance from London

6.8 · Sources

Chapter 7

Money

Thread A. The chain's finance in one place: who funds each layer, what their money costs, where the debt is sized, and what a lender will and will not lend on, from Ofgem's allowed returns to a GPU loan at ten per cent. Chapter 7 of From power to answer.

In shortMoney gets dearer at every layer. A signed contract brings it back down.
6.08%
Ofgem's real cost of equity, ED3
£2.45bn
Virtus's bank package, thirteen banks
5.9% / 16%
a GPU loan with and without a contract
$725bn
big-four capex, 2026
THE COST OF MONEY, LAYER BY LAYER · PERCENTNetwork transactions, implied cost of equity4.3%GPU loan with a hyperscaler contract (CoreWeave DDTL 4.0)5.9%GPU loan with Nvidia's guarantee (Nscale, Texas)6.05%Ofgem ED3 cost of equity, real, early view6.08%Our term debt against rent, sterling6.5%Lambda term loan, Baa26.64%GPU loan without the contract (DDTL 5.0)8.03%Neocloud unsecured notes9.75%GPU loan, DDTL 6.0, yield to maturity10.44%First GPU loan at scale, 202315%CoreWeave 2031 bonds, mid-October 202616%Rates as published in 2026; dollar loans quoted all-in over SOFR; our debt at the sterling range seen in 2026. The gap between 5.9% and 16% is what a signed hyperscaler contract is worth to a borrower.

Basis. Market study, no returns. Costs of debt and allowed returns are as published; rates quoted in the currency of the deal. The description of our own layer is of structure, not outcome. "Our arithmetic" is marked. Sources in section 7.8.

Chapter 7, in shortThe cost of money rises with every layer, and a buyer's contract brings it down

Cheapest
The grid, at c.6%

Ofgem's early view for ED3 allows a 6.08% real return on equity at 60% gearing and a debt allowance of c.5.5% to 6.2% nominal. Engie paid a c.50% premium to UKPN's regulated asset base, implying a cost of equity of about 4.3%.

Middle
Buildings and halls, at 5% to 7%

Property and infrastructure debt against rent: Virtus's £2.45bn from thirteen banks, Yondr's £532m AA-rated securitisation, Pulsant's £187m. Prime UK data centre yields 5.5% to 6.5%.

Dearest
The chips, at 6% to 16%

A GPU loan costs SOFR plus 2.25% with a hyperscaler contract behind it and SOFR plus 5.50% without; CoreWeave's unsecured notes pay 9.75% and its bonds yielded 16% in October. The difference is the absence of a buyer's contract.

For us
Borrow at the building's rate, and fund none of the chips

Our debt is sized on capacity rent from a tenant whose own debt is priced on its contracts. Lease terms that let a property lender see through to those contracts are worth more to us than a point of rent.

7.1 · The stackWho funds what, and at what price

CAPITAL STACK BY LAYER · SHARE OF DEBT (TEAL) AND EQUITY (GREY) · INDICATIVEDEBTEQUITY0 · Grid (DNO)c.60% debtRegulated asset base: Ofgem notional gearing 60%Debt allowance c.5.5–6.2% nominal; equity 6.08% CPIH-real (early view)Equity: Engie, National Grid, Iberdrola, Berkshire Hathaway, SSE1 · Powered site (us)c.60% debtProperty: development debt at purchase, refinanced on the rent once letTerm debt c.6–7%; sized on capacity rent only, cover c.1.25x+Equity: Property and programme equity2 · Fitted hallc.55% debtInfrastructure: bank clubs, ABS, private creditVirtus £2.45bn, 13 banks; Yondr £532m ABS rated AA; nLighten £85m private creditEquity: Antin, I Squared, Macquarie, Infratil, L&G, Elliott, DigitalBridge, Brookfield3 · Computec.50% debtGPU-backed loans in bankruptcy-remote vehicles, vendor leases, bondsSOFR+2.25% (5.9%, A3) on hyperscaler contracts; SOFR+5.50% (10.4%) without; unsecured 9.75%; bonds 14–16% in a bad weekEquity: Venture funds, Nvidia, the public market4 · Buyerc.15% debtHyperscaler balance sheets; neocloud contracts booked as operating costInvestment-grade bonds; c.$725bn of capex in 2026, c.$1tn in 2027Equity: Shareholders of Microsoft, Alphabet, Amazon, Meta5 · Model and appc.5% debtVenture equity, subscriptions, public frameworksLittle debt; Fireworks $1.5bn at $17.5bn, Baseten $1.5bn at c.$13bnEquity: Venture and growth fundsDebt shares are typical structures, not any one company. Costs of debt as published in 2026; sterling and dollar rates shown as quoted.

Debt shares are typical structures by layer, drawn from the sources in this chapter; no single company is depicted. Costs as published in 2026. Leverage falls and the cost of money rises from the regulated grid to the venture-funded application.

7.2 · Layer by layerThe lenders, the equity and the rules they lend by

LayerWho provides the moneyWhat it costs, as publishedWhat the lender lends onWhat the lender will not lend on
0 · GridRegulated utilities with infrastructure owners behind them: Engie (UKPN, £10.5bn equity value, May 2026), National Grid, Iberdrola, Berkshire Hathaway Energy, SSE. Reinforcement is funded by the DNO and recovered from all usersED3 early view: cost of equity 6.08% CPIH-real at the midpoint (range 5.10% to 7.05%), notional gearing 60%, debt allowance c.5.50% rising to 6.19% nominal over 2028 to 2033; transaction premiums of c.50% to the asset base imply investors accept c.4.3%The regulated asset base and the price control. The cheapest capital in the chain, by designAnything outside the allowance: a customer's sole-use works are paid by the customer
1 · Powered siteProperty equity and property debt. In our structure, development debt at purchase, refinanced on the rent once the lease is signed, with debt sized on capacity rent alone and never on revenue share; three gates (the DNO's confirmation of the connection, the operator agreement, funding) before capital is committedTerm debt c.6% to 7% in 2026 sterling; prime UK data centre yields 5.5% to 6.5% (Savills, H1 2026); a US powered shell at a 5.0% cap rate against 6.5% for turnkey (Loudoun, 2026)Firm rent from a creditworthy tenant on a long lease, the re-let value of the building, interest cover of 1.25x or more, loan-to-value of 50% to 60%, and a firm connection in writingRevenue share, turnover top-ups, uncontracted capacity, a connection that is Indicated rather than Confirmed, or a tenant whose rent it cannot see through to a contract
2 · Fitted hallInfrastructure equity (Antin at Pulsant, I Squared at nLighten with more than $500m committed, Macquarie's 40% of Virtus, Infratil and L&G at Kao, Elliott at Ark with TPG in talks at c.$5bn, Brookfield's $10bn AI fund, BlackRock's £500m with Gravity Edge, L&G's new €600m digital fund, ICG's €3.15bn); bank clubs; securitisation; private creditVirtus £2.45bn from thirteen banks led by BNP Paribas, Crédit Agricole, Société Générale and Standard Chartered, September 2026, with £1.2bn of green capex facilities; Yondr £532m of term notes against two Slough halls let to a hyperscaler, rated AA by Fitch, March 2026; Pulsant £187m over five years, October 2025; nLighten £85m led by Rivage, secured on nine UK sites of 10 MW rising to 20 MW, March 2026; Echelon €1.7bn from Morgan Stanley; Maincubes €1.8bn from twelve lenders; Segro and Pure publish a 9 to 10% net yield on costContracted kW with hyperscalers and large enterprises, DSCR, loan-to-cost on development, the operator's track record, ESG criteria increasingly written into the marginSpeculative halls without pre-lets at scale; neocloud tenants without credit support, for which operators charge more rent instead
3 · ComputeVenture and public equity (Nscale's c.£1.5bn Series C and IPO; Fluidstack's $750m; Nvidia's stakes); GPU-backed loans in bankruptcy-remote vehicles; vendor leases; unsecured bondsOne borrower's history shows the range. CoreWeave's first GPU loan in 2023 cost c.15%; its second in 2024 SOFR plus 6.00% (11.3%); its fourth in March 2026, $8.5bn against Meta's contracts, SOFR plus 2.25% floating or 5.9% fixed, rated A3; its fifth in May 2026, without that contract quality, SOFR plus 4.50% (8.0%, Ba2); its sixth SOFR plus 5.50% (10.4% to maturity); its unsecured notes 9.75%; its bonds above 16% in the week of 14 October. Elsewhere: Lambda SOFR plus 3.00% (6.6%, Baa2); Nebius SOFR plus 2.50% (6.1%); IREN's Microsoft-backed facility SOFR plus 2.25% (5.9%, rated A); Nscale's Ward County facility SOFR plus 2.375% (6.05%, Baa1) behind Nvidia's guaranteeContracted cash flows from a named customer, ring-fenced in a special-purpose vehicle, with the chips as secondary collateral amortised over three to four years; a vendor or customer backstop where one existsSpot or on-demand revenue; chips older than a generation; a borrower's corporate credit on its own; the same company borrowed at 5.9% and 10.4% in the same year
4 · BuyerHyperscaler balance sheets and investment-grade bonds; neocloud contracts sit in operating costs, not capex, which is part of their appealAmazon, Microsoft, Alphabet and Meta guided c.$725bn of capital spending for 2026, up c.77% on 2025; Alphabet raised its range to $195bn to $205bn in July; Moody's puts the wider group at $785bn in 2026 and close to $1tn in 2027Their own shareholders and bondholders lend on cash flow from advertising, cloud and software; the AI spend is the use of funds, not the securityThe buyers are the credit the rest of the chain borrows against; they borrow against nothing in it
5 · Model and appVenture and growth equity; little or no debtFireworks $1.5bn at $17.5bn; Baseten $1.5bn at c.$13bn; Together $800m at $8.3bn; the three at c.$1bn of annual revenue each; OpenAI and Anthropic in the tens of billionsGrowth, not collateralThere is no debt at this layer; equity carries the risk

7.3 · Where the debt is sizedThree sizing rules

  1. The regulator sizes the grid's debt at a notional 60% of the asset base and allows a return for which the market has paid a 50% premium. The connection a building holds was financed at this rate, which is why it is cheap to own and expensive to replace.
  2. The property lender sizes our debt on the rent: the capacity rent of £750k a megawatt, from a tenant it can underwrite, at a cover ratio it can defend, against a building it could re-let. In our structure, development debt is drawn at purchase and the site is refinanced when the lease is signed. Only rent counts in the sizing. Revenue share, if it ever existed, would be equity upside only; the Edge rules exclude it in any case.
  3. The GPU lender sizes the tenant's debt on the tenant's contracts. The spread between a loan at SOFR plus 2.25% and one at SOFR plus 5.50% is the difference between a Meta contract behind the chips and no such contract. The lender lends on the buyer's contract and holds the chips as secondary security.

Rules two and three meet at our lease. The property lender asks who our tenant's customer is, because the tenant's ability to pay rent in year eight depends on its contract book and its own lenders' patience. A lease that gives the landlord sight of the tenant's contracts, a deposit or guarantee where the covenant is thin, a short cure period and a clean re-let right is a lease a property lender will advance more against. The credit support behind the lease, set out in chapter 5, therefore matters to our layer even though we never fund a GPU.

7.4 · The cost of money, in one table

InstrumentRate, as publishedWho, when
Allowed cost of equity, distribution networks (CPIH-real, early view)6.08%Ofgem ED3 methodology, 21 May 2026
Allowed cost of debt, distribution networks (nominal, average 2028 to 2033)5.86%Ofgem ED3, same
Implied cost of equity from UKPN and other network transactionsc.4.3%Ofgem ED3 market-to-asset ratio analysis
Prime UK data centre yield5.5% to 6.5%Savills Spotlight, H1 2026
Powered shell and turnkey cap rates, Northern Virginia5.0% and 6.5%Loudoun County guidelines, 2026
Fully fitted development, net yield on cost9% to 10%Segro and Pure, Park Royal
Data centre securitisation, UK, rated AAcoupon not publishedYondr, £532m, March 2026
GPU loan with a hyperscaler contract, investment gradeSOFR + 2.25% (c.5.9%)CoreWeave DDTL 4.0, March 2026; IREN–Microsoft facility
GPU loan with a chipmaker's guaranteeSOFR + 2.375% (c.6.05%), Baa1Nscale, Ward County, 2026
GPU loan, sub-investment gradeSOFR + 4.50% to 5.50% (8.0% to 10.4%)CoreWeave DDTL 5.0 and 6.0, 2026
Neocloud unsecured notes9.75% couponCoreWeave, April 2026
Neocloud bonds in a bad weekabove 16% yieldCoreWeave 2031 notes, mid-October 2026
First GPU loan ever made at scalec.15%CoreWeave, 2023

The grid borrows at about six because the regulator guarantees its revenue. A building borrows at six or seven because a lease is a contract and the building has another use. A fitted hall borrows at a little more because the fit-out has one use. The chips borrow at six when a hyperscaler has signed and at ten or sixteen when it has not. At every layer the rate falls when a buyer's commitment stands behind the cash flow.

7.5 · The money that is newThree things that did not exist two years ago

The money that is old is also moving. Infrastructure funds that used to buy towers and fibre now buy halls: Antin, I Squared, Macquarie, Infratil, Brookfield, Elliott, and the new L&G and ICG funds. Their cost of capital sits between the property lender's and the venture fund's. Their appetite is for platforms of many sites, and a regional edge operator is one.

7.6 · Why nowWhy the capital is arriving faster than the power

7.7 · What it means for usSix rules for our layer

7.8 · Sources

Chapter 8

Paper

Thread B. The documents that carry a megawatt from the substation to the user: the connection agreement, the planning consent and the rules that come with it, the operator lease clause by clause, the credit support behind the lease, the power contract, and the data obligations that follow the tenant in. Chapter 8 of From power to answer.

In shortDraft the lease for the lender and for the next tenant.
DCP181
terms survive a change of occupier
8 Jan 2026
data centres can opt into the national regime
+22%
South East data centre rateable values
14
clauses in one lease
SEVEN RULES FOR THE PAPER1Connection stayswith the building2Planning per site,before exchange3Rent is rent4The intake is theline5Yield-up leavesthe hall6Credit supportscheduled, notpromised7Power nevertouches our books

Basis. Market study, not legal advice. Clauses are heads for discussion, drawn from published law-firm guidance and the Edge method's own lease checklist; the solicitors draft. Regulatory positions are as published to 31 October 2026 and several are still moving. Sources in section 8.9.

Chapter 8, in shortSix documents, and the clauses that matter in each

The connection
Held by the landlord

A connection agreement names a customer and a capacity. Bilateral terms now survive a change of occupier, and capacity cannot be cut without the customer's agreement. Keep the agreement in the building's name and let the tenant take the supply.

The consent
Case by case, and moving

Data centres have no use class; a shed may already be lawful, an office is not. They can opt into the national regime since January 2026, are critical national infrastructure since 2024, and may in time be required to supply waste heat to a network.

The lease
Scope splits at the intake

Triple net, 10 to 15 years, rent per MW of firm supply, indexed. Landlord scope stops at the intake switchgear; tenant scope starts there. Yield-up is the most negotiated clause in the market. Under our form the tenant leaves the hall fit-out and removes the compute.

For us
Write it for the lender and the next tenant

Two parties who do not sign the lease will read it closely: the bank that sizes debt on the rent, and the operator who takes the hall after this one. Draft with both in mind.

8.1 · The paper trailWhat moves the megawatt, and who signs it

DocumentPartiesWhat it fixesWhere it goes wrong
Connection agreement and connection offerDNO and the customer (owner or occupier)The agreed supply in MVA, the point of supply, firm or non-firm, the sole-use works, milestonesAgreement in a departed occupier's name; capacity de-energised and reviewed; "firm" undefined
Planning permission and conditionsLocal planning authority, or the Secretary of State under the national regimeThe lawful use, hours, noise at the boundary, generators and fuel, heat rejection, landscapingUse not lawful for compute; a noise condition the dry coolers cannot meet; a residential neighbour
Agreement for lease and fit-out guideLandlord and tenantWhat the landlord builds, what the tenant may install, the technical protocol, the long-stopScope creep across the intake; a long-stop the DNO cannot meet
Operator leaseLandlord, tenant, guarantorRent, term, scope, operations, alterations, assignment, default, yield-up (section 8.4)Rent that is not rent; a yield-up that leaves the landlord a chiller
Credit supportGuarantor, off-taker or chipmaker, landlord, lenderWho pays if the tenant does not (section 8.5)A guarantee of the wrong thing, for the wrong period, from an entity that can walk
Supply contract and meteringTenant and electricity supplier; DNO for the MPANWho buys the power, at what price, through whose meterPower through the landlord's books; a pass-through that turns into a trading business
Facility agreement and direct agreementLandlord and property lender; tenant acknowledgesDebt sized on rent; lender's step-in and cure rights; no lease variation without consentA lease the bank was not shown
Data and security scheduleTenant with its customers; landlord for the buildingUK GDPR and the 2025 Act, ISO 27001, breach procedure, who may enterA landlord promising data obligations it cannot perform

8.2 · The connection paperWhose name is on the megawatt

8.3 · The consent paperPlanning, designation and the duties that follow

InstrumentPosition at October 2026For a 10 MW conversion
Use classNone. Authorities treat data centres as B8 storage, sui generis, or occasionally Class E; a parliamentary answer in 2026 says the class "will depend on the individual circumstances", and office to data centre "will generally" need permission. A London committee in February 2026 approved a data centre as B8 on a warehouse site; a change to or from sui generis always needs permissionA shed or print works may already be lawful; a call centre or office is not. Pre-application advice or a lawful development certificate per site, before exchange
National regime (NSIP)Since 8 January 2026 a data centre may ask the Secretary of State for a section 35 direction to be consented nationally; no size threshold is set; a national policy statement is in preparationIrrelevant at our size, but it tells councils what Whitehall wants
Critical National InfrastructureDesignated September 2024; "Critical National Priority" status for grid access under consideration in 2026A line in the planning statement and the tenant's sovereignty case
Planning and Infrastructure Act 2025Royal Assent 18 December 2025; the powers behind the strategic-demand prioritisation of chapter 1Watch for the distribution-level process
NoiseConditions set separately for commercial and residential receivers; dry coolers are the loudest plant and run at about 87 dB close to; acoustic reports are standardScreen for residential neighbours before buying; put the yard on the far side
Heat network zoningEngland's zoning regime names data centres as heat sources; no duty to supply yet, but the regulations "expressly envisage" one; government is "looking at how waste heat from data centres can be used"A future obligation on the tenant's cooling; reserve the right to connect in the lease
Business rates2026 list from 1 April 2026: data centre rateable values up 16% in London and 22% in the South East (Knight Frank); a new multiplier of 50.8p for values above £500,000, which covers about 90% of data centres; the VOA values modern facilities on a "rentals plus" basisThe tenant's cost under a triple-net lease; a 10 MW site will cross the £500,000 line
Fire and batteriesBuilding Safety Act 2022 governs; lithium UPS batteries bring thermal-runaway risk; UK practice borrows the US standard NFPA 855 (separate battery rooms above 600 kWh)Tenant's fit-out; the lease should require compliance with a named standard
Energy performanceMEES applies to non-domestic lettings; data centre halls are often argued out of EPC scope; the position variesCheck the EPC position per building before marketing

8.4 · The leaseOne operator lease on one page

ONE OPERATOR LEASE ON ONE PAGE · POWERED SHELL · HEADS FOR DISCUSSION, NOT DRAFTINGLANDLORD-LEDTENANT-LED1 · Parties and termLandlord: Yeats Edge site company. Tenant: the operator. Guarantor: parent or off-taker where the covenant needs it. Term 10 to 15 years; tenantrenewal options; no landlord break.2 · DemiseThe building, yard and intake room; the right to use the agreed supply of X MVA at the point of supply. Space is never the measure; the megawatt is.3 · Rent£750k per MW of firm supply a year, quarterly in advance, indexed annually (collar and cap stated). No turnover rent, no revenue share. Phased MW onlyagainst binding dates.4 · PowerConnection agreement held by the landlord; supply contract and MPAN in the tenant's name; electricity at cost, never through the landlord. PUE anddensity declared; consumption capped at the agreed supply.5 · Landlord scopeStructure, envelope, security line, welfare, base fire, the connection and the intake switchgear and metering. Landlord repairs these; nothing insidethe intake.6 · Tenant scopeEverything beyond the intake: distribution, UPS, generators, cooling, data-hall fire, fibre, racks, compute. Tenant installs, insures, maintains,refreshes and removes.7 · OperationsNoise limits at the boundary (dry coolers), fuel storage, heat rejection and any heat-network duty, hours of works, access protocol with tenant escortto secure areas.8 · Alterations and refreshFit-out guide and technical protocol agreed at AFL; kit turns every 3 to 5 years at the tenant's cost; landlord consent not unreasonably withheldinside the intake, never required for racks.9 · Assignment and sublettingAssignment to a substantial operator with consent; subletting of halls to colocation customers permitted on notice; no operator group above 50% ofplatform capacity.10 · Credit supportDeposit or parent guarantee where the covenant needs it; the off-taker's or chipmaker's backstop (assume-or-pay, rent guarantee, or residual value)scheduled to the lease.11 · Default and re-letShort cure period; landlord re-let right; step-in for the off-taker; lender's right to cure. The hall fit-out stays; the compute goes.12 · Yield-upTenant removes compute and what the landlord elects; leaves the hall fit-out and connection intact; makes good to the shell; no dilapidations claimfor the landlord's own scope.13 · Security and dataSecurity schedule: policies, breach procedure, ISO 27001; tenant carries UK GDPR and DUAA duties; landlord warrants UK ownership and siting for thetenant's sovereignty case.14 · Lender provisionsDirect agreement with the property lender; the tenant's contract book disclosed on request; no lease variation without lender consent.

Heads for a powered-shell operator lease, drawn from the Edge method's lease checklist, Hogan Lovells' note on UK data centre leases (30 September 2025), BCLP's note on shell-and-core structures (23 October 2025) and Gowling WLG's note on colocation agreements (16 April 2025). Teal markers are the clauses the landlord should lead; grey the ones the tenant will. Solicitors draft; this is the commercial brief.

BCLP reports that leases are "almost always triple net", that deposits of six to twelve months' rent and parent guarantees are typical for smaller tenants, and that the yield-up clause is "one of the most heavily negotiated", with most developers requiring tenants to strip the fit-out back to shell. Our position on yield-up is the reverse. The hall fit-out is what the next operator wants, so the tenant leaves it and removes the compute. Hogan Lovells says the lease must state who maintains the "core infrastructure, such as power and cooling systems". In a fitted hall that is the landlord; in our shell it is the tenant, and the lease must say so without ambiguity because the lender's engineer will read it. Gowling WLG notes that the operator "does not own, provide or manage" the customer's equipment, and that the agreement must give the operator rights if equipment is not removed at the end. The same right belongs in our lease against the tenant's compute.

8.5 · The credit paperWho pays if the tenant does not

InstrumentWhat it doesPrecedentOur ask
Rent depositCash held against arrears; six to twelve months typical for smaller tenantsBCLP, UK marketOnly where a covenant needs support; substantial tenants are not asked for a fixed deposit
Parent company guaranteeThe tenant's parent stands behind the leaseStandardAlways, where the tenant is a site company
Rent guarantee from a third partyA chipmaker or off-taker guarantees the rent for a periodNvidia guaranteed up to $860m of Nscale's rent to its Texas landlord for $60m of warrants (chapter 5)Ask every bidder; decide beforehand what we give
Assume-or-pay backstopOn tenant default, the off-taker pays the termination fee or takes the leaseGoogle at TeraWulf and CipherThe preferred form: it gives the building a second tenant on day one
Residual value guaranteeA floor on the asset's value at the end rather than every payment along the wayEmerging in the US, per Vinson & ElkinsAcceptable for a lender; weaker for us than assume-or-pay
Direct agreementLender's right to notice and to cure the tenant's default; tenant's acknowledgmentStandard in financed leasesRequired by any lender; draft it at the start

8.6 · The power paperPass-through, private wire and the licence

8.7 · The data paperWhat follows the tenant in

8.8 · What it means for usSeven rules for the paper

  1. Connection agreement. It stays with the building. Before exchange, have the DNO confirm in writing that DCP181 and DCP114 apply to each site.
  2. Planning. Before exchange, per building: a lawful development certificate or pre-application view on the compute use, a noise screen for residential neighbours, and the EPC position.
  3. Rent. Per MW of firm supply, indexed with a collar and cap, phased only against binding dates. No turnover rent or revenue share; nothing else counts towards the rent the lender sizes on.
  4. Scope. Landlord scope ends and tenant scope begins at the intake switchgear. Both are listed in a schedule, in plant terms, with the fit-out guide agreed at the agreement for lease.
  5. Yield-up. The hall fit-out stays; the compute goes; the landlord elects what else is removed. Put this in the first heads of terms, because the market default is the reverse.
  6. Credit support. Scheduled to the lease, not promised. Parent guarantee always; deposit where needed; the off-taker's or chipmaker's backstop as a schedule, with a direct agreement for the lender.
  7. Power. Supply contract in the tenant's name; landlord metering for information only; a reduced-draw right to protect the connection; no multi-tenant distribution until the licence exemption is checked.

8.9 · Sources

Chapter 9

What it means for us

This chapter draws the eight before it into one set of conclusions: where we sit on the chain, what we need from the layers around us, who we lease to and what we ask of them, what we offer in return, and what we do in the next ninety days. Chapter 9 of From power to answer.

In shortWhat is missing is not money or demand. It is a megawatt that exists.
5
first calls
10
questions for every bidder
3
options for what we give
90
days
THE NEXT NINETY DAYSDays 1 to 30Two DNO letters on the seed sitesPlanning view per siteThe one-page packThe backstop decision, in writingDays 31 to 60Five calls in one week: Nscale, Civo,Radiant, Pulsant, nLightenOne agent retained, two soundedTwo lenders shown the lease headsDays 61 to 90TT Group on exchanges with real MVAShortlist two bidders; term sheetsWatch list reviewed: Curate decision,DCP463, Ark sale, AIRR award

Basis. Everything here rests on the evidence in chapters 1 to 8. Market study, no returns. For discussion between the partners.

The study, in shortBritish users need compute in Britain, there is not enough of it, and the scarce input is a connected megawatt

Our position
Layer 1, and never above it

We own the building and the connection and lease them per MW of firm supply. Our scope ends at the intake switchgear. Above it the cost of capital doubles and the asset wears out in three years; below it, at the grid, the revenue is guaranteed by the state.

The product
A connected building in Britain, available this decade

We do not sell proximity to London. Latency puts the compute in Britain; sovereignty and grid access decide where in Britain. A 10 MW building with its supply in hand sits outside every queue, fee and milestone the regulator has written since 2025.

The tenant
An operator whose end customer we can see

The tenant is a neocloud or a regional colocation operator; the credit is its customer. We underwrite the contract book, ask what its GPU debt costs, and ask who stands behind the lease.

The paper
Seven lease rules, drafted for the lender and the next operator

Neither signs the lease, but both read it: the lender sizes debt on the rent, and the next operator takes the hall after this one. Yield-up leaves the hall in place; power never passes through our books; the connection stays with the building.

9.1 · The seatThe chain, and our position on it

THE CHAIN, WITH OUR POSITION MARKED · WHAT WE NEED FROM EACH LAYERLAYER 0GridWrittenconfirmation: agreedMVA, firm, point ofsupply, surviving achange of occupierLAYER 1Powered siteOur position. Buy atbuilding prices;scope ends at theintake switchgear;debt sized on rentonlyLAYER 2Fitted hallA tenant that fitsout and sells kW;PUE and densitydeclared; fit-outstays at the endLAYER 3ComputeA tenant whosecontracts we cansee; the cost of itsGPU debt shows itscreditLAYER 4Capacity saleThe credit supportbehind the lease:who stands behindit, and in what formLAYER 5Model and appSovereignty wordingin the pack; latencycited only for thetenants it matterstoLAYER 6UserIn Britain, withpower, this decadeRead left to right: the DNO's confirmation, our building, the tenant, the tenant's customer, the user. Our position does not change; the rest is what we ask of each layer.

9.2 · What each chapter foundEight findings, eight consequences

ChapterWhat it foundWhat follows for us
1 · GridThe demand queue stood at 96 GW at transmission and 29 GW at distribution by June 2025; 11 to 13 GW can connect before 2030. Every reform since bites on large, new, speculative applications and none on a building that already holds its supply. 1,029 primaries publish 10 MW spare today; UKPN holds 251 of themBuy a building with an agreed connection, not one with an application pending. Confirm the agreed supply, the point of supply and survival on change of occupier in writing before exchange. Kent and London are the right DNO
2 · Powered siteThe market prices a connection at c.£0.7m to £1.2m per grid MW in the London hub. The listed landlords are moving up to fitted halls at 50 MW+; the exchange owner sells to housebuilders; nobody does 5 to 15 MW in existing buildings at scale. Our rent is c.43% of a fitted London rate for a quarter of the capitalBuy at building prices and lease at power prices. Say whether a megawatt is grid or IT load. Open talks with TT Group on exchanges with real MVA. Put the land premium per MW on every appraisal
3 · Fitted hallOf a c.£9m London hall the landlord's share is £0.5m to £1.3m; the lessee's is £4m to £9m before a chip. Racks went from 16 to 27 kW in a year and AI racks run 120 to 230 kW; liquid cooling makes the building matter less and the yard matter more. Regional operators are consolidating with fresh debtDefine our scope as ending at the intake switchgear, in plant terms, in a schedule to the lease. Design for the yard and the slab. Ask PUE and density first. Pitch the regional operators in their own numbers
4 · ComputeA megawatt of chips costs c.£26m and must earn it back in three to six years while the hourly price swings by a factor of four. Money follows the contract; loans fall due in 2026 to 2028 before contracts pay out. No neocloud bankruptcy yet, but Gartner expects most to lose independence by 2030. Nscale's own prospectus sets out the layer's risksUnderwrite the contract book, not the brand. Prefer tenants whose debt or customer is investment grade. Deposit or guarantee through the refinancing window. Write the re-let right for a chip-owner's exit
5 · Capacity saleFive buyers hold most of the take-or-pay value; the state is a real buyer in Britain. Marketplaces trade hours, not megawatts. Google backstops Fluidstack's leases for warrants; Nvidia guarantees $860m of Nscale's rent for $60m of warrants and rents back unused capacity. Europe has none of this and charges neoclouds more rent insteadAsk in the first meeting who stands behind the lease. Decide beforehand what we offer in return. Keep the rent unchanged and take the guarantee. A named off-taker is worth more than a well-known tenant
6 · Model, app and userHalf the country and a third of firms use AI; the labs have moved to London; the NHS, finance and government buy as if an onshore rule existed, and none does yet. From Kent, 59% of Britain's urban population is within 2 ms and 92% within 4 ms. Tokens got 600 times cheaper and volumes rose fasterSell the building as compute in Britain, with power, available this decade. Name latency only to the metro-latency tenants. Sovereignty and Kent's coastal position are features we can offer as landlord. Token deflation is the tenant's risk, not ours
7 · MoneyThe cost of money rises with every layer: 6% at the grid, 5 to 7% against rent, 6% to 16% for chips depending on whether a hyperscaler has signed. Property lenders lend on rent and re-let value; GPU lenders lend on contracts. Hyperscaler capex is c.$725bn in 2026 and heading for a trillionStay at the building's cost of capital. Size debt on rent only. Write the lease so a property lender can size debt on it. Ask bidders what their GPU debt costs. Watch for the first UK powered-shell securitisation
8 · PaperBilateral connection terms now survive a change of occupier and capacity cannot be cut without consent; data centres have no use class and get consented case by case; the market's yield-up strips the hall and ours keeps it; deposits of six to twelve months are typical for small tenants; the data duties belong to the tenantSeven rules: the connection stays with the building; planning per site before exchange; rent only, no revenue share; scope ends at the intake; yield-up leaves the hall; credit support in a schedule; power never on our books

9.3 · What we never doFive rules the evidence confirms

  1. We do not fund the kit. The hall costs £4m to £9m a megawatt and is bespoke to a cooling method that changes every two years; the chips cost £26m and halve in price. Every pound spent inside the intake borrows at a hall's or a chip's rate. Chapters 3, 4 and 7.
  2. No megawatt is quoted unless it is confirmed in writing. Nscale lost Microsoft at Loughton over a connection that was never confirmed. The reforms of 2025 and 2026 penalise exactly that. Chapter 1.
  3. Debt is sized on rent and nothing else. Revenue share is excluded by our rules and by every lender's. Chapter 7.
  4. Power does not pass through our books. The tenant's electricity bill is three times our rent. Chapter 8.
  5. We do not depend on one tenant type or one operator. The exits in the compute layer are mergers and asset sales; the lease must let the hall pass to the next operator. Chapters 4 and 8.

9.4 · The tenantThe target list, revised by the study

The list of 31 October stands, re-ordered on credit and with one addition. The first five remain the first five calls; only their order has changed.

RankWhoWhy, after the studyThe one question for them
1Nscale, with BTThe strongest demand in Britain and the clearest need for power this decade: $103bn of conditional contracts, a flagship site delayed to the 2030s, an anchor tenant lost in October. The Nvidia rent guarantee at its Texas site is the precedent we would ask for. Through the BT partnership it is the natural operator for the exchange channelWill Nvidia or Microsoft guarantee the rent on a UK site the way they did at Ward County?
2CivoStill the closest match in size and thesis: 40 sites at c.8 MW for sovereign inference, build-or-lease unstated. Second rather than first because its 1 GW programme has no disclosed financing; a backstop or a partner would move it back upWho funds the 40 sites, and will they stand behind a lease?
3Radiant (Ori)New to the top five. Brookfield's $10bn AI fund behind a UK operator, Nvidia in the fund, sovereign and enterprise contracts as the model. The kind of covenant chapters 4 and 7 point toWould Radiant take a UK shell rather than a Kao hall, and on what term?
4PulsantBuys sites of our size with a £187m facility; retrofitting for density; Antin behind it. The colocation route: better covenant, more re-lettable hall, lower rent appetiteWhat does a 10 MW shell at £750k a MW do to their hall economics?
5nLightenI Squared's $500m and an £85m private-credit facility secured on nine UK sites of 10 MW rising to 20 MW: a lender has already priced our asset class for themWould their lenders extend the ring-fence to a leased shell?
6LatosA 40-site model that needs sites; funding to be tested before a leaseWho are the investors?
7Nebius£1.7bn in Britain, hyperscaler contracts, but a fitted-hall habit at 22 MW+Is there a shell in the 65 MW?
8Gravity Edge (BlackRock)The closest strategy to ours, one layer up, with £500m. Partner or competitor; worth knowing whichWould they fit out a Yeats shell rather than buy a hall?
9TT GroupNot a tenant; the counterparty for 4,600 exchanges with power and fibre that it has so far sold for housingWhich exited exchanges hold more than 2 MVA?
10Microsoft, Google, the AIRR primeNot tenants; the credit behind them and the demand our tenants sell intoWhich neocloud carries your UK sovereign work, and would you stand behind its lease?

CoreWeave, Fluidstack, Lambda, Yondr, Ark and the London campus operators remain references, not targets, for the reasons in chapters 3 and 4.

9.5 · The askTen questions for every bidder, in order

#QuestionChapterWhy it decides
1Who is your end customer for this capacity, and will they, or your chipmaker, stand behind the lease?5Identifies the credit support behind the lease, which decides what debt the building carries
2What is your contracted value, your largest customer's share, and how much is conditional on delivery?4Nscale disclosed all three; we hold a private bidder to the same
3What does your GPU debt cost, and who lent it?7SOFR plus 2.25% has a hyperscaler behind it; plus 5.50% does not
4What density and cooling do you run, and what do you need at the intake?3Fixes where our scope ends; liquid cooling changes nothing outside the intake
5What PUE do you design to?3Decides how much IT load our megawatt carries, and what our rent is worth to them per kW
6When must the power be energised, and what does a six-month delay cost you?1Tests the premium on a connection in hand
7Whole 10 MW or phased, and at what binding minimum?8Phasing shifts vacancy to us unless the dates bind
8How many UK sites in three years, and who finds them?2Turns a letting into a pipeline
9What leaves with you at the end, and what stays?8Our yield-up keeps the hall in place; raise it early
10Who else have you leased from, and may we speak to them?4Conduct and covenant

9.6 · What we giveThe decision to take before the first meeting

The American landlords paid for their backstops in warrants. We have no listed equity. Three options remain, and we recommend trying them in this order.

  1. Nothing but the power. Where the operator needs a connected building this decade, the building itself is the consideration. Nscale's position after Loughton suggests we try this first.
  2. A right of first offer on the next cluster. Costs us nothing today, ties the tenant to our pipeline, and gives the regional operators and the neoclouds what both say they want, which is more sites.
  3. A share of exit value above a hurdle, on that site only. The nearest sterling equivalent to a warrant. A lender can accept it because it ranks below the debt. Not a share of rent, and not revenue share.

9.7 · The next ninety days

  1. Two DNO confirmations in writing. For each seed site: agreed supply, point of supply, firm, and confirmation that the bilateral terms endure on a change of occupier and that capacity will not be reduced without the customer's consent. Chapters 1 and 8.
  2. Planning per site. A pre-application view or a lawful development certificate on the compute use, a noise screen for residential neighbours, and the EPC position. Chapter 8.
  3. The one-page pack. The building, the MW with its evidence label, the programme, the lease heads of chapter 8, the conversion from grid MW to IT kW, the sovereignty wording, and for the metro-latency tenants only, the latency rings. Chapters 3, 6, 8.
  4. The decision in 9.6, taken and written down.
  5. Five calls in one week: Nscale, Civo, Radiant, Pulsant, nLighten, with the ten questions. Chapter 9.
  6. One agent retained on the cluster, two sounded. Chapter 0.
  7. TT Group: open the exchange conversation with a list of exited buildings screened on power.yeats.com. Chapter 2.
  8. Two lenders sounded on the lease heads, before a tenant is chosen, so the heads are drafted to their requirements. Chapter 7.
  9. A watch list, reviewed monthly: Ofgem's Curate decision (due by the end of 2026); the DCP463 working group on unidentified-customer capacity; the distribution-level prioritisation process the government has promised; the heat network zoning regulations; the Ark sale; the AIRR cloud-compute award; CoreWeave's cost of capital; and the first UK powered-shell securitisation.

9.8 · What we still do not know

Each of these needs a conversation rather than further desk research.

9.9 · Sources

Chapters 0 to 8 of this study, each with its own source list; the operator and broker target list of 31 October 2026; the Edge method and its lease checklist.

Appendix A

Appendix A · The cards

One card per player. Eight deep cards cover the study's eight questions; the rest are short. UK only, with the American and European names that explain a structure. Facts as published to 31 October 2026, sterling in brackets at £1 = $1.33.

In shortEvery name the chapters mention, one card each.
8
deep cards
40+
short cards
6
layers
0
approached

Basis. Market study, no returns. Ownership and figures are from company announcements, filings and trade press cited in the chapters; where a fact could not be confirmed the card says so. Nobody on these cards has been approached.

A.1 · The deep eight

UK Power Networks · layer 0

What it isThe distribution network operator for London, the South East and the East of England: three of the fourteen licences, c.8.3m homes and businesses
What it is, as a companyOwned by Engie since 7 May 2026, bought from CK Infrastructure, Power Assets and CK Asset at a £10.5bn equity value, a premium of c.50% to the regulated asset base
What it doesConnects, reinforces and operates the network under Ofgem's RIIO-ED2 price control (to March 2028) and the ED3 methodology now being set
Who runs itEngie, an energy group rather than a financial holder; a director has said data centres on its network draw only 30 to 40% of their agreed capacity
How it makes moneyAllowed revenue on the asset base; ED3 early view 6.08% real cost of equity at 60% gearing; reinforcement for demand funded by the DNO and recovered from all users
Why now125 GW of demand offers in seven months; new 5 MVA application rules from 1 June 2026; Ofgem's Curate, Plan and Connect reforms
What it means for usOur DNO holds 251 of the 1,029 primaries with 10 MW spare and 178 of the 536 that hold to 2030. Its written confirmation of spare capacity is the first gate. Chapter 1

Segro · layer 1

What it isFTSE 100 industrial REIT; owner of the Slough Trading Estate, Europe's largest data centre hub
What it holdsA power bank of 3.0 GVA across European availability zones (July 2026), 1.4 GVA of it to lease within seven years
What it doesPivoting from powered shells to fully fitted halls in joint ventures with Pure DC: Park Royal (56 MW IT, c.£1bn, 70 MVA, ready 2029) and Paris. Still signs shells where asked: Slough, 50 MVA, pre-let March 2026 with the customer contracting power directly
Who runs itA listed board; development capex guided at £450m to £550m for 2026
How it makes moneyRent and development profit; publishes a 9 to 10% net yield on cost for the fitted scheme
Why nowHyperscaler and neocloud demand; its own land with power
What it means for usThe reference landlord; moving up the stack and starting at 50 MVA. Its Slough structure (landlord holds the connection, tenant contracts the power) is the one we would use. Chapter 2

Kao Data · layer 2

What it isUK campus operator; Harlow, Stockport (40 MW consented), Manchester (£350m, due 2026)
What it is, as a companyInfratil 53%, Legal & General Capital 32%, Goldacre NOÉ 15% (2023 split)
What it doesBuilds and operates fitted halls; the landlord of choice for neoclouds in Britain: Nebius (22 MW, ten years), Ori, Civo
Who runs itInfrastructure owners; chaired from Goldacre
How it makes money£ per kW a month on fitted capacity
Why nowNeocloud take-up of European capacity rose from 133 MW to 414 MW in a year
What it means for usWill not lease a Kent shell; knows every tenant on our list and what they pay. Chapter 3

Pulsant · layer 2

What it isRegional edge operator, 14 UK sites (platformEDGE)
What it is, as a companyAntin Infrastructure Partners since 2021; revenue c.£126m and EBITDA c.£24m per a data vendor, year unstated; £187m five-year facilities refreshed October 2025
What it doesColocation to enterprises and the public sector; bought two SCC sites (Birmingham c.2 MW, Fareham c.3 MW) in 2025; 1.2 MW AI-ready hall at Milton Keynes and £1m into Birmingham for inference in 2026
Who runs itInfrastructure-fund ownership; customer racks up from c.4 kW to 10 to 20 kW
How it makes moneyRetail and wholesale colocation; small AI-ready increments
Why nowDensity is forcing refits; fresh debt for acquisitions
What it means for usBuys sites of our size; the colocation route to a better covenant. Fourth call. Chapters 3 and 9

Nscale · layer 3

What it isUK neocloud founded 2024; Nvidia holds over 5%; S-1 filed 18 September 2026 for a NYSE listing
What it is, as a companyH1 2026 revenue $140.6m (c.£106m), net loss $1.02bn (c.£770m, $457m of it currency); $103.4bn of active and contracted value over c.461,000 GPUs; Microsoft up to $43.8bn and Anthropic up to $44.6bn, conditional on delivery; largest customer 52% of revenue; "has not yet obtained binding commitments for the financing" those contracts need
What it doesOwns and operates AI data centres; Loughton (50 to 90 MW) grid-delayed to the 2030s and lost Microsoft as anchor on 18 October 2026; three BT sites, 14 MW; Stargate UK with OpenAI; US site at Ward County, Texas, with a $860m Nvidia rent guarantee
Who runs itA founder-led team with Nvidia, Microsoft and OpenAI relationships; c.£1.5bn Series C at c.£11bn
How it makes moneyTake-or-pay contracts with hyperscalers and labs; sovereign pitch via BT
Why nowContracts far ahead of financed, powered capacity
What it means for usFirst call. It needs power this decade, and in Texas its chipmaker has guaranteed its rent. Chapters 4, 5 and 9

Civo · layer 3

What it isStevenage cloud provider founded 2015; hosted at Kao today
What it is, as a companyFounder-led; THG took a minority stake (c.£1.4m) in 2021; no venture round or project financing found
What it does40 UK edge sites planned at c.8 MW each for sovereign inference, c.1 GW combined; first site Hertfordshire (8 MW rising to 38); five more sites of 150 MW secured in Lancashire, Greater Manchester, London and Oxfordshire; Vera Rubin-ready, liquid cooled; build-or-lease not stated
Who runs itIts founders
How it makes moneyCloud and GPU services sold on UK-owned, UK-incorporated sovereignty
Why now"Inference at the edge rather than training overseas"
What it means for usClosest to us in size and thesis; the weakest public balance sheet on the list. Second call, moving to first if a backstop or partner appears. Chapters 4 and 9

Nebius · layer 3

What it isAmsterdam-headquartered, Nasdaq-listed neocloud
What it is, as a companyMicrosoft ($17.4bn to $19.4bn, New Jersey) and Meta (c.$27bn) contracts; borrows at SOFR plus 2.50%
What it does£1.7bn UK programme (8 June 2026): 22 MW at Kao Harlow on ten years hosting its cloud and the Token Factory inference service; three UK clusters reported at 65 MW by 2027; also at Ark Longcross
Who runs itA listed board; a Lepton partner
How it makes moneyTake-or-pay and on-demand GPU capacity; inference by the token
Why nowUK sovereignty demand and the government's action plan
What it means for usBest-funded fitted-hall tenant in Britain; takes halls, not shells. Second pass. Chapters 4 and 9

Microsoft UK · layer 4

What it isThe largest buyer of neocloud capacity in the world and the credit behind Nscale, Nebius, IREN and Lambda
What it is, as a companyc.$60bn (c.£45bn) of neocloud contracts booked as operating cost; 2026 capex guided at c.$190bn
What it does in BritainOwn regions; a supercomputer building with Nscale in its UK plans; left Nscale's Loughton site on 18 October 2026 for want of power while remaining Nscale's largest customer; designated a critical third party to UK finance from 13 July 2026
Who runs itn/a
How it makes moneyCloud, software, advertising; AI capacity is a use of funds
Why nowCapacity scarcity; it buys from anyone who can energise
What it means for usNot a 10 MW tenant. The credit support to ask for behind one. Chapters 5 and 9

A.2 · The cards, by layer

Layer 0 · Grid

WhoWhatRead for us
NESONational Energy System Operator, public since October 2024; runs the transmission queue; 96 GW of demand at June 2025; 11 to 13 GW connectable before 2030; to be directed by government on strategic demandNot our counterparty at 10 MW unless the grid supply point binds
National Grid Electricity DistributionMidlands, South Wales, South West; c.8m customers; National Grid plc since 2021 (£7.8bn)Most industrial floorspace; no 2030 forecast in its published data
SSEN DistributionSouthern England and North Scotland; SSE plc; c.3.1m southern customersBorders UKPN's South East; no 2030 forecast
Northern PowergridNorth East and Yorkshire; Berkshire Hathaway Energy; 3.9m customersYorkshire second for primaries with 10 MW spare
SP Energy NetworksCentral Scotland and Merseyside, Cheshire, North Wales; Iberdrola; c.3.5m customers (Indicated)Most spare capacity in Britain, least demand near it
Electricity North WestNorth West; Iberdrola 88% since 2025 (£2.1bn), Kansai-led 12%; c.2.4m connectionsSame owner as SPEN
OfgemRegulator; ED3 methodology decided 21 May 2026; Curate consultation closed 16 September 2026 with a decision due by year endIts 40 MW fee threshold sits above our size

Layer 1 · Powered site

WhoWhatRead for us
Tritax Big BoxManor Farm, Heathrow: 74 acres for an initial £70m plus 21% of phase-one profit; 107 MW (147 with phase two) consented after judicial review; powered shell subject to pre-let; 50% joint venture with an unnamed generator for two substation connectionsWhat a listed landlord pays for powered land and needs before it builds
Harworth GroupPure-play powered land; Skelton Grange, Leeds, two plots to Microsoft for £106m; c.0.8 GW of further connections; up to six hyperscale sites; second-site exclusivity August 2026The purest powered-land seller; buyers are hyperscalers
TT Group (Telereal Trillium)Bought c.6,700 BT properties in 2001 for £2.38bn; owns nearly all c.5,600 Openreach exchanges, c.4,600 closing from 2025 into the early 2030s; main lease to 2031; exited buildings sold for housing; pilot exits slipped to November 2026The exchange counterparty; open the conversation on exchanges with real MVA
BT Group and OpenreachLeaves 4,600 exchanges, keeps c.1,000; Nscale partner on three sites, 14 MW; AI-RAN trials on EE's live network in BirminghamA FTSE counterparty on any exchange site
Stellanor (DWS)Eight Redcentric data centres, EV up to £127m, completed May 2026; £3.1m to £5.5m per MW derivedA UK price for small sites with power
The US minersTeraWulf, Cipher, Applied Digital, Core Scientific: powered sites leased turnkey to neoclouds at c.$1.5m to $2.3m per MW a year, fit-out $8m to $10m per MW, Google backstops behind FluidstackPrecedent, not UK fact
Cogent and I SquaredConverted Sprint switch sites asked at $10m to $17m per MW; ten sold to I Squared for $225m, $4.25m per MW, for an inference platformUS precedent for exchange conversion, four years ahead of the UK

Layer 2 · Fitted hall

WhoWhatRead for us
Ark Data CentresElliott-owned; TPG reported in talks at c.$5bn (c.£3.8bn), late October 2026; 27 facilities; Crown Hosting joint venture with the Cabinet Office; £807m Longcross expansion for NebiusThe public-sector channel; a sale would set a new price for UK halls
nLightenI Squared's European edge platform with more than $500m committed; owns Proximity (ten UK sites); £100m UK programme; £85m Rivage-led facility secured on nine sites of 10 MW rising to 20 MW; Bristol refitFifth call; a lender has priced our asset class for them
Latos Data CentresFounder-led; Cardiff, three buildings, 90 MVA, under construction; Stockton £100m approved; 40 sites by 2030; investors not disclosedSixth; funding to be tested
Datum DatacentresFarnborough and Manchester; 1 MW halls; ownership not confirmed onlineToo small alone
YondrSlough 100 MW campus; £532m green securitisation rated AA, March 2026Shows the bond market lends on let halls
VirtusST Telemedia with Macquarie at 40%; 18 UK sites, 300 MW+; £2.45bn from thirteen banks, September 2026Largest UK operator; builds its own
Green MountainAzrieli; LON-East, Romford; a neocloud took 14 MW in September 2026Demand proof at our size
Gravity EdgeBlackRock and DGP; Camberley to 20 MW; 5 to 20 MW sites with under-used capacity; £500m committedClosest strategy to ours, one layer up
Equinix, Digital Realty, Global Switch, Telehouse, VantageThe London campus operators; CoreWeave's UK landlords; Global Switch's owners have tried to sell since 2021; Vantage 223 MW in the UKReferences for turnkey rent, not tenants

Layer 3 · Compute

WhoWhatRead for us
Radiant (Ori)Brookfield's AI cloud unit, formed with UK neocloud Ori in February 2026 at a reported $1.3bn; part of a $10bn Brookfield fund with Nvidia among backers; Ori's first UK region at Kao; sovereign, enterprise and telecom contracts on Nvidia's DSX designThird call; the covenant quality the funding case needs
CoreWeave UKDocklands, Crawley, DataVita in Scotland; c.£2.5bn UK commitment; leases rather than builds; c.$50bn of debt, bonds above 16% in mid-October, $104bn backlog, Nvidia commitment to April 2032The bellwether; watch its cost of capital
FluidstackHeadquarters moved to New York, December 2025; left a €10bn French project; $750m at $7bn; Google-backstopped US leasesStructure reference only
Lambda$926m term loan rated Baa2 at SOFR plus 3.00%, September 2026; $1.5bn Nvidia lease-back; no UK site foundGPU debt going mainstream
DataVitaLanarkshire AI Growth Zone, up to 500 MW; $406m financing, August 2026; CoreWeave's Scottish hostThe Growth Zone model; too big and too far
Isambard-AI and the AIRR5,444 H100s at Bristol; twenty-fold expansion by 2030 under a £1bn roadmap; £500m Sovereign AI Unit; c.£250m cloud-compute contract tenderedDemand for our tenants, not a tenant

Layer 4 · Capacity sale

WhoWhatRead for us
Google£5bn UK programme; backstops Fluidstack's leases at TeraWulf ($1.8bn rising to $3.2bn), Cipher ($1.4bn) and a Texas joint venture ($1.3bn) for warrantsOriginator of the lease-backstop structure we want
OpenAI$22.4bn with CoreWeave in 2025; Stargate UK with Nscale, reported paused; first permanent London office for 544 staffUK plans depend on Nscale delivering power
AnthropicNscale up to $44.6bn conditional; CoreWeave multi-year; London office for c.800Same dependency
MetaCoreWeave $14.2bn plus a reported $21bn; Nebius c.$27bnSets the scale of one take-or-pay
NvidiaEquity in CoreWeave, Nebius, Nscale; rents back unused capacity from 1 July 2026; guarantees up to $860m of Nscale's rent at Ward County for $60m of warrantsThe chipmaker as guarantor
SF ComputeMarket for H100 and H200 clusters by the hour; $40m at $300m; c.10% fee; resale recovers c.25%Trades hours, not megawatts
Nvidia DGX Cloud LeptonMarketplace routing developers to partner clouds including Nscale, Nebius, Fluidstack, Scaleway, Mistral; no rate cardA channel our tenant's cluster can sell through
Vast.ai, ShadeformPeer-to-peer market at c.$2.13 an hour; aggregator across twenty clouds at no buyer feeThe price floor; the easiest way to buy hours
Together AI, Fireworks, BasetenInference platforms at c.$1bn of annual revenue each; rent capacity and sell tokensWholesale buyers of our tenant's hours
Crown Commercial Service, Crown Hosting, the AIRR prime, the MoDG-Cloud 15 live from 6 August 2026; Crown Hosting awards; a c.£250m research-compute prime; the MoD's £180m framework with an edge compute lotThe state as buyer; our tenants' route to it

Intermediaries and advisers

WhoRole
CBRE, JLLRetained-agent candidates on a cluster; CBRE writes the UK and European outlooks used throughout
Cushman & Wakefield, Knight Frank, Savills, Avison YoungMarket soundings; Savills' H1 2026 Spotlight and Knight Frank's rates note are cited
DC Byte, datacenterHawk, Structure Research, DCDWho is leasing what, where, at what MW
BCLP, Hogan Lovells, Gowling WLG, AshurstThe names on UK shell-and-core, lease and colocation guidance

From power to answer · bound edition · draft of 31 Oct 2026 · For discussion. Each chapter keeps its own source list.